🧱 CFC 212Anchorages, stability and wind resistanceChapter 4 of 10 in the section

Filling anchor holes after removal: who does it and with what

After this chapter, the team leader and the site manager will be able to define the contractual responsibilities for filling the anchor holes before the scaffolding is dismantled. They will master the choice of products according to the nature of the facade substrate and will be able to formalise the traceability of the treated points to prevent any water-ingress dispute.

Key takeaways

  • The preliminary written agreement specifies precisely who carries out the final sealing of each anchor hole.
  • The choice of mortar or sealant depends strictly on the composition of the external substrate.
  • Defective sealing exposes the building envelope to destructive water ingress during freeze-thaw cycles.
  • The joint photographic record made at removal protects the company against late claims for defects.

Define the contractual boundary and carry out the technical sealing according to the substrate

Dismantling the scaffolding frees dozens of holes that pass through the protective covering to reach the load-bearing substrate. A hole left open or sealed only superficially lets rainwater penetrate to the core of the structure, causing major damage after a few freeze-thaw cycles. To prevent such damage, the allocation of tasks must absolutely appear in the contract documents before the construction site opens. Under standard SIA 118, the scaffolder's primary mission is to guarantee the stability of its temporary structure and to ensure it is removed safely; the final refurbishment of the facades falls by default to the specialised trades such as plasterers-painters or facade contractors. However, without an explicit clause, site management may require the scaffolder to seal the openings itself as the decks are dismantled.

Sealing is not limited to inserting a protective plastic plug. The watertightness of the filling requires strict physico-chemical compatibility with the substrate being penetrated. In raw concrete, removal of the plug or its deep driving-in must be followed by careful dust removal, injection of a non-shrink mineral grout or application of a repair mortar based on a hydraulic binder. On masonry of terracotta or calcium-silicate bricks with mineral render, the body of the hole is filled with a lime mortar or a gauged mortar, then closed with a hybrid elastomer or polyurethane sealant that is watertight against driving rain but remains open to water-vapour diffusion. For facades fitted with external thermal insulation, water penetration would ruin the insulation: a rot-proof closed-cell expanding foam must be injected at the level of the insulation, a suitable sealing washer inserted, and then a surface seal made that is compatible with the finishing render.

Recommended sealing materials according to the nature of the facade
Type of substrateTreatment of hole baseSurface sealing
Exposed reinforced concreteExtraction of plug or driving in to 20 mmThixotropic non-shrink mineral repair mortar
Traditional rendered masonryRemoval of dust and flexible backing cordPaintable polyurethane or hybrid elastomer sealant
External insulation (render on insulation)Reconstitution of the insulation with compact foamWatertight washer and tinted reinforced render plug

Organise traceability through a photographic record and control the legal risk

Scaffolding is the only secure means of access to reach the anchor points on the upper floors. When the filling task falls to the facade contractor, the latter must work in concert with the erection team, intervening level by level as the standards and frames are removed. If the scaffolder leaves the construction site with the holes still open under the responsibility of another trade, it must absolutely document this situation. A joint inspection record with site management and the trades concerned attests to the accessibility of the areas and the condition of the facades at the time the equipment is withdrawn. This record relieves the scaffolder of any damage caused later by the weather.

  1. Systematic countCount every anchor point per facade and per level on the layout plan before dismantling starts.
  2. Coordination of interventionsCheck that the company in charge of sealing is actually present on the upper deck before it is physically dismantled.
  3. Geolocated photographPhotograph the released anchor and its filled state with a clear visual marker on the facade.
  4. Signing of the recordHave the dismantling sheet countersigned, expressly stating that the holes will be made good by the designated tradesperson or by site management.

The photographic record at dismantling is essential technical evidence in the event of a later dispute concerning water ingress. A close-up photograph shows that the filling was properly carried out or, conversely, the absence of filling contractually agreed with the third party. Art. 367 CO states that after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects. If water ingress appears months after the acceptance of the work because of deteriorated or omitted seals, the visual history protects the scaffolding company against an unfounded claim. Art. 365 CO also reminds us that the contractor informs the client if a circumstance jeopardises the proper execution of the work; notifying in writing that holes remain open in the rain is part of this basic duty of care, so as to avoid bearing the damaging consequences.

Choice of sealing components according to the nature of the facade substrate

Sealing a scaffolding anchor is not just a matter of hiding a hole on the surface. Each type of substrate requires strict physical and chemical compatibility between the original material, the backing cord and the levelling or caulking compound. An error in the product invariably leads to the plug detaching, the surrounding render cracking or interstitial moisture becoming trapped in the masonry.

Suitability of filling systems according to the nature of the substrate
Type of substrateInternal sealing layerExternal filling materialTechnical points of attention
Exposed reinforced concreteNeoprene plug or closed-cell PE backing cordThixotropic non-shrink mineral repair mortarDust removal by blowing out; prior dampening without a shiny film of water.
External insulation (render on EPS/mineral wool)Cut insulating cylinder or watertight expanding sleevePolyurethane or hybrid elastomer sealant under finishing renderThermal continuity is imperative to avoid a localised dew point.
Terracotta brick masonryCalibrated cellular backing cordNatural hydraulic lime mortar or gauged mortarWater-vapour permeability preserved; avoid overly rigid pure cements.
Ventilated facade (composite panels, fibre boards)EPDM washer under plate or compriband sealing tapeSynthetic closure cap in RAL colour or sealed blind rivetStrict compliance with the drainage plan and the rear air cavity.

On off-form raw concrete, the use of shrinkage-compensated hydraulic mortars ensures intimate contact with the walls of the 12 to 14 mm diameter hole. Before any extrusion or tamping with a steel tool, the drilling dust must be removed completely: the powdery residue forms a separating film that destroys mechanical adhesion. For external thermal insulation composite systems, the scaffolder leaves the plastic plug in place if the specification provides for it, or inserts a core of rock wool or polystyrene before the surface sealing, thereby preventing any localised thermal bridge.

Staged dismantling protocol, lasting sealing and closure of responsibilities

The filling operation cannot be separated from the descent of the facade scaffolding. As soon as a deck level is dismantled, the area of facade immediately above becomes inaccessible without heavy rope-access means or lifting platforms. Sealing is therefore carried out bay by bay, level by level, while the scaffolder stands safely on the working deck.

  1. Removal of the mechanical fixing and brushingUnscrew the anchor eye without damaging the edge of the render. Clean the hole with a round wire brush and blow the residual dust outwards.
  2. Installation of the watertight base barrierPush the residual nylon plug at least 20 mm below the outer face, or insert a watertight synthetic backing cord to block the path of water towards the structural work.
  3. Application of the sealing productFill the hole by continuous injection with a gun or by tamping with a flat steel tool, expelling the air to prevent any internal water pocket. Strike off rigorously flush with the substrate.
  4. Reconstitution of the facade finishFit the matching tinted plug or float the finishing mortar layer according to the instructions of the descriptive quote.
  5. Georeferenced photographic recordPhotograph the treated point with a bay-axis marker and the floor number, before going down one scaffolding level.

According to art. 367 CO, after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects, the client having 60 days to report them for an immovable work. The scaffolding company prevents late disputes relating to concealed water ingress by annexing its joint photographic register to the dismantling record. This document proves the effective watertightness of the fixing points carried out under its care before the construction site is released.

Water-ingress disputes and handling of reservations at dismantling

When water ingress occurs behind a former anchor point, expert assessments frequently call the scaffolding removal into question. A plug cut off flush without sealing, or a cavity left open in a calcium-silicate brick, allows driving rain to reach the insulating lining. The cost of repairing a ventilated facade or a damaged external insulation far exceeds the original erection budget. For the scaffolder, risk control rests on rigorous application of the works contract and traceability of the interfaces.

According to art. 367 CO, after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects. For an immovable work, the client has 60 days to report defects. If the agreement provides that filling is the responsibility of the plasterer-painter or the facade contractor, the scaffolder must give notice of the condition of the fixing points when handing over the facades, level by level.

  • Draw up a joint inspection record with site management when each working deck is withdrawn.
  • Record each PVC plug retained, together with its closure plug with watertight collar.
  • Record the holes that required a non-shrink mortar or a polyurethane sealant where the filling was entrusted to the scaffolder.
  • Attach the geolocated photographic records identifying the bay numbers and the corresponding levels.

Art. 365 CO states that if another circumstance jeopardises the proper or timely execution of the work, the contractor informs the client, failing which it bears the consequences. A scaffolder who finds friable masonry, a pre-existing crack at the position of an anchor bracket, or a refusal of access by a third-party trade for the final sealing must record these facts in writing. This protocol protects the company against recourse actions during the first frost periods.

Frequently asked questions

Who is responsible for watertightness if the contract does not mention filling?

Without specific mention in the works contract, the scaffolder's services end with the dismantling of its equipment in accordance with the rules of the trade. The structural work contractor or the facade contractor takes care of making good the cladding and the watertightness of the substrates in accordance with standard SIA 118. The scaffolder must nevertheless fit temporary watertight plugs on its anchors to prevent any immediate water ingress before the formal handover of the work to the client.

What product should be used to fill an anchor hole in exposed reinforced concrete?

On a raw reinforced concrete facade, the scaffolder extracts the mechanical or plastic plug, cleans the hole of dust with compressed air and applies a non-shrink repair mortar based on a hydraulic binder. If the colour must faithfully match the original concrete, the work is for a concrete specialist. Pending the facade contractor, a watertight cellular elastomer plug protects the internal reinforcement against rainwater.

How should an anchor penetration in an external thermal insulation system be treated?

In external thermal insulation, the anchor passes through the render and the insulation. The scaffolder extracts the sleeve and injects a polyurethane foam disc or a thermal-break washer into the thickness of the insulation. The surface seal requires an acrylic or polyurethane sealant suited to the vapour permeability of the render, followed by fitting of a preformed washer by the plasterer to avoid any thermal bridge.

Why record a systematic photographic condition survey when the scaffolding is withdrawn?

The absence of traceability exposes the scaffolder to challenges several months after leaving the construction site. Photographing each anchor hole with a reference rule or a bay marker proves the condition of the masonry when the fixing is removed. This document certifies the fitting of watertight plugs or highlights damage attributable to third parties. The images are included in the dismantling record sent to site management.

Texts and standards cited

  • CO art. 365material and ground: the contractor is responsible for the good quality of the material it supplies; if the material supplied by the client or the ground designated by the client is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, it must inform the client immediately, failing which it bears the consequences (para. 3).
  • CO art. 367after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects; for an immovable work, the client has 60 days to report them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2).
  • norme SIA 118General conditions for the execution of construction work.