Skip to content
Website
🧱 CFC 250Cold water, hot water and recirculation distributionChapter 4 of 10 in the section

The riser: service shaft, access hatches and floor valves

This chapter guides you through organising sanitary service shafts with rising distribution. You will learn to position the floor and dwelling shut-off devices in accordance with the recognised rules, to check the real accessibility of the valves through properly sized hatches and to produce clear identification so that maintenance work can be carried out without a general shut-off of the building.

Key takeaways

  • Sectorisation by floor avoids interrupting the supply to the whole building during a simple private repair.
  • The SIA 385/1 standard sets the requirements for distribution and for maintaining sanitary water temperatures.
  • An access hatch must offer sufficient clearance to handle two spanners without striking the transom.
  • Rigid identification of the valves ensures immediate identification of each dwelling in an operational emergency.

Positioning the isolation valves per floor and per dwelling according to SIA 385/1

In a multi-occupancy residential building or an office building, the absence of intermediate isolation turns the replacement of a simple tap washer into a general shut-off. The distribution of cold water and domestic hot water requires a strict hierarchy of shut-off devices. The riser is the main artery of the building; each horizontal branch must be able to be isolated completely independently without disturbing the floors below or above.

Domestic hot water distribution and circulation installations must be designed and operated so as to maintain the set-point temperatures, ensure drinking water hygiene and allow sections to be isolated for maintenance without unbalancing the whole network.

Norme SIA 385/1

The principle diagram adopted in French-speaking Switzerland is based on a two-level isolation arrangement. At the tapping point on the riser, a first floor valve allows work on the whole landing loop or on the main manifold. Then, at the property boundary or immediately where the pipe enters the apartment, an isolation valve specific to the dwelling ensures the complete autonomy of the user and of the maintenance services. This rule applies to cold drinking water, domestic hot water and the circulation return.

Shut-off levels and functions on a sanitary riser
Shut-off deviceRecommended locationMain role in operationConsequence of operating it
Riser base valveBasement or plant roomComplete isolation of the vertical riser for repair workShut-off of all floors served by the riser
Floor branch valveService shaft on the landingMaintenance of landing manifolds and metersSupply stopped on the floor concerned only
Dwelling shut-off valveApartment entrance or dedicated hatchTap replacement, repair or private water damageShut-off confined to the dwelling with no impact on neighbours
Circulation balancing valveDHW return in the landing shaftThermal balancing according to SIA 385/1Change in the floor's temperature-maintenance flow rate

Sizing the shaft hatches and formalising pipe identification

An inaccessible shut-off valve is a useless valve. All too often, technical coordination overlooks the final opening left by the finishing work: ball valves end up offset behind a metal frame stud or wedged at the back of a service shaft that is too narrow. The sanitary installer must require, from the structural work and plastering coordination meetings onwards, the provision of an access opening compatible with tightening tools and the swing of the handles.

  • Front clearance: provide at least 200 mm of free space between the valve handle and the hatch door.
  • Lever swing: check that the butterfly handle or quarter-turn lever can pivot through 90 degrees without striking a neighbouring pipe or the thermal insulation.
  • Line of sight and operation: place the operating heads between 0.80 m and 1.50 m above finished floor level to avoid the use of a stepladder in a cramped shaft.
  • Replacement of components: reserve a sufficiently long straight section to remove a sub-meter or an anti-pollution check valve without removing the riser clamps.

Identification of installations in service shafts tolerates no improvisation with an indelible marker. Each valve must carry a rigid identification plate, firmly fixed to the valve body or to the adjacent pipe with a durable clamp. The label states legibly the fluid carried, the direction of flow and the precise designation of the unit served, for example the apartment number or the land-register reference of the dwelling. In the event of water damage, the caretaker, the resident or the fire service must be able to identify the right valve within seconds, avoiding operating errors with disastrous consequences.

  1. Checking the installation of risers and branchesCheck the vertical alignment of the pipes, the thickness of the insulation shells and the orientation of the branches so that the valves face the opening of the hatch.
  2. Checking the opening dimensions with the plastererMeasure the rough frame of the service shaft before the door frame is fitted to confirm real accessibility to the connection nuts.
  3. Fitting standardised identification labelsFix engraved plates indicating the type of water (cold drinking water, domestic hot water, circulation) and the official number of the dwelling concerned.
  4. Operating test and acceptanceFully open and close each valve through the hatch, with the hatch closed and then open, to confirm that there is no dynamic obstruction to the handle.

Installing shut-off devices in the shaft: mechanical accessibility, draining and operating requirements

Installing a floor or dwelling isolation valve is not simply a matter of inserting a ball valve on the riser branch. In a vertical service shaft shared with other fluids, the bulk of the insulation, the crossing of drainage collectors and the swing of the handles dictate the exact position of each component. A valve that is inaccessible, or whose handle strikes an acoustic clamp, loses all operational usefulness on the day of an incident.

To reconcile the requirements of the SIA 385/1 standard on the sectorisation of domestic hot water distribution with routine maintenance, each apartment branch must include a dedicated shut-off valve, supplemented by an adjustable drain system located immediately downstream of the shut-off element. This arrangement makes it possible to lock out and drain the private installation without disturbing the floor circulation or depriving the other dwelling units of hot or cold water. The drain valve must be oriented downwards or towards the outside of the shaft so that a drain hose can be connected during maintenance work.

Positioning constraints for shut-off devices in a rising service shaft
Sanitary componentRequired position relative to the hatchMinimum tool clearanceRisk if not complied with
Main floor valve (cold / hot water)Facing the opening, horizontal axis or inclined at 45°150 mm around the handwheel or leverImpossible to close the valve without dismantling the lining
Dwelling shut-off valve with drainAt the edge of the shaft, at a height between 800 and 1400 mm100 mm below the drain plugFlooding of the shaft bottom or of the slabs below during draining
Sub-meter for waterDirectly downstream of the dwelling shut-off valve250 mm lengthwise for a torque wrenchReplacement impossible without cutting the pressed pipes
Circulation control or balancing valveOn the return pipe, accessible without a ladder80 mm around the pressure test pointsThermal balancing impossible according to SIA 385/1

Coordination of openings, airtightness and functional check before closing the hatches

The effectiveness of the access hatch depends on close coordination between the sanitary fitter and the finishing trades. The sanitary installer positions his riser manifolds and floor branches before the lightweight service shaft partitions are erected. If the axis of a meter or valve is offset relative to the opening provided for the hatch frame, access becomes partial, preventing two hands from being used to hold a back-up spanner when dismantling a threaded fitting.

  1. Setting out and marking on the floorPosition the axes of the risers and floor branches according to the hatch opening drawings. Mark with an indelible marker the plumb line of the opening frame supplied by the plasterer or joiner.
  2. Installing the branches and rigid fixingFix the isolation valves on galvanised shaft brackets. The pipes must not carry the weight of the shut-off devices or the forces of operation during sudden opening and closing.
  3. Permanent labelling and colour codingFit rigid, waterproof engraved plates secured with a strong plastic clamp on each pipe and at each valve. The designation must state the fluid (cold sanitary water, domestic hot water, circulation) as well as the exact number of the unit or dwelling supplied, in accordance with the distribution drawings.
  4. Operability test and pressure testingBefore the shaft is closed with plasterboard, check the full closing travel of each valve and operate the drain plug. Carry out the leak-tightness tests at the test pressure required by the SSIGE W3 directive.
  5. Acceptance check of the hatchOnce the hatch is fitted and finished, open the door to confirm that the direct view gives onto the meter dial, the valve levers and the engraved markings without any structural obstruction.

Rigorous identification of the valves is the last essential step of the sanitary work. In the event of a hose failure or a leak on a pressurised appliance, the caretaker, the tenant or the on-call plumbing service must identify within seconds the isolation valve of the dwelling concerned. A handwritten label on masking tape is prohibited because of condensation and thermal ageing in a closed shaft. Only engraved plates in multilayer plastic or anodised aluminium, mechanically fixed, guarantee lasting legibility throughout the service life of the building.

Handling access non-conformities and shaft acceptance

On the construction site, the late discovery of an inaccessible floor valve is a frequent dispute between the sanitary contractor and the site management. When the shaft lining is closed over a frame that is too narrow or offset relative to the manifold, the shut-off device becomes inoperative. Such a situation contravenes the maintenance principles of the SIA 385/1 standard and prevents rational operation of the water distribution. Faced with this defect, the sanitary installer must not accept the closing of the hatches without stating his reservations in writing in accordance with the rules of the SIA 118 standard.

  • Require the opening to be enlarged if the clear passage does not allow the lever to be fully operated through 90 degrees or a sub-meter to be replaced.
  • Fit stem extensions or offset the quarter-turn valves by means of removable fittings if the shaft can no longer be modified by the plasterers.
  • Reconfigure the riser fixing clamps to free the axis of rotation without mechanically stressing the secondary branches.
  • Replace deteriorated temporary adhesive labels with rigid engraved plates, riveted or fixed with metal clamps on the valve body.

If the site management refuses to adapt the inspection opening, the installer records the non-conformity in the site diary. Responsibility for a general shut-off imposed on a whole building to repair a simple mixer tap lies with the designer who approved an inaccessible shaft. The pressure test and flushing record must include the complete inventory of isolation valves, with a certificate of operability for each dwelling. This document protects the sanitary contractor at final acceptance of the work and guarantees the client a durable installation that complies with Swiss safety and drinking water hygiene requirements.

Frequently asked questions

What should be done if the plasterer has fitted a hatch that is too small to reach the floor valve?

You must notify the defect to the site management in accordance with the SIA 118 standard before any acceptance. Do not attempt to adapt the valve with non-removable makeshift fixes. The plastering company must cut the lining and fit a frame with dimensions conforming to the coordination drawings. An inaccessible valve is equivalent to no valve: in the event of a leak, the sanitary contractor would be held liable if he accepted the work without reservation.

Why does the SIA 385/1 standard require individual shut-off per dwelling in addition to the riser valve?

The SIA 385/1 standard aims at continuity of service and at limiting stagnation in the distribution network. Isolating an apartment to replace a tap or repair a leak avoids draining the whole riser of the building. This reduces the waste of treated water, prevents air from entering the main network and eliminates hydraulic disturbances for neighbours. This arrangement also facilitates maintenance of individual water meters without affecting the co-ownership.

What type of identification must be fitted on the shut-off valves in the service shaft?

The identification must be permanent, clearly legible and firmly fixed. Use rigid engraved plates in synthetic material or aluminium, fixed by small chains or metal clamps directly on the pipe or the valve. The label states the fluid (cold sanitary water or domestic hot water), the number of the dwelling served and, where applicable, the reference of the associated sub-meter. Marker pen markings or adhesive tapes are prohibited.

How can the fire resistance of the shaft be ensured while keeping access to the sanitary valves?

The service shaft forms a vertical fire compartment passing through the slabs. The access hatch must have a fire resistance equivalent to that of the shaft wall, generally EI30 or EI60 according to the VKF/AEAI fire protection requirements. The sanitary contractor makes sure that the swing of the leaf does not strike the valves and that the peripheral intumescent seal remains intact. Any pipe passing through the shaft must also receive an approved fire stop.

Texts and standards cited

  • SIA 385/1Domestic hot water installations in buildings - Design and sizing
  • SIA 118General conditions for the execution of construction work

In the same section