Key takeaways
- The pressure test is always carried out on fully visible pipes, before any screed is poured.
- The SSIGE guidelines require specific thermal equalisation holds, adapted to metal or multilayer pipes.
- No pressure drop is tolerated on the pressure gauge during the final inspection phase.
- The jointly signed test report certifies that the installation is compliant, vis-à-vis the site management.
Carrying out the hydraulic test methodically according to SSIGE directive W3
The leak-tightness test certifies the mechanical strength of the joints and the complete absence of leaks in the drinking-water network. According to SSIGE directive W3, this operation is carried out with filtered drinking water or with oil-free compressed air where hygiene requirements rule out prolonged stagnation before commissioning. On ordinary building construction sites, the hydraulic test remains the reference procedure. It requires all draw-off points to be closed with threaded metal plugs fitted with new flat seals; the use of service taps or temporary plastic protective plugs is prohibited at test pressure. Pressure reducers, safety valves and backflow preventers must be isolated or replaced by temporary spacer pieces.
- Filling and complete air purgingFill the installation from the lowest point to the highest point. Open each vent and terminal tap in turn until a continuous jet with no gas emulsion is obtained. Residual air pockets compromise the pressure stability and falsify the test.
- Relaxation and thermal equalisation holdBring the network to preliminary pressure with the test pump. On multilayer or cross-linked polyethylene pipes, the material undergoes viscoelastic expansion under load. Allow a rest period of at least 30 minutes to stabilise the mechanical deformation of the polymer and balance the temperature between the injected water and the ambient air.
- Raising to test pressurePump until the pressure prescribed by SSIGE directive W3 is reached, i.e. at least 1.5 times the maximum permitted service pressure, with a usual minimum threshold of 10 bar on internal distribution systems. Readjust the pressure if the creep of synthetic materials has caused a drop during the first ten minutes.
- Main inspection phaseMaintain the test pressure for the regulatory observation time, set at 120 minutes for installations including synthetic pipes, or 30 minutes for rigid metal networks assembled by crimping.
The jointly signed test report before the works are closed up
The leak-tightness test only has evidential value if it is carried out before any pipes are concealed. No embedding in floor screed, no concrete pouring and no lining of a lightweight partition may take place before the formal validation of the test. The plumbing installer must visually inspect every fitting, branch, press-fit sleeve and socket while the network is at maximum pressure. A successful inspection guarantees the integrity of the work at the precise moment when the finishing work begins.
| Item | Required technical data | Purpose of the check |
|---|---|---|
| Identification of the section | Floors, rooms, risers, type of pipes and fittings | Define precisely the pipes tested |
| Test parameters | Pressure applied (bar), duration (min), fluid used | Demonstrate compliance with the SSIGE guidelines |
| Ambient conditions | Water temperature, ambient air temperature | Justify the absence of a thermal artefact on the pressure gauge |
| Measuring equipment | Pressure gauge serial number, accuracy class, calibration date | Ensure the metrological reliability of the readings |
| Result and signature | Initial and final pressures, visual findings, signatures | Record the absence of leaks and close the inspection |
Under art. 367 CO, the client examines the condition of the work as soon as is practicable after delivery and notifies the contractor of any defects. The test report, drawn up on the official SSIGE form or an equivalent company document, must be initialled by the plumbing team leader and countersigned on site by the site management or the client's representative. This joint step fixes the condition of the pipes on a certain date. In accordance with the principles of art. 370 CO, acceptance of the work releases the contractor from defects that were recognisable during the regular inspection. If another trade later pierces a concealed pipe with a rail fixing or a screed perforation, this signed document removes the presumption of fault against the installer.
Test parameters according to materials and pressure stabilisation
A successful leak-tightness test is not simply a matter of pressurising a section to see that there is no visible leak. According to the guidelines of the Swiss Association of Gas and Water Industry, the test procedure requires a calibrated pressure, complete degassing of the pipe and a strict thermal waiting period. Internal distribution networks today combine rigid metal pipes in stainless steel or copper and flexible pipes in synthetic materials such as cross-linked polyethylene or multilayer. These pipe families react in diametrically opposite ways under mechanical stress.
On synthetic pipes, raising the pressure causes a physical phenomenon of temporary lengthening and radial expansion. If the tester applies the test pressure without a prior stabilisation phase, the pressure gauge records a constant pressure drop that mimics a micro-leak on a press-fit or push-fit connection. The SSIGE guidelines therefore provide, for these networks, a preliminary loading phase intended to absorb the mechanical creep of the material, followed by a rapid release and then the main test phase proper.
| Pipe material | Test pressure | Stabilisation time | Inspection time | Permitted pressure drop |
|---|---|---|---|---|
| Rigid metal (stainless steel, copper) | 1.5 times the service pressure (min. 11 bar) | 15 minutes (temperature equalisation) | 30 minutes | 0 bar (no measurable variation apart from thermal drift) |
| Plastic and multilayer (preliminary test) | 1.5 times the service pressure (min. 11 bar) | 30 minutes of loading with readjustment | 30 minutes | Gradual drop tolerated during elastic expansion |
| Plastic and multilayer (main test) | Residual pressure after partial decompression | Controlled release of the pipe | 120 minutes | 0 bar (the pressure must remain strictly constant) |
| Preliminary test with dry air or inert gas | 150 mbar (low-pressure leak-tightness) | 15 minutes | 120 minutes (for volumes up to 100 litres) | 0 bar (visual check of the fittings with foaming agent) |
The hydrostatic test requires the pipework to be completely filled with filtered drinking water, meticulously purged at the highest point of each riser. The presence of a residual air pocket falsifies the measurement entirely: as the air is compressed by the thrust of the manual or electric test pump, it dampens the volume variations and masks seepage at defective press-fit joints. Moreover, a fitting failure under compressed-air pressure releases stored energy and violently throws the fitting or pipe, creating a major danger for personnel on site.
Classification of the defect, jointly signed test report and enforceability
The pressure drop observed during the main test is an absolute technical finding: no pressure-loss tolerance is granted during the final inspection phase. Once thermal equalisation between the make-up water and the ambient air of the building has been reached, the curve of the precision glycerine-filled calibrated pressure gauge must be a perfectly horizontal line. A decrease of 0.1 bar within a few minutes indicates an immediate leak-tightness defect that must be located before any other step.
The test must necessarily be carried out before the pipes are made inaccessible by the pouring of floating screeds, embedding in masonry chases or the closing of technical shafts with plasterboard. Draw-off fittings, fragile sanitary appliances, water heaters and safety valves set at 6 bar must be disconnected and isolated with sealed metal test plugs, otherwise the control components may be damaged or the test biased by a valve opening.
- Isolating and purging the networkIsolate the main distribution, close the floor isolating valves, block the plumbing stub-outs with threaded test plugs fitted with new seals and purge all the air at the high point.
- Pressurising and equalisingApply the prescribed pressure with the test pump equipped with a fine-scale pressure gauge (class 1.0 or 1.6), and wait for thermal equalisation between the injected water and the unfinished room.
- Visual walk-through of the distributionVisually inspect all the sockets, press-fit joints, threaded fittings, distribution manifolds and sound-insulating fixings while the network is held at test pressure.
- Finding and joint signatureRead the pressure gauge value at the end of the regulatory time together with the site management, fill in the official form and have both parties sign on the spot.
The leak-tightness test report, jointly signed by the plumbing installer and the representative of the site management, is the only supporting document certifying the compliance of the work at the time it is covered. This document expressly states the date, the precise start and end times, the fluid used, the pressure applied, the ambient temperature recorded and the exact identification of the flats, risers or technical rooms inspected. In the absence of this formal signature, any water damage occurring during the finishing work will engage the liability of the plumbing installer, who will be unable to prove the soundness and intrinsic leak-tightness of his pipework at the time the floor layer or plasterer took over the premises.
Handling non-conformities, repeat tests and enforceability of the finding
When the pressure gauge records a pressure drop greater than the value permitted by the SSIGE guidelines, the installation is declared non-compliant. No part of the work may be concealed, embedded or encased. The plumbing team leader must immediately stop the work of plasterers or screeders in the area concerned in order to preserve direct access to the networks.
- Methodical isolation of sectionsTo locate the fault without depressurising the whole network, the fitter isolates the risers and floor distributions using isolating valves or temporary test plugs. This sectioning narrows the search to a defined section.
- Visual inspection of the joints and purgingThe installer inspects every socket, thread and press-fit joint. Fittings left uncrimped by oversight are the most frequent source of an outright leak. He also checks for the complete absence of residual air pockets at the high points, whose compressibility falsifies the pressure reading.
- Replacing defective componentsAny leaking component or deformed fitting must be removed and replaced according to the manufacturer's instructions. No makeshift sealing, excessive tightening on a tapered thread or tampering with a crimp ring is tolerated on the drinking-water distribution network.
- Full restart of the test cycleOnce the repair has been made, the leak-tightness test does not resume where it stopped: the complete procedure is reset from the beginning, including the thermal stabilisation phase and the prescribed pressure hold.
The final test report records the compliant results obtained after correction. Completed jointly on the SSIGE directive W3 form, it bears the signature of the plumbing manager and that of the site management. According to standard SIA 118, this signed document is the only supporting document releasing the pouring of the screed and the closing of the technical shafts, formally discharging the installer from any damage prior to the fitting of the linings.
Frequently asked questions
Why is it forbidden to pour the screed before the test report has been signed?
The joint signature of the test report certifies the perfect leak-tightness of the exposed pipework. If the screed is poured before the test or before signature, any later trace of moisture will be attributed to the plumbing installer. He would then have to bear the demolition of the floor and its complete reinstatement at his own expense, having failed to prove jointly the compliance of his network before it was buried in the structure.
How do you tell a real leak from a pressure drop due to temperature?
Cold water introduced into a heated building warms up and rises in pressure, whereas lukewarm water introduced in winter cools down and loses pressure without any leak. To isolate this physical phenomenon, a sufficient rest period must be observed to reach thermal equilibrium with the surroundings. If the pressure gauge keeps falling steadily after this stabilisation phase, the water loss is real.
What should be done if the site management refuses to sign the test report after a successful test?
The installer immediately records the values read, the exact time and the refusal to sign in the site diary. He sends the report in writing without delay with a formal notice, inviting the site management to attend a repeat test within 24 hours. After this period and without a substantiated objection, proof of compliance is deemed established and bars any claim for an initial leak-tightness defect.
Can the leak-tightness test be carried out with compressed air rather than drinking water?
SSIGE directive W3 permits the test with oil-free compressed air or inert gas for hygiene reasons, in particular in winter to avoid frost or on long construction sites to prevent bacterial growth in stagnant water. The test pressures and durations differ from the hydraulic test. A high-precision pressure gauge suited to gases is then mandatory to detect the slightest leak.
Texts and standards cited
- directive SSIGE W3Guidelines for drinking-water installations, principles of testing and commissioning
- norme SIA 118General conditions for the execution of construction works, inspection and acceptance of works