Key takeaways
- SIA 385/1 sets precise waiting-time requirements according to the comfort level.
- The maximum stagnant volume tolerated in a non-circulated terminal branch must not exceed three litres.
- A circulation loop is required as soon as the geometric distance between the distribution and the draw-off point creates stagnation.
- The domestic circulation pump must maintain a minimum temperature of fifty degrees along the entire route.
Calculating the stagnant volume and complying with the limits of SIA 385/1
The time it takes for usable hot water to arrive is the main complaint from users when they move in. SIA 385/1 addresses this issue by linking the comfort of use to the volume of water contained in the individual connection pipework. When a user opens a mixer tap, the cooled water in the terminal pipe must first be flushed out before water at a temperature of at least fifty degrees reaches the draw-off point.
- Domestic dead leg
- Section of pipework located between the main pipe kept at temperature (riser or circulation loop) and the terminal fitting, in which the water stagnates and cools between two draw-offs.
To avoid excessive waste of drinking water and to guarantee a wait of less than ten seconds at nominal flow, SIA 385/1 applies a fundamental rule: the volume of water contained in a floor-level pipe without temperature maintenance must not exceed three litres for an ordinary draw-off point, and drops to one litre for a higher comfort level. Exceeding these thresholds without installing active circulation or self-regulating heating tape directly exposes the installer to the sanctions of the Code of Obligations (CO) regarding defects in the work.
| Nominal diameter (DN) | Mean internal diameter (mm) | Volume per metre (l/m) | Maximum length for 3 litres (m) |
|---|---|---|---|
| DN 12 | 12.0 | 0.113 | 26.5 |
| DN 15 | 16.0 | 0.201 | 14.9 |
| DN 20 | 20.0 | 0.314 | 9.5 |
| DN 25 | 26.0 | 0.531 | 5.6 |
| DN 32 | 32.0 | 0.804 | 3.7 |
When the client reports an excessive waiting time, art. 367 CO requires a check upon delivery of the work. If the volume measured on the test bench confirms that the limits prescribed by SIA 385/1 have been exceeded without an explicit derogation agreement, the network is deemed defective under art. 368 CO, obliging the installer to carry out extensive remedial work to correct the terminal distribution pipes.
Deploying the circulation loop network and setting the domestic circulation pump
As soon as the building's layout places the water points far from the distribution risers, a hydraulic circulation loop becomes mandatory. It consists of circulating a flow of domestic hot water, continuously or on a programmed intermittent basis, from the boiler room to the foot of the floor manifolds, then back to the water heater. This closed circuit guarantees water at temperature immediately at each apartment branch or bank of appliances.
- Positioning the branches as close as possible to the appliancesBring the circulation pipe to within five metres of the most demanding water points, such as the shower or bathtub, by routing the loop directly through the landing service duct.
- Installing the dedicated domestic circulation pumpFit a circulator approved for drinking water, with a bronze or stainless steel body, to rule out any risk of corrosion and ferrous contamination of the drinking water network.
- Fitting the adjustment and safety devicesAlways fit a non-return valve on the circulator discharge to block backflow of cold water during draw-offs, as well as thermal balancing valves on each return branch.
- Calibrating the flow and temperature settingsSet the circulator speed to ensure a flow velocity of between 0.2 and 0.5 m/s in the return pipe, avoiding velocities that are too low, which promote deposits, and erosion by cavitation.
Hydraulic balancing of the circulation risers is the keystone of the installation. Without thermostatically controlled balancing valves at the foot of each riser, the fluid takes the shortest loop to the detriment of the upper floors. Thermostatic circulation valves modulate their opening according to the local return temperature, thus ensuring that hot water supplies each branch with rigorous uniformity.
Waiting time at the tap and actual drift of the dead leg length
As soon as users move in, the slow arrival of domestic hot water is the most recurrent complaint. The client and the tenants judge the quality of the installation on an immediate physical criterion: the number of seconds elapsed between operating the mixer tap and obtaining water at usable temperature. According to SIA 385/1, the permissible waiting time depends on the comfort level agreed at the time of order, but it must not exceed the contractual thresholds, otherwise the plumbing installer's liability for a defect in the work may be engaged.
This waiting time results directly from the volume of the dead pipe, that is to say the terminal section without circulation located between the branch from the riser (or the floor circulation manifold) and the draw-off point. Two factors often aggravate this delay on the construction site: the oversizing of individual connection pipes and the widespread use of water-saving fittings. A modern basin mixer often restricts the draw-off flow to between 4 and 6 litres per minute. At such a flow rate, the slightest excess capacity in a multilayer or stainless steel pipe drastically lengthens the purging of the stagnant cold volume.
To keep the delivery time below the recommended 10 seconds, the dead pipe must not hold more than one litre of water for high comfort requirements, or three litres for standard requirement levels. As soon as the distance to a bathroom or kitchen results in a larger static volume, a simple branch connection no longer complies with the recognised rules of the trade. Extending the domestic circulation loop network to the floor distribution boxes or directly to the foot of the banks of appliances then becomes technically necessary.
Balancing the circulation loop and joint inspection at acceptance
Laying a circulation pipe and connecting a domestic pump in no way guarantees a uniform waiting time throughout the building. In branched networks, hot water naturally takes the path with the lowest hydraulic resistance, creating a short circuit on the risers close to the boiler room and leaving the distant risers to cool. For every tap to benefit instantly from distributed hot water, the methodical balancing of return flows is a mandatory step before any acceptance of the work under SIA 118.
- Setting the balancing devicesAdjust each static or thermostatic balancing valve located at the foot of the domestic circulation riser to obtain the calculated setting and prevent temperature drops of more than 5 kelvins on the returns.
- Heating up and stabilisationLet the domestic circulation pump run continuously for at least two hours, without any draw-off in the dwellings, in order to equalise the temperature on all terminal circuits.
- Timed measurement at the most unfavourable draw-off pointOpen the furthest mixer tap at nominal flow, start the stopwatch and use a calibrated temperature probe to measure the exact time needed to reach the required hot water temperature.
- Recording in the test reportEnter the flow, tap water temperature and waiting time values on the joint protocol sent to the site management.
| Finding at the draw-off point | Hydraulic or thermal origin | Corrective measure on site |
|---|---|---|
| Wait of more than 20 seconds on an entire riser | Balancing fault on the return valve of the riser concerned; circulation flow almost zero. | Adjust the return balancing valve or replace the faulty thermostatic cartridge at the foot of the riser. |
| Excessive waiting time only at the first draw-off in the morning | No non-return valve on the circulation loop discharge, or reverse thermosiphon during the night. | Check the tightness and the mounting direction of the non-return valve of the domestic circulation pump. |
| Delay concentrated on a single isolated sink or basin | Excessive dead leg between the connection to the loop and the mixer tap, combined with a tight flow limiter. | Rework the route to bring the loop closer or reduce the internal diameter of the terminal pipe, subject to pressure loss. |
| Prolonged lukewarm water followed by a sudden rise in temperature | Massive heat losses on the uninsulated dead pipe passing through a ventilated void or cold false ceiling. | Fit continuous thermal insulation with a vapour barrier over the entire concealed or exposed dead section. |
Delivering a domestic water distribution without a thermal test protocol exposes the company to costly disputes after the keys are handed over. As soon as the joint report proves the agreement between the loop flows, the waiting times recorded and the tolerances of SIA 385/1, the compliance of the installation is legally established against the client's requirements.
Remedying distribution defects and handling complaints
The finding of an excessive waiting time when moving in is the main complaint addressed to the plumbing installer. When hot water is slow to flow at the draw-off point, clearing the reservation requires a rigorous diagnostic method before any destructive intervention on the ducts or false ceilings.
- Joint measurement of flow and timeOpen the most unfavourable tap at the nominal service flow with a graduated container and a stopwatch. Record the water temperature with an immersion thermometer from the moment of opening until the setpoint stabilises.
- Hydraulic check of the loopCheck that the non-return valve downstream of the domestic circulation pump is working properly. A valve stuck in the open position causes flow reversal by drawing lukewarm water from the loop return during a heavy draw-off.
- Inspection of the actual branch measurementMeasure the physical route between the connection tee on the circulated riser and the terminal fitting. Unforeseen offsets to bypass dual-flow ventilation ducts frequently lengthen the dead leg beyond the initial calculations.
| Observed symptom | Hydraulic origin | Corrective action on site |
|---|---|---|
| Persistent lukewarm water at the draw-off point | Leaking pump check valve or reverse thermosiphon | Replacement of the non-return valve and cleaning of the pump body |
| Excessive waiting time on a single riser | Balancing fault in the circulation loop network | Fine adjustment of the riser thermal control valves |
| Actual dead leg longer than the planned route | Offset not recorded when the slabs were poured | Fitting of a self-regulating heating tape under reinforced insulation |
Frequently asked questions
How can you identify whether the hot water delay comes from the pump or from the terminal network?
Place a contact thermometer directly on the branch tee between the circulated riser and the individual branch. If the main pipe is already at setpoint temperature before the tap is opened, the malfunction stems exclusively from an excessive dead leg on the terminal branch. If the riser is cold, the fault comes from a hydraulic imbalance, a stopped domestic circulation pump or a stuck check valve.
Does fitting a heating tape compensate for a non-compliant dead leg under SIA 385/1?
Yes, self-regulating electric trace heating fitted under the insulation is a recognised alternative for turning a dead branch into a section kept at temperature. However, this solution requires rigorous coordination with the electrician for the connection and thermostatic control. It must be validated by the site management, because it entails a permanent residual electricity consumption that alters the theoretical energy balance planned for the domestic hot water installation.
Who bears the cost of the changes if the structure requires the domestic hot water branch to be offset?
The plumbing installer must notify the site management of any structural obstacle that requires an offset increasing the dead leg beyond the calculation tolerances. If this finding is notified before the pipes are laid in the slab or false ceiling, the change of route or the addition of a circulation point is the subject of a technical addendum. Without prior notice, the installer bears the correction of the defect at acceptance.
What test flow should be applied during the joint check of the waiting time at the tap?
The check is carried out at the standard nominal flow of the installed fitting, without removing the aerator or the flow regulator. For a standard basin fitted with an economical flow restrictor, this flow is generally around six litres per minute. The tap must be opened fully in the maximum hot water position. Timing starts when the lever is operated and stops as soon as the required usage temperature is measured at the jet.
Texts and standards cited
- norme SIA 385/1Domestic hot water installations in buildings: general principles and thermal comfort requirements
- norme SIA 118General conditions for the execution of construction work: handling of notices of defects and acceptance of the work
