🧱 CFC 232Installation: conduits, distribution boards and switchgearChapter 7 of 10 in the section

Bathroom: safety zones and the equipment permitted in each

After this chapter, you will be able to delimit zones 0, 1 and 2 around baths or showers according to the NIBT without hesitation. You will determine precisely which equipment or luminaire is permitted in each zone, which IP protection rating to require, and how to carry out local equipotential bonding while avoiding the classic trap of the badly positioned spotlight.

Key takeaways

  • The precise delimitation of the zones strictly determines the type and voltage of the permitted equipment.
  • Zone 0 prohibits all equipment except waterproof submersible equipment supplied at extra-low voltage.
  • The common mistake of the recessed spotlight above the bath directly exposes the installation to rejection at inspection.
  • Supplementary equipotential bonding locally interconnects all exposed metal parts and conductive pipework in the room.

Delimiting zones 0, 1 and 2 around the bath according to the NIBT

On a finishing-work construction site, the positioning of flush-mounting boxes and cable outlets in a bathroom tolerates no approximation. Water drastically lowers the electrical resistance of the wet human body, which turns an otherwise harmless indirect contact into a potentially fatal shock. The NIBT structures the protection of persons through a strict geometric division into three distinct zones, taking the inner edge of the bath or shower tray as the starting point. Every electrician-installer must mark out these boundaries before drilling any lining or pulling any conduits.

Zone 0
Interior of the bath or shower tray. For a walk-in shower without a tray, this is the zone bounded by the floor of the drain area up to a height of 10 cm above the finished floor, over an area equivalent to the footprint of the shower.
Zone 1
Zone bounded vertically by the outer perimeter of the bath or shower tray and rising to a height of 2 m 25 above the finished floor, or above the bottom of the tub if this is higher. For showers without a tray, the radius extends to 1 m 20 around the fixed water outlet.
Zone 2
Zone surrounding zone 1, extending horizontally over a width of 60 cm from the outer limit of zone 1, and vertically from the finished floor up to a height of 2 m 25.
Permissibility of equipment and accessories according to the NIBT
ZoneMinimum IP ratingMaximum permitted voltagePermitted equipment and appliances
Zone 0IPX7SELV 12 V AC or 30 V DCNo switchgear or boxes. Only fixed appliances designed for immersion.
Zone 1IPX4 (IPX5 if water jets)SELV 25 V AC or 60 V DCInstantaneous water heater, suitable SELV luminaires, approved whirlpool pumps.
Zone 2IPX4 (IPX5 if water jets)230 V with 30 mA residual current deviceClass II luminaires, class II heating appliances, shaver sockets with isolating transformer.

Outside these zones, in what was historically called zone 3 and which now falls under the general rules with mandatory residual 30 mA RCD protection, standard 230 V sockets become permissible. However, routing electrical cables supplying other rooms through zones 0, 1 or 2 remains formally prohibited by the NIBT, unless these cables are buried under at least 5 cm of solid masonry.

Dealing with the badly placed spotlight and connecting local equipotential bonding

The most recurrent error found during end-of-construction-site inspections concerns the alignment of recessed luminaires in plasterboard false ceilings. The architect or decorator frequently specifies a regular grid of LED spotlights running right across the room. If the false ceiling is 2 m 20 above the finished floor, a spotlight positioned directly above the bath lands squarely in the middle of zone 1.

To validly install lighting above a bath with a low ceiling, the installation team has two compliant technical solutions: move the SELV supply outside zones 1 and 2 by running a dedicated secondary connection to a light source certified IPX4 or IPX5, or raise the finished ceiling level above 2 m 25 so that the space falls outside the zones.

  • Connect the metal hot-water, cold-water and heating pipes using suitable earthing clamps.
  • Interconnect accessible fixed metal casings, including the frames of whirlpool tubs or uninsulated metal shower trays.
  • Use an insulated green-yellow copper conductor with a minimum cross-section of 4 mm² without mechanical protection, or 2.5 mm² in a protective conduit.
  • Run this bonding directly back to the earth bar of the sub-distribution board or to a dedicated, labelled local junction box.
  • Verify by continuity measurement that the resistance is below the prescribed value before the safety report is drawn up.

The foreman systematically checks that this continuity is actually in place before the conduits are covered by the tiler or plasterer. A failure exposes the work to a disqualifying non-conformity at the acceptance inspection under the Ordinance on Low-Voltage Electrical Installations, blocking the issue of the final safety report required by the electricity distributor.

Equipment permitted per zone and IP ratings required according to the NIBT

The positioning of electrical equipment in a bathroom depends strictly on the delimitation of the zones defined by the NIBT. Each zone requires a minimum level of protection against water splashes and drastically restricts the type of appliances permitted, in order to rule out any risk of electric shock when the human body has a lowered electrical resistance due to immersion or moisture.

Permissibility of equipment and minimum degrees of protection per zone
ZoneMinimum IP ratingMaximum permitted voltagePermitted equipment and appliances
Zone 0 (inside the tub)IPX7SELV 12 V AC or 30 V DCOnly fixed appliances intended for this use (waterproof whirlpool jets). No switches or sockets.
Zone 1 (above the tub up to 2.25 m)IPX4 (IPX5 if water jets)SELV 25 V AC or 60 V DC (or 230 V for dedicated fixed appliances)Instantaneous or storage water heater, fixed class III SELV luminaires, hydromassage pumps permanently connected. No 230 V sockets.
Zone 2 (60 cm perimeter around zone 1)IPX4 (IPX5 if water jets)230 V AC (protected by 30 mA RCD) or SELVFixed class II luminaires, class II heated towel rails, shaver socket with built-in isolating transformer (according to product standard). Conventional sockets prohibited.
Outside the zones (beyond 60 cm from zone 1)IPX0 (IPX4 if splashes are possible)230 V AC (protected by 30 mA RCD)Standard sockets with earth contact, single-pole or two-way lighting switches, usual household appliances.

Concealed cables supplying zone 1 or zone 2 must be limited to what is strictly necessary to serve the appliances located in these zones. Any routing of cables not related to these zones remains prohibited in the walls bounding these spaces, unless the chase or the installation in conduit keeps a solid masonry cover at least 5 cm thick to avoid accidental drilling when fixing bathroom accessories.

Carrying out the compliance check and supplementary equipotential bonding

The overall safety of a sanitary installation relies jointly on the instantaneous action of residual current protection and on the equalisation of metallic potentials. The electrician-installer must ensure that every circuit supplying the bathroom benefits from automatic disconnection by a residual current device (RCD) rated at 30 mA maximum, whether for lighting circuits, sockets or heating.

  1. Survey of exposed metal parts and conductive bodiesIdentify all fixed metal elements entering the zones: copper or steel sanitary water pipes, metal underfloor heating manifolds and aluminium frames if they are in electrical contact with the building structure.
  2. Connection of the equipotential bonding conductorInstall an insulated green-yellow copper conductor with a minimum cross-section of 4 mm² (without mechanical protection) or 2.5 mm² (if run in a protective conduit), connected directly to the main protective conductor of the distribution board or to the local earth bar.
  3. Treatment of acrylic baths and shower traysIf the body of the bath or shower tray is synthetic (acrylic, resin), metallic equipotential bonding on the tub is impossible. The connection must then be made on the supply pipework upstream of the tap hoses.
  4. Electrical continuity checkMeasure the continuity between each accessible conductive metal element and the main earth terminal using an ohmmeter delivering a test current of at least 200 mA at a voltage between 4 and 24 V, confirming a resistance below 0.2 ohm.

The contractor notifies the client of any architectural arrangement that makes a compliant installation impossible, in accordance with art. 365 CO al. 3. Defective work that knowingly creates a direct danger for the user incurs the criminal liability of the installer under art. 229 CP. The final safety report certifies the RCD tripping measurements and the continuity of the equipotential bonding.

Handling positioning non-conformities and installation rework

On the construction site, conflict frequently arises when the false ceiling or the tiling is installed: a luminaire opening cut at 2 m 15 above the bottom of the tub automatically places a 230 V spotlight in zone 1. Similarly, a socket installed too close to the outer edge of a shower tray without a fixed screen violates the delimitation of zones prescribed by the NIBT. As soon as an unauthorised appliance, or one with an insufficient protection rating, is installed in these critical zones, the foreman must refuse energisation during the preliminary tests.

  1. Establishing the geometric breachMeasure with a tape measure the exact distance from the inner edge of the bath or from the origin of the shower hose. If the luminaire is less than 2 m 25 from the finished floor or from the bottom of the tray, it necessarily falls within zone 1.
  2. Replacing the equipment with a permissible solutionIf the opening can no longer be filled by the plasterer, replace the 230 V luminaire with a model supplied at safety extra-low voltage 12 V AC or 30 V DC, certified at least IPX4. The safety transformer must absolutely be relocated outside zones 0, 1 and 2.
  3. Restoring the local equipotential bondingIf the protective conductor to the fixed metal elements entering the room has been omitted, remake the bonds on the sanitary pipes upstream of the insulating couplings using nickel-plated copper clamps before the service ducts are closed.
  4. Recording the rectification of defects on the measurement recordMeasure earth continuity below 0.2 ohm with the measuring bridge, check the tripping of the 30 mA residual current circuit breaker and formally record the corrected values on the test record before handing the file to the client.

The electrician incurs civil liability and criminal liability if they knowingly connect an installation that contravenes the recognised rules: under art. 229 CP, anyone who breaches the rules of the building art and thereby endangers the life or limb of others is liable to prosecution. Immediate correction of the box position or of the operating voltage remains the only acceptable technical outcome.

Frequently asked questions

Is a waterproof IP65 230 V spotlight permitted in zone 1 above a bath?

No. Even with a high IP rating protecting against water jets, the NIBT prohibits any lighting appliance supplied directly at 230 V in zone 1. Only fixed luminaires designed specifically for this use, supplied at safety extra-low voltage of at most 12 V AC or 30 V DC and with a rating of at least IPX4, may be installed within this perimeter.

Where exactly does zone 1 end if the shower has no tray?

In a walk-in shower without a tray, zone 1 does not stop at the level of the sloped tiling. It extends over a horizontal radius of 120 cm measured from the centre point of the fixed shower head or from the attachment point of the wall-mounted hose, and rises vertically to a height of 2 m 25 above the finished floor. Any equipment installed in this zone must meet the strict requirements of zone 1.

Must the acrylic bath be connected to the local equipotential bonding?

No. A bath made of synthetic material is not a conductive element capable of propagating a dangerous potential. However, the metal cold-water and hot-water pipes supplying it, as well as metal tap bodies connected to conductive pipes, must be connected to the local equipotential bonding of the bathroom if this continuity is not ensured directly upstream of the room by the main network.

What should be done if the equipotential bonding conductor was forgotten before the tiling was laid?

Identify the accessible extraneous conductive parts and run a 4 mm² copper protective conductor in exposed conduit or in the skirting boards to the distribution board or the nearest junction box. If the sanitary pipes are entirely made of non-conductive multilayer composite material, direct local bonding on the taps is no longer required by the NIBT, which avoids heavy reopening of the walls.

Texts and standards cited

  • NIBTStandard on low-voltage installations: requirements for rooms containing a bath or shower, delimitation of zones 0, 1 and 2, minimum protection ratings and permitted equipment
  • OIBTOrdinance on Low-Voltage Electrical Installations: safety rules, the installer's final inspection and issue of the safety report
  • CP art. 229breach of the rules of the building art: anyone who, in directing or carrying out a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or limb of persons is liable to a custodial sentence of up to five years or a monetary penalty; if through negligence, up to three years or a monetary penalty