Earthing, equipotential bonding and lightning protection: the execution reference
Intended for team leaders, foremen and site managers in electrical installations (CFC 232), this section details the implementation of the building's ultimate passive safety. From connecting the foundation earth loop to surge protective devices, including main equipotential bonding and periodic inspections, it sets out the technical procedures, disconnection thresholds and coordination essential on Swiss construction sites according to the NIBT.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
1 m 50
Maximum depth of an unsupported excavation for laying earth electrodes
0,4 s
Maximum disconnection time for a 230 V final circuit, TN system
50 V
Conventional limit touch voltage in alternating current
16 mm²
Minimum cross-section of the copper main equipotential bonding conductor
6 mm²
Minimum earthing cross-section for photovoltaic frames without a lightning conductor
Technical scope: the earthing chain and its construction site interfaces
Earthing and equipotential bonding form the ultimate line of defence to ensure the safety of persons against electric shock and to protect property against atmospheric overvoltages. This section covers all passive protection installations under the direct responsibility of the electrical installer: connection of the foundation earth electrode, design and installation of the main earthing conductor, disconnection terminal bar, main equipotential bonding, supplementary local bonding, lightning protection and routing for photovoltaic roofs.
From a legal standpoint, the correct execution of joints and the choice of materials compatible with the soil prevent hidden deterioration that could engage the criminal liability of the professional within the meaning of art. 229 CP in the event of bodily danger caused by a lack of earthing.
| Component | Recommended material | Strictly prohibited / Risk |
|---|---|---|
| Foundation earth electrode (in concrete) | Unalloyed mild steel round bar or galvanised steel strip | Never leave bare black steel exposed to open air without corrosion protection. |
| Electrode in bare soil | Bare copper or hot-copper-coated steel | Galvanised steel in direct contact with acidic or peaty soils: rapid destruction. |
| Concrete / soil junction | Suitable grade of stainless steel (V4A) | Copper-steel galvanic couple without an insulating sleeve: accelerated corrosion of the steel. |
Methodical order of execution: from excavation to final acceptance
The safety of an electrical installation tolerates no improvisation in sequence. The equipotential bonding network is secured in successive layers as the structural work progresses through to the technical finishing work. Any failure at a buried stage later requires destructive and extremely costly remedial work.
- 1. Coordination of the foundation slab and earth electrodeCheck the reinforcement mesh placed by CFC 211.1, install the certified clamps and place the stainless steel V4A outlet bars before the concrete is poured.
- 2. Initial measurements and installation of the main terminal barMeasure the earth resistance value using the appropriate method, fix the accessible disconnection terminal bar and connect the main loop to the distribution board.
- 3. Main equipotential bonding and steel frameworkInterconnect the metallic water, gas and heating pipes, as well as the structural elements of the building (steel columns, reinforcement).
- 4. Supplementary equipotential bonding and sensitive roomsImplement local bonding in bathrooms, medical rooms or industrial areas requiring a reduced touch voltage threshold.
- 5. External systems: lightning and solarEnsure the lightning conductor down-lead complies with the separation distances and connect the metal frame of the photovoltaic arrays.
- 6. Periodic inspection and OIBT traceabilityRecord the insulation, fault loop and continuity measurements in the acceptance protocols and keep the inspection register.
When working in excavations or along embankments to reach external earth electrodes, the safety of personnel remains the priority. Connection trenches deeper than 1 m 50 must be secured in accordance with art. 68 OTConst to prevent any burial.
📘 Chapters in this section 10
Foundation earth electrode: connection, stubs and timing of the work
Master the connections on the foundation slab before pouring to ensure the durability of the foundation earth electrode.
Earthing, equipotential bonding and lightning protectionMeasuring earth resistance: method, expected value and the influence of the season
Apply the three-pole method and correctly interpret variations in ground moisture.
Earthing, equipotential bonding and lightning protectionMain equipotential bonding: what is connected to it and the accessible busbar
Methodically connect incoming metallic pipes to the disconnection terminal bar to eliminate dangerous potentials.
Earthing, equipotential bonding and lightning protectionSupplementary equipotential bonding: bathrooms and special locations
Make wet rooms and critical areas safe using local bonding that compensates for insulation faults.
Earthing, equipotential bonding and lightning protectionBuried earth connections: corrosion, metals and protection of the junction point
Choose the right alloys to bury your joints without suffering destructive soil electrocorrosion.
Earthing, equipotential bonding and lightning protectionLightning protection: down conductors, separation distance and dedicated earth
Calculate precisely the separation distances of lightning down-leads to avoid any destructive arcing.
Earthing, equipotential bonding and lightning protectionOld installation without a protective conductor: what you can and cannot do
Adopt compliant safety solutions when refurbishing private PE conductors.
Earthing, equipotential bonding and lightning protectionSteel structure: equipotential bonding, continuity of connections and connection points
Guarantee the galvanic continuity of steel frameworks to turn the structure into an effective natural shield.
Earthing, equipotential bonding and lightning protectionPhotovoltaics: earthing of structures and continuous cable routing
Avoid induction loops on solar roofs by arranging the routing of the equipotential conductors in an orderly way.
Earthing, equipotential bonding and lightning protectionPeriodic earth testing: intervals, traceability and change over time
Document the evolution of earth measurements in accordance with the OIBT to anticipate the deterioration of ageing electrodes.