🧱 CFC 232Lockout/tagout, dead working and arc flash riskChapter 10 of 10 in the section

Co-activity: circuits re-energised by another party, and shared lock-out

On a construction site with co-activity, switching off without locking out directly exposes the electrical installer to re-energisation by a third party. This chapter details how to apply personal locking, the rigorous application of the principle that only the person who locked out may unlock, and the communication protocols with the other trades.

Key takeaways

  • Simple adhesive tape on a circuit breaker offers no protection against an unintended operation.
  • Each worker must place their own padlock on a hasp during shared operations.
  • The fundamental rule requires that only the tradesperson who locked the device may remove their personal padlock.
  • Prior information and a notice at the main switchboard prevent re-energisation attempts by third parties.

Individual physical locking: neutralising the risk of unintended re-energisation

On refurbishment or structural work construction sites, co-activity exposes the installer-electrician to a recurring danger: accidental re-energisation of a circuit by a third party. A plasterer trying to connect a spraying machine, a tiler whose mixer has stopped, or a subcontractor from another work package will often operate the switches of temporary distribution boards or main switchboards if they notice a loss of power. A felt-tip marking or a piece of adhesive tape placed on a modular circuit breaker is in no way a sufficient mechanical barrier to guarantee the absence of voltage.

To prevent accidents and occupational diseases, the employer shall take all measures that experience has shown to be necessary, that are feasible given the state of the art and that are appropriate to the given conditions; workers shall support the employer (in particular by using personal protective equipment).

art. 82 LAA

To comply with the SUVA directives and the five vital safety rules of the electrical trade, the isolation of the circuit must be locked against re-energisation. This mechanical protection relies on personal locking. Each installer working on the isolated part of the installation places their own safety padlock on the locking device (circuit-breaker lock-out device, switch handle blocker or lockable isolator handle). The padlock must have a unique key: master keys and spare keys left on the construction site are strictly prohibited.

Mandatory components of the personal locking device
Hardware itemTechnical functionApplication requirement
Modular lock-out deviceMechanically blocks the circuit-breaker leverSuited to the profile of the device (clamping screw or jaw)
Lock-out padlockPrevents access to the reset operationNon-conductive body, single key kept by the operator
Personal tagIdentifies the holder and the reason for the switch-offShows name, company, telephone and date
Multiple haspAllows 2 to 6 separate padlocks to be attachedSteel or filled polyamide, to be fitted systematically from two workers onwards

Strict unlocking and active coordination with the other companies

The second operational requirement of the SUVA directives is simple: only the person who locks out may unlock. No foreman, site manager or colleague has the authority to remove an electrician's padlock in their place. This absolute rule ensures that the person exposed to the risks of direct contact or electric arc remains the sole decision-maker for re-energising the supply conductor. Before releasing their lock, the electrician checks visually that all insulating protections are closed again, that temporary earth connections have been removed and that personnel are out of reach.

The employer shall take the protective provisions and measures that meet the requirements of the ordinance, the other applicable occupational safety provisions and the recognised rules of safety engineering and occupational medicine.

art. 3 OPA
  1. Analysis of the work areaCheck that the connection work is actually finished, that tightening has been done to the specified torques and that the enclosures or protective covers are closed.
  2. Formal notice to neighbouring companiesInform the other trades present in the work area verbally that re-energisation is imminent.
  3. Removal of personal padlocksEach worker individually unlocks their own padlock from the hasp or the group lock-out box.
  4. Reset and customary checksRemove the lock-out device, operate the switching device, then check the phase sequence and the operating voltages.

Site coordination also requires rigorous management of information intended for the other companies. Any planned shutdown of a sub-distribution board supplying site sockets must be announced by a prior notice posted at least 24 hours in advance or passed on at the weekly coordination meeting. Laminated A4 warning sheets stating explicitly "Construction site under electrical lock-out - Switching on strictly prohibited" are fixed directly on the front of the cabinets concerned, together with the direct telephone number of the person responsible for the lock-out.

Personal locking and the principle of exclusive unlocking

On a refurbishment or structural work construction site, the unintended re-closing of a circuit breaker or isolating switch by a third party is one of the main causes of electric shock and arc-flash burns. Whether it is a worker trying to reactivate a temporary lighting line, a plumbing fitter resetting a circuit to test a circulator pump, or an electrician working on another section, the attempt to re-energise without consultation almost always stems from faulty signage or a purely symbolic block.

To eliminate this risk, the SUVA directives on work on electrical installations require strict application of the five vital safety rules, including mechanical locking against re-energisation. This cannot rely on a simple piece of electrician's tape or a loose tag placed on the switch. It requires a physical blocking device combined with uncompromising personal locking.

  • Personal single-key padlock: body made of insulating material (thermoplastic polyamide) or sheathed shackle, supplied with a single key to rule out any duplicate left in the van or in the site storage cabinet.
  • Personal warning tag: tear-proof tag fixed directly to the padlock, showing the name and first name of the installer-electrician, their company, their direct mobile number, the date and the exact nature of the work.
  • Multiple safety hasp: steel plate or aluminium bracket allowing up to six separate padlocks to be attached to the same isolation point, essential as soon as several technicians work in parallel on the same circuit.

The employer is responsible for providing this lock-out equipment and ensuring it is used in the field, in accordance with art. 82 LAA, which requires taking the prevention measures that are appropriate to the given conditions and whose necessity experience has shown.

Managing co-activity and shared lock-out on distribution cabinets

When the work concerns a low-voltage main switchboard (TGBT) or a site distribution board supplying several trades, locking cannot remain an isolated act. The power interruption affects overall progress: cranes stopped, dewatering pumps cut, safety lighting in basements switched off. Informing the other companies before any lock-out operation is an essential precondition to prevent dangerous behaviour and site claims.

Matrix of hardware provisions for locking according to the switching device
Device to be locked outBlocking device requiredImplementation on the boardVerification of absence of voltage
Modular circuit breaker (DIN)Circuit-breaker lock-out with universal clamping screw or side pinsClamp directly on the switch in position 0 (OFF), fit the personal padlock through the locking eyeletCheck with a multimeter/two-pole detector directly downstream of the device's cage terminals
TGBT load-break isolating switchIntegrated lockable handle or lockable locking coverInsert the padlock shackle or hasp directly into the handle opening provided by the manufacturerFour-pole measurement (phases and neutral) immediately downstream of the switching block before any dismantling
HRC (NH) fuse cut-outRemove the fuse cartridges with the insulated gripping handle and fit lockable dummy bladesMechanical locking of the bases with plastic parts preventing the insertion of any third-party blade or fuseVoltage check on the lower and upper clips, cartridges secured in a key-locked closed box
  1. Prior notice to third partiesAnnounce the shutdown at the coordination meeting or send a notice of interruption to the main foreman and the team leaders of the affected work packages at least 24 hours in advance, specifying the sectors without power.
  2. Physical signage at the boardFix a "do not operate" sign on the door of the electrical cabinet and on the internal cover, showing the identity of the responsible electrician and a formal reminder of the ban on re-energising.
  3. Fitting the group lock-out boxFor complex construction sites, the keys of the padlocks locking the main switching devices are placed in a collective lock-out box; each trade or technician then places their personal padlock on the box.
  4. Unlocking in stagesIndividual removal of the personal padlock only after tools have been cleared away, the refitting of covers has been checked and a visual check has confirmed that nobody is on the connected loads.

In the event of the unforeseen absence of a worker who has left their padlock in place (sudden departure from the construction site, accident, illness), no unilateral breaking of the device is tolerated on the basis of a simple decision in the field. Forced opening requires a formalised procedure under the direct responsibility of the competent person in charge of safety, in accordance with OTConst para. 1. This step requires full physical verification of the line up to the last load, traceable notification to the worker concerned and formal authorisation from site management.

Breach of lock-out and co-activity dispute: emergency stop protocol

On a construction site with co-activity, discovering a forced padlock, a circuit breaker reset without agreement or a removed locking device is an immediately life-threatening situation. When a worker from another trade restores power to test equipment, connect a mixer or carry out trials without warning the installer-electrician, all work in the area must stop without delay. The exclusive unlocking rule — only the person who placed the padlock with personal locking holds the key and has the right to unlock it — tolerates no compromise, even under pressure from site management or delivery schedules.

  1. Immediate stop and moving to safetyThe installers put down their tools, move away from bare conductors and carry out a verification of absence of voltage using a two-pole tester checked before and after use. Every live conductor is deemed energised until the source has been fully neutralised and verified.
  2. Joint inspection record of the factsThe team leader records the physical forcing of the distribution cabinet. He photographs the isolating switch in the ON position, documents the state of the sub-distribution board and precisely identifies the workers or foremen of the third-party work package involved in the uncoordinated operation.
  3. Site arbitration and notificationThe foreman immediately alerts site management and the safety coordinator. Art. 5 OTConst provides that any person who, through their behaviour or condition, endangers themselves or others must be sent away from the construction site. The information given to the other companies is recorded in the site diary.
  4. Strict re-locking before work resumesThe entire five-safety-rules procedure is started again from the beginning. The switching device receives a new personal padlock with a multi-hole hasp if other work packages are later to work on the installation.

Strict compliance with the SUVA directives prevents fatal improvisation during partial commissioning phases. According to art. 82 LAA, to prevent accidents and occupational diseases the employer takes all measures that experience has shown to be necessary, that are feasible given the state of the art and that are appropriate to the given conditions. Installers have an obligation to exercise their right to withdraw when faced with an unlocked cabinet. In the event of a repeat offence by a third-party company, access to the electrical technical room must be physically locked until formal arbitration by the project management.

Frequently asked questions

What should be done if a personal padlock remains in place while the responsible electrician has left the construction site?

It is strictly prohibited to cut or force a lock-out padlock without a written protocol. The site manager must first contact the key holder by name to check their progress and their safety away from the site. If the installer cannot be reached, only an authorised person named in the safety plan may carry out forced unlocking, after a complete check of the line over its entire length and the signing of a record that engages their responsibility.

How should lock-out be organised when a plumber or heating engineer has to connect an appliance to the same supply?

The shared locking rule requires the use of a multiple lock-out hasp placed on the main switch. The installer-electrician places their own personal padlock with their tag, then the worker from the other trade places theirs on the same hasp. The circuit may be re-energised only when each worker has finished their work and personally removed their own padlock. No key may be entrusted to or shared between separate companies on the construction site.

What does the obligation to inform the other companies involve when a board is energised?

The installer-electrician must never energise a section without notice given to site management and posted on site. A clear information notice is fixed at the entrance to the technical room and on the cabinets concerned, stating the date, the time and the areas supplied. At the weekly coordination meeting, the team leader explicitly points out the live circuits to prevent a worker from another trade from touching bare terminals.

What does a third-party worker risk by breaking a lock-out padlock to use a socket?

Deliberately breaking a locking system is a serious endangerment of others on the construction site. Site management must immediately exclude the worker from the site on the basis of the occupational safety requirements. The company responsible for the person who committed the act is also exposed to contractual claims for forced stoppage of the work and restoration of the installations. The electrician records the breach in writing to clear their own responsibility in the event of an accident occurring downstream.

Texts and standards cited

  • OTConstorganisation of occupational safety and health protection: any person who, through their behaviour or condition, endangers themselves or others must be sent away from the construction site
  • LAA art. 82general prevention rules: to prevent accidents and occupational diseases, the employer takes all measures that experience has shown to be necessary, that are feasible given the state of the art and that are appropriate to the given conditions