Key takeaways
- A measurement taken with loads still connected distorts the result and risks damaging the electronics.
- All-pole disconnection and the absence of voltage must be verified before any connection of the megohmmeter.
- For standard low-voltage final circuits, the NIBT requires a minimum resistance of one megohm.
- The test is carried out at a DC voltage of 500 volts between live conductors and the protective conductor.
Preparing the feeders and isolating sensitive loads
Applying a test voltage to an installation without prior preparation systematically distorts the result and exposes the equipment to serious damage. When loads remain connected to the network during the test, the megohmmeter no longer tests the dielectric resistance of the cable's own insulation, but includes the internal impedances of the appliances, their filter circuits or their power supply modules. A toroidal transformer, an electronic control board, a light dimmer or an LED luminaire often presents a low apparent impedance or a leakage path to earth. The displayed result then falls below the regulatory acceptance threshold, simulating an insulation fault on a cable that is in fact flawless.
Beyond the false reading, applying a high DC voltage frequently destroys semiconductor components not designed to withstand such a dielectric potential. Built-in surge protective devices, rectifier diodes, class X or Y interference-suppression capacitors and switched-mode power supply units are the first in line. The preparation protocol therefore requires isolating the switchboard, opening the main overcurrent protective device and the sub-circuit breakers, then physically separating the loads connected to the section under test.
- Physical disconnection of the plugs of portable appliances from the final socket outlets of type 13 or type 23.
- Tripping or removal of the cartridges of the surge protective devices (SPD) present in the distribution boards.
- Disconnection of rotary dimmers, modular timers and electronic power supply units.
- Isolation of lighting circuits fitted with electronic ballasts or fixed, non-removable LED luminaires.
- Opening of the neutral disconnect links to clearly separate the neutral conductor from the protective earth.
Selecting the DC test voltage and acceptance criteria
The NIBT precisely defines the electrical values to be applied during initial and periodic verifications. Insulation resistance is measured exclusively with an instrument supplying a DC test voltage, capable of delivering a current of at least 1 mA under the prescribed nominal load. Using direct current eliminates the intrinsic capacitive effect of long electrical cables, which would distort an AC measurement by creating continuous capacitive leakage currents.
| Circuit voltage range | Rated circuit voltage | DC test voltage | Minimum insulation resistance |
|---|---|---|---|
| Extra-low voltage (SELV / PELV) | Up to 50 V | 250 V DC | ≥ 0.5 MΩ |
| Functional extra-low voltage (FELV) | Up to 500 V | 500 V DC | ≥ 1.0 MΩ |
| Standard low voltage (buildings) | From 50 V to 500 V | 500 V DC | ≥ 1.0 MΩ |
| Higher-voltage circuits | Above 500 V | 1000 V DC | ≥ 1.0 MΩ |
For usual indoor installations at 230/400 V, the minimum insulation value required by the NIBT is set at 1.0 MΩ at 500 V DC. The measurement must be taken successively between each pair of live conductors (phases and disconnected neutral), as well as between all the live conductors together and the protective conductor PE connected to earth. However, in refurbishment situations or on complex feeders where complete disconnection of the electronic devices is technically impossible without destructive dismantling, the NIBT allows a derogation procedure.
- Temporary equipotential bonding of the live conductorsElectrically connect together all the phase conductors (L1, L2, L3) and the neutral conductor (N) at the start of the circuit disconnected from the supply.
- Setting the test voltage to 250 V DCLower the test voltage of the installation tester to 250 volts DC to avoid dielectric breakdown of the varistors and filter components connected between phases and neutral.
- Overall measurement to the protective conductorApply the voltage between the bridge of the bonded live conductors and the protective conductor (PE). The minimum measured resistance must remain greater than or equal to 1.0 MΩ to confirm compliance of the section.
On-site test method: disconnection protocol and sequencing
Applying a DC voltage of 500 V without having prepared the feeder beforehand inevitably leads to two major pitfalls: irreparable destruction of electronic components or a value close to zero ohms that masks the true condition of the conductors. Insulation measurement according to the NIBT requires absolute galvanic separation of the installation from the supply network and from the connected appliances. A check for absence of voltage on the live conductors (L1, L2, L3, N) must always precede the opening of the neutral disconnect link. Leaving the neutral connected to the main collector brings back, by return path, the distribution network or the loads of neighbouring feeders, invalidating the insulation measurement of the neutral conductor to earth.
- Isolation and upstream separationTripping of the assigned protective device, locking out by padlock, verification of absence of voltage and systematic opening of the neutral disconnect link dedicated to the group of feeders being tested.
- Neutralising the surge protectionRemoval of the surge arrester cartridges (type 2 SPDs or combined type 1+2), disconnection of frequency converters, LED power supply units and fixed electronic timers connected to the board.
- Physical disconnection of the final loadsRemoval of the plugs from all final socket outlets and mechanical disconnection of fixed loads that cannot be bridged, such as room thermostats, local controllers and luminaires with electronic ballasts.
- Applying the calibrated DC voltageConnection of the test instrument between the bonded or separate live conductors and the protective conductor (PE). Application of the DC test voltage for a stabilised cycle of at least 60 seconds.
| Type of circuit tested | DC test voltage | Handling of loads | NIBT minimum value |
|---|---|---|---|
| SELV and PELV circuit up to 50 V | 250 V DC | Electronic modules must be disconnected | ≥ 0.5 MΩ |
| Low-voltage circuit up to 500 V (sockets, lighting, power) | 500 V DC | Physical disconnection or L and N bridged to PE | ≥ 1.0 MΩ |
| Low-voltage circuit above 500 V | 1000 V DC | Complete disconnection of all loads | ≥ 1.0 MΩ |
| Circuit with built-in, non-removable surge arresters | 250 V DC | Surge arresters connected, live conductors shunted | ≥ 1.0 MΩ |
Analysis of insulation deterioration, fault location and recording
A measurement showing a few kilohms or a value below the regulatory megohm does not necessarily indicate a damaged cable. If loads have remained connected along the run, the test loop inevitably closes through transformer windings, heating resistors or interference-suppression filters. In a new installation in KRMR conduit or TT cable, the expected insulation resistance is typically above 100 MΩ, regularly reaching the display limit of the measuring instruments (> 999 MΩ). A measured value fluctuating between 1.0 MΩ and 5 MΩ on a new feeder must immediately alert the team leader: it often indicates residual moisture in a flush-mounted junction box, ingress of pulling water in a duct or the onset of mechanical damage to the insulation of a conductor pinched against a metal frame.
In the event of confirmed non-compliance below the 1.0 MΩ threshold, the fault is located by methodical bisection along the cable run. The electrician opens the intermediate junction boxes to split the circuit into independent sub-sections, repeating the insulation test between phases, neutral and earth on each isolated section. Once the fault has been eliminated, all the raw measured values are recorded in the test report attached to the installation file. These results are the essential technical supporting document for issuing the safety report (RaSi) provided for by the OIBT, guaranteeing, before any final commissioning, that the installation presents no risk of electric shock or fire of electrical origin.
Procedure for rectifying an insulation fault
When a feeder measured at DC test voltage shows a resistance below the minimum value set by the NIBT, the team immediately freezes the board. A non-compliant value indicates critical degradation of the dielectric, ingress of mixing water into a conduit, a conductor crushed during pulling, or an electronic load inadvertently left connected.
- Isolating the section concernedOpen the overcurrent protective devices and disconnect the neutral conductor at the disconnect link. Measure the live conductors separately against each other, then each live conductor against the protective conductor. The test shows whether the leakage is on the phase-neutral connection or is a clear insulation breakdown to earth.
- Ruling out the equipmentPhysically disconnect the final appliances, the type 2 surge arresters and the dimmers still connected. Repeat the measurement at 500 V DC on the fixed wiring alone. If the resistance rises above the 1 megohm threshold, the fault comes from a load or a surge protective device that remained connected.
- Physically splitting the lineIf the fixed wiring is still faulty, open the line at the intermediate junction boxes to test each segment. This methodical search narrows the damaged conductor down to between two access points, avoiding the complete, blind replacement of the embedded cable run.
Where the damage results from mechanical deterioration caused by another trade on the construction site — a plasterboard screw passing through a conduit or drilling of a slab — the installer immediately draws up a joint technical report. Under art. 365 CO, they inform the client that this circumstance jeopardises the work. The damaged conductors must be removed and new ones pulled into the original conduit. The NIBT strictly prohibits inaccessible connections concealed in masonry.
No final circuit showing an insulation measurement below 1 megohm may be put into permanent service. Complete rectification of the section must necessarily precede the drawing up of the safety report required by the OIBT and the official handover of the installation to the owner.
Frequently asked questions
Why must insulation measurement always be carried out with direct current?
Using a DC test voltage makes it possible to disregard the capacitance per unit length inherent to installation cables. Under an AC voltage, the parasitic capacitance between the conductors and earth would generate a continuous capacitive current that would completely distort the reading of the pure resistance. Direct current briefly charges this natural capacitance of the circuit at the start of the test, then allows the instrument to measure exclusively the true resistive leakage current of the dielectric.
What are the risks of measuring a circuit without disconnecting the electronic appliances?
Applying a test voltage of 500 V DC to a circuit where electronic loads remain has two direct consequences. On the one hand, sensitive components such as motherboards, dimmers or switched-mode power supplies risk irreversible destructive breakdown. On the other hand, the presence of interference-suppression filters or surge-limiting varistors diverts the test current to earth, displaying a false insulation measurement close to zero ohms even though the fixed cable run is sound.
Which test voltage should be chosen to check a circuit supplying non-removable surge protective devices?
Where surge protective devices or surge arresters cannot be disconnected without complex dismantling of the installation, the NIBT allows the test voltage to be reduced to 250 V DC. This voltage, below the varistors' triggering threshold, avoids their destruction as well as parasitic leakage to the earth conductor. In this specific derogation configuration, the minimum insulation resistance required remains set at 1 megohm to certify the compliance of the cable run.
Why must the neutral conductor always be disconnected during the measurement?
In a TN-C-S earthing system, usual in Switzerland, the neutral conductor is connected to earth at the separation point located in the service entrance box or the main board. Leaving the neutral connected to the terminal bar creates an unintentional earthing of the measurement. Testing the insulation of a live conductor against the neutral, or testing the neutral itself, would systematically give a zero value, masking the true condition of the insulation.
Texts and standards cited
- CO art. 365materials and land: the contractor is responsible for the good quality of the materials he supplies; if the materials supplied by the client or the land designated by him are found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).