🧱 CFC 250Cold water, hot water and recirculation distributionChapter 8 of 10 in the section

When the pressure won't rise: booster set, tank and floors served

This chapter details the method for properly supplying the upper floors without subjecting the lower part of the building to destructive overpressures. You will be able to calculate the dynamic pressure required according to SIA 385/1, size and adjust the setpoint of a variable-speed unit, correctly pre-charge the diaphragm tank and decouple the booster set to put a stop to the noise transmitted to the structure.

Key takeaways

  • Calculating the geometric head and the pressure losses guarantees a minimum pressure at the top floor.
  • Dividing the network into pressure zones prevents premature wear of the fittings on the lower floors.
  • Pre-charging the diaphragm tank to 0.3 bar below the setpoint prevents hammering.
  • Decoupling the unit with elastomer sleeves and anti-vibration mounts prevents noise transmission.

Sizing the minimum pressure at the highest point without crushing the lower floors

In renovation as in new construction, the dynamic pressure supplied by the municipal water utility fluctuates regularly between 2.5 and 4.0 bar at the main meter. In a multi-family residential building of four to six levels, this driving energy proves insufficient to supply the attic apartments during the morning peak hours. SIA 385/1 prescribes a guaranteed minimum flow pressure of 1.0 bar at the most disadvantaged tap, a value raised in workshop practice to 1.5 bar for the flawless operation of recent thermostatic mixers and overhead showers with large shower heads.

To determine the exact pressure setpoint at the outlet of the substation, the installer calculates the cumulative pressure-loss equation at the simultaneous peak flow: geometric height difference (0.10 bar per metre of riser), linear resistance of the stainless steel or multilayer pipes, local losses of the isolating valves, fine filters and the sub-meter of the top level. Boosting the entire riser indiscriminately to satisfy two apartments under the roof is a common technical error with heavy financial consequences.

Indicative distribution of static pressures in a ground-plus-five building without zoning
Level servedRelative geometric heightResulting dynamic pressureBehaviour of the installation
Penthouse (5th floor)+16.5 m1.6 barFittings operating correctly
3rd floor+9.9 m2.3 barOptimal standard operation
1st floor+3.3 m3.0 barComfortable service pressure
Ground floor0.0 m4.1 barModerate mechanical stress
Basement / laundry room-2.8 m5.2 barWear of valve seats, risk of water hammer

Setting the setpoint, pre-charging the tank and treating the vibrations of the unit

Modern units use vertical multistage centrifugal pumps regulated by an integrated electronic frequency converter. This device continuously adjusts the rotation speed of the hydraulic impellers to maintain a strictly stable pressure setpoint, whatever the instantaneous draw-off. The addition of a diaphragm accumulation tank remains indispensable to damp the night-time micro-draw-offs and prevent untimely cycling of the electric motors.

  1. Checking the gas pressure of the tankHydraulically isolate the sanitary expansion vessel using its dedicated isolating valve and drain the water contained on the fluid side. Measure the air or nitrogen pre-charge pressure on the Schrader valve with an accurate workshop pressure gauge.
  2. Adjusting the pre-charge relative to the setpointInflate or deflate the gas cushion to set its pressure between 0.2 bar and 0.5 bar below the start-up pressure or the setpoint of the converter. An over-inflated tank stores no useful volume; if under-inflated, the diaphragm slaps against the steel walls.
  3. Setting the stop delaySet the zero-flow detection on the control cabinet to stop the pump after a delay of twenty to thirty seconds of running at minimum speed once the draw-offs have closed.

The mechanical installation in the plant room requires rigorous acoustic care to meet the comfort criteria of the dwellings located on the ground floor. Art. 22 OLT 3 requires noise and vibrations to be combated by construction measures and technical provisions on the operating installations. The unit is anchored on a massive concrete base decoupled from the slab by elastomer mounts calibrated to the total loaded mass of the equipment.

Pressure zoning and floor pressure reducers: avoiding wear of the building

In a multi-family residential building of six to eight floors, the lack of pressure often affects only the attic and the top level. If the public network supplies an inlet pressure fluctuating between 2.8 and 3.2 bar in the basement, the water reaches the top with barely 0.8 bar static after overcoming the 22 metres of height difference. The frequent temptation on site is to install a centralised booster set and set it to 6.5 bar to guarantee a vigorous jet at the last shower head. This simplistic approach solves the comfort of two apartments while prematurely degrading the fittings, hoses and appliances of the lower floors.

The SVGW directive W3 and SIA 385/1 set a minimum dynamic pressure of 1.0 to 1.5 bar at the most disadvantaged draw-off point, while limiting the static pressure at the appliances to a maximum of 5.0 bar. Subjecting the ground-floor and first-floor apartments to a constant 6.5 bar causes violent water hammer each time a washing machine's solenoid valve closes, accelerates the failure of the ceramic cartridges of the mixers and forces continuous dripping from the sanitary safety valves.

Theoretical pressure distribution by floor height for a booster setpoint of 5.5 bar in the basement
Level servedGeometric heightGross static pressurePrescribed corrective measure
Ground floor0.0 m5.5 barMandatory installation of a floor pressure reducer set to 3.5 bar
2nd floor6.0 m4.9 barPressure tolerated without reducer, wear threshold limit
4th floor12.0 m4.3 barOptimal direct distribution, acoustic comfort under control
6th floor18.0 m3.7 barBalanced direct distribution in hot and cold water
Attic24.0 m3.1 barFinal dynamic pressure of 1.8 bar at the most disadvantaged draw-off point

To reconcile the protection of the lower installations with the supply of the upper floors, two technical configurations are available to the sanitary installer. The first consists of creating a riser dedicated solely to the top boosted levels, leaving the first floors connected directly to the natural pressure of the water utility. The second configuration, common in refurbishment when replacing the risers is impossible, keeps a single riser but incorporates individual floor pressure reducers on each floor branch exposed to more than 4.5 bar.

Control setting, vessel charge and acoustic decoupling

The control of a modern booster set is based on variable-speed pumps driven by a frequency converter. Unlike the old units operating on-off with a mechanical pressure switch, speed modulation continuously adapts the motor speed to the flow drawn in order to maintain a strictly constant pressure setpoint. This principle eliminates pressure surges in the risers and limits the mechanical stress on multilayer or stainless steel pipes.

  1. Determining the setpoint pressureCalculate the required pressure by adding the static height up to the highest point (1 bar per 10 m), the linear and local pressure losses at peak flow (allow 0.8 to 1.2 bar) and the residual dynamic pressure required by the terminal fittings (at least 1.5 bar).
  2. Adjusting the pre-charge of the diaphragm tankHydraulically isolate the buffer tank and drain its volume of water. Measure the pressure of the nitrogen bladder with the pressure gauge. Adjust the gas pressure to a value equivalent to 70% or 80% of the regulated setpoint pressure, i.e. 0.2 to 0.5 bar below the minimum switch-on pressure.
  3. Checking the zero-flow stop thresholdCheck the automatic cut-out of the pumps when the draw-offs are fully closed. The converter must detect zero flow, slightly raise the pressure to charge the tank, then stop the motor without generating a transient overpressure.

The hydraulic connection also requires a total acoustic break. The installer must fit reinforced elastomer anti-vibration compensating sleeves on the suction and on the discharge, mounted in the axis of the pipe stubs without mechanical twisting. The fixing clamps of the manifolds and of the first metres of the riser must have an insulating EPDM rubber lining, supplemented by flexible sleeves at the slab penetrations to prevent any transmission of vibrational energy to the walls of the building.

Diagnosing hydraulic faults and acoustic remediation

When tenants report continuous whistling from the pipework or sharp slamming when the mixers are closed, the problem often stems from a clear mismatch between the booster set and the topography of the building. An overall supply pressure raised to supply two attic apartments imposes destructive static stresses on the lower dwellings, easily exceeding six bar during off-peak hours. The first intervention on the construction site requires fitting check pressure gauges at the high and low points during periods of heavy draw-off. This measure isolates the real pressure losses and avoids adjusting the variable-speed drive on erroneous assumptions.

Intervention protocol for hydraulic and vibration faults
Observed symptomMechanical or hydraulic originImmediate corrective measure
Slamming at start-up and untimely pumpingExpansion vessel deflated, punctured or diaphragm flattenedIsolate the tank from the network, drain the residual water chamber and re-inflate the bladder to the prescribed value.
Shrill whistling and leaks on the lower floorsExcessive static overpressure on the fittingsInstall floor pressure regulators set to four bar at the start of the landing branches.
Dull humming audible in the apartmentsDirect sound bridge between base and load-bearing structureFit flexible compensating sleeves and insert resilient linings in all clamps.

The propagation of impact and rotation noise requires a review of all the physical connections with the structure. The booster set must rest on a heavy concrete base, completely decoupled from the raft slab by resilient mounts calculated for the rotation speed of the pumps. The hydraulic connection requires the fitting of flexible axial anti-vibration sleeves on the discharge and on the suction, preventing metallic vibration from passing into the risers. Floor and partition penetrations must include sound-insulating sleeves to meet the criteria of SIA 181 on noise from technical equipment. On collective distribution installations compliant with SIA 385/1, checking the circulators and thermal regulators often resolves the top-floor complaints without any need to apply a hydraulic overpressure that is dangerous for the equipment.

Frequently asked questions

How do you check precisely the air charge of a pressure tank?

To measure the pre-charge pressure of a sanitary tank, you must isolate the vessel from the water network and then open its dedicated drain. Checking the pressure with the pneumatic pressure gauge on a bladder still under hydraulic load gives a false value, equal to the network pressure. If the measured air pressure is below the required setpoint, re-inflate with nitrogen or dry air before reopening the valves.

Why install floor pressure reducers after fitting a booster set?

The unit raises the overall pressure to provide at least one dynamic bar at the highest level of the building. This load adds to the weight of the water column in the lower floors, where the static pressure frequently exceeds six to seven bar. Installing pressure regulators set to four bar protects the mixer cartridges, limits accelerated scaling and eliminates violent flow noise in the intermediate and lower dwellings.

What is the minimum pressure value required at the highest draw-off point?

According to SIA 385/1, the dynamic flow pressure available at the most disadvantaged tap must be at least one bar at the simultaneous design flow. A lower value causes malfunctions in thermostatic mixers and abnormally prolongs the hot water waiting time. If the public network does not guarantee this residual pressure after deducting the geometric and linear pressure losses, installing a booster set becomes indispensable.

How do you eliminate the dull humming generated by a booster set on the floors?

This fault comes from structure-borne transmission through the floor or the pipework. Check that the frame rests on flexible anti-vibration mounts not clamped by rigid screws to the floor. Elastomer sleeves must be fitted immediately on the suction and discharge of the unit. Finally, all the fixing clamps of the rising water pipes must be fitted with insulating elastomer strips to meet the strict requirements of SIA 181.

Texts and standards cited

  • norme SIA 385/1Domestic hot water installations in buildings - Calculation bases and requirements