🧱 CFC 232Earthing, equipotential bonding and lightning protectionChapter 4 of 10 in the section

Supplementary equipotential bonding: bathrooms and special locations

In a wet room, the lowering of the human body's resistance caused by water makes the risk of electric shock critical. This chapter details how to carry out local supplementary equipotential bonding: the rigorous sorting of conductive elements from isolated bodies, the sizing of protective conductors, the clamping rules on pipework and the continuity measurement method required before acceptance.

Key takeaways

  • Local bonding compensates for general earth faults to prevent any dangerous potential difference.
  • Bond only the metallic pipes entering the room, fixed conductive casings and accessible metal structures of the room.
  • Install a minimum cross-section of 2.5 square millimetres in conduit or 4 square millimetres uncovered.
  • Measure continuity with a current of at least 200 milliamperes to validate each metallic connection.

Identify extraneous conductive parts and size the conductors according to the NIBT

Main equipotential bonding, established at the building entry on the earth bar, is not enough to eliminate the risk of electrical accidents in rooms containing a bath or a shower. When the skin is wet or immersed, the electrical resistance of the human body drops critically. A minimal potential difference between two metallic elements within arm's reach then causes serious physiopathological effects. If a stray voltage is carried by a metallic pipe from another floor, or if an insulation fault occurs on a class I appliance, local supplementary equipotential bonding comes into play. It keeps all accessible conductive parts at the same electrical level, neutralising the touch voltage. The NIBT prescribes this supplementary bonding to interconnect the exposed conductive parts of fixed electrical equipment and the extraneous conductive elements.

  • Metallic hot and cold domestic water supply pipes entering the room.
  • Metallic central heating pipes and gas or fuel oil lines where applicable.
  • Metallic wastewater drainage pipes if they offer usable electrical continuity.
  • Metallic baths and shower trays when they are in contact with the masonry structure.
  • Metallic reinforcement of the building structure if it is accessible and capable of propagating a potential.

The installation electrician must analyse the make-up of the sanitary networks. The widespread use of plastic pipes, such as cross-linked polyethylene or multilayer pipes, changes the bonding obligation. A tap fitted on a distribution made of plastic pipes is not an extraneous conductive element capable of propagating a potential. Earthing such equipment is pointless and may even introduce a stray voltage. Only continuous metallic pipes, coming from outside the room or passing through the slab, are conductive elements that must be connected to the local network.

Minimum cross-sections of supplementary equipotential bonding conductors
Installation configurationMinimum copper cross-sectionRecommended installation method
Mechanically protected conductor2.5 mm²In corrugated conduit or rigid recessed tube
Conductor not mechanically protected4 mm²Direct surface fixing on walls or bases
Connection between equipment exposed conductive partsCross-section of the smallest PEIn sheath with the supply circuit

Make the physical connections and validate continuity by measurement

  1. Prepare the contact surfacesThoroughly clean the surface of the pipe or metal part with sandpaper to remove any trace of varnish, paint or oxidation before positioning the earthing clamps or collars.
  2. Fit the clamps and fittingsTighten the equipotential clamps in tinned brass or stainless steel to the appropriate torque. Avoid destructive galvanic couples between copper and galvanised steel by using suitable interfaces.
  3. Run and interconnect the conductorsRoute the green-yellow copper conductors of 2.5 or 4 square millimetres to the local junction box or the dedicated earth bar, without creating unnecessary inductive loops.
  4. Carry out the electrical continuity measurementConnect the installation test instrument between each bonded element and the local earth terminal, injecting a direct current of at least 200 milliamperes with automatic polarity reversal.

Instrumental verification of local supplementary equipotential bonding is inseparable from its installation. The electrician uses an installation tester measuring low resistances according to the requirements of the NIBT. The procedure requires compensating for the resistance of the test leads to make the result reliable. The resistance measured between the protective conductor of the room and each bonded metallic element must be less than or equal to 0.2 ohm. A higher value indicates an execution defect: a poorly tightened clamp, an insulating sealing film on a fitting or a poor terminal contact.

Continuity measurements must be recorded in the company's test reports before the safety report required by the OIBT is drawn up. In the event of non-conformity, the electrician corrects the tightening or inserts an additional bridging link between pipe segments. The durability of the mechanical contacts guarantees protection against touch voltages in a wet environment. The conductors must remain accessible for periodic inspections, protected against screed moisture and free from any mechanical tension.

Conductive elements to be bonded and cases of exemption according to the NIBT

In a bathroom or shower room, the simultaneous presence of water, humidity and an unclothed human body greatly lowers the electrical resistance of the skin. In this critical environment, the automatic disconnection of supply provided by circuit breakers and upstream overcurrent protective devices is not always enough to remove the risk of electric shock through voltage transfer. The technical function of local supplementary equipotential bonding is to instantly cancel any potential difference between the accessible metallic parts and the protective conductors of the electrical circuits supplying the room. This local mesh protects the user against dangerous touch voltages imported from other parts of the building or generated by an internal insulation fault.

The installation electrician must rigorously identify the exposed conductive parts and extraneous conductive parts entering the volumes of the wet room. According to the NIBT, the following fixed metallic elements capable of introducing an electrical potential must be connected to the supplementary equipotential bonding: metallic cold water, domestic hot water, circulation and central heating pipes, steel or cast-iron heating bodies, and metallic wastewater drainage pipes. If reinforced concrete reinforcement is exposed or if metallic door frames are in direct contact with the conductive framework of the building, their inclusion in the local bonding is also required to guarantee absolute equipotentiality of the touchable surfaces.

Criteria for subjecting wet-room components to supplementary bonding
Element encounteredNature of upstream connectionLocal bonding obligationNIBT technical justification
Sanitary manifoldCopper pipe distributionMandatoryExtraneous conductive part that can propagate a fault potential.
Sanitary manifoldComposite/plastic riserNot requiredElement isolated from the structure, no external potential propagated.
Class I heated towel railTwin-pipe copper supplyMandatoryContinuity between the appliance's exposed conductive part and the metallic pipe.
Metallic bathPlastic pipework and PVC trapExcludedIsolated component with no direct contact with the building structure.
Metal frame of dry partitionMechanical fixing isolated from the structural workNot requiredInsulation resistance to earth higher than the conduction thresholds.

Sizing, routing and metrological verification of continuity

The sizing of supplementary equipotential bonding conductors follows strict rules of mechanical strength and thermal withstand. The copper conductor must have a minimum cross-section of 4 mm² when installed uncovered or fixed directly to the walls without additional mechanical protection. If the green-yellow conductor is run in KRMT conduit or thermoplastic recessed tube providing continuous physical protection against impact and crushing, the minimum permissible cross-section drops to 2.5 mm². When it connects the exposed conductive parts of two separate appliances, its cross-section must never be less than that of the smallest protective conductor associated with the supply circuits of those parts.

The physical connection of metallic pipes is made using earthing clamps in tinned copper strip or solid brass, previously cleaned mechanically with fine sandpaper to remove any trace of oxidation, varnish or insulating paint. The bonds are routed in a star configuration or as a continuous loop to a junction box fitted with a disconnecting link or a specific earth terminal block, easily accessible for the periodic inspections prescribed by the ordinance on low-voltage installations. This local terminal block is itself connected directly to the main protective conductor of the sub-distribution board of the flat or house.

  1. Preparing the test instrumentSwitch on the multifunction installation test instrument. Select the low-impedance continuity measurement function. Connect the test leads fitted with probes or crocodile clips and first compensate for the resistance of the test leads (zero calibration).
  2. Injecting the standardised test currentApply one end of the test lead to the protective conductor of the sub-distribution board or to the local disconnecting link, then the other probe to the connected metallic part. The instrument injects a test current of at least 200 mA at an open-circuit direct voltage between 4 and 24 V.
  3. Validating the measured resistance and recording itCheck that the resistance read on the measuring bridge remains strictly below the limit threshold calculated according to the NIBT, usually set at less than 0.2 ohm for short conductors in dwellings. Immediately enter the measured value in the test record for the drawing up of the safety report.

Handling continuity non-conformities and acceptance disputes

During the final inspection before handover of the installation, measuring the continuity of local supplementary equipotential bonding with a minimum current of 200 mA frequently reveals loop anomalies. A measured value exceeding the permissible threshold indicates a break in conduction or an excessive contact impedance. On wet-room construction sites, this failure almost systematically comes from insulating sealing fittings made up with hemp or PTFE tape, from recessed pipe sections in multilayer synthetic materials inserted between two copper segments, or from faulty tightening of earthing clamps on painted pipes.

  1. Locating the point of isolationMethodically isolate each metallic section using fine-tipped probes to identify the non-conductive fitting. Taps connected by braided flexible hoses do not guarantee any reliable continuity and must be checked directly on the brass body.
  2. Correcting the physical contactRemove the clamp, strip the varnish or oxidation layer down to bare metal, then refit the clamp with a mechanical tightening torque that avoids crushing the pipe. If general hydraulic continuity is interrupted by a plastic manifold, bridge each metallic outlet.
  3. Connection and metrological traceabilityReplace any damaged conductor, observing the minimum cross-section prescribed by the NIBT, i.e. 2.5 mm² in conduit or 4 mm² uncovered. Repeat the continuity measurement and record the value in ohms in the measurement record appended to the safety report.

Where the discontinuity results from construction choices imposed by another trade — for example the installation of a sealed-in metallic shower tray without an accessible connection tab, or the unplanned replacement of risers with polyethylene —, the installation electrician cannot validate safety without adaptation. Under art. 365 CO, if a circumstance compromises the proper execution of the work, the contractor immediately informs the client. This written notification relieves the installer of responsibility regarding the requirements of the NIBT and requires site management to order the local bonding to be brought into compliance.

Frequently asked questions

Must an acrylic or synthetic bath be connected to the supplementary equipotential bonding?

A bath made entirely of synthetic material (acrylic, resin, fibreglass) is an insulating body and is not an extraneous conductive part under the NIBT. It must therefore not be connected. However, if the bath incorporates a continuous metallic support frame resting on the structural work or has an electric whirlpool system, this frame or the motor casing must be connected to the corresponding protective conductor.

What is the maximum resistance value tolerated during the continuity measurement?

The NIBT does not impose a single numerical value for supplementary bonding, but the resistance measured between two simultaneously accessible conductive elements must not generate a dangerous touch voltage. In inspection practice on construction sites in French-speaking Switzerland, a continuity resistance of less than 1 ohm, measured with a current of at least 200 mA, is required to guarantee a clear metallic contact and validate the bonding on the final inspection record.

Do multilayer domestic water pipes require equipotential bonding in the wet room?

No, composite multilayer pipes with an aluminium core and inner and outer polyethylene layers are considered insulating. Their crimped fittings do not guarantee any continuous longitudinal electrical connection. Connecting an insulated coupling or a valve on a multilayer network is pointless and prohibited by the NIBT rules, because it brings no dangerous external potential into the room and would risk propagating a fault potential.

Can the PE conductor of a socket circuit be used to make the supplementary bonding?

Yes, the NIBT allows extraneous conductive parts to be interconnected with the protective conductor of a final circuit serving the wet room, directly in a local junction box or at the sub-distribution board. However, the dedicated supplementary equipotential bonding conductor must comply with the required minimum mechanical cross-section: at least 2.5 mm² copper if installed in protective tube, or 4 mm² copper if installed without direct mechanical protection.

Texts and standards cited

  • CO art. 365material and ground: the contractor is liable for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he must immediately inform the client, failing which he bears the consequences (para. 3)