🧱 CFC 232Schematics, sizing and circuit protectionChapter 9 of 10 in the section

EV charging point: available power, load management and dedicated circuit

Installing an EV charging point changes the electrical balance of a building by imposing a maximum rated current continuously for many hours. By the end of this chapter, you will be able to size the dedicated cable, specify the residual current protection specific to DC currents, deploy a dynamic load management system and carry out the connection notification required by the network operator.

Key takeaways

  • Continuous charging of a vehicle imposes a unity diversity factor on the dedicated feeder.
  • Residual current protection requires a device sensitive to smooth DC residual current above six milliamperes.
  • Dynamic management modulates the available current to protect the main overcurrent protective devices of the existing building.
  • The installation notice must be submitted to the network operator before connection.

Sizing of the dedicated circuit and switching devices under permanent load

The supply of an EV charging station tolerates no diversity factor. Unlike ordinary household appliances, whose thermal cycle varies, mode 3 charging loads the line at its maximum rated current without interruption over a period of several hours. According to the NIBT, each charging point must be supplied by a dedicated final circuit, individually protected against overcurrents and fault currents. The installation electrician sizes the conductor cross-section so as to rule out the risk of thermal degradation of the insulation and keeps the voltage drop below three per cent between the origin of the installation and the charging point.

Connection parameters of final circuits for AC charging points according to the NIBT
Charging powerRated voltageOvercurrent protective device ratingMinimum copper cross-sectionResidual current protection
3.7 kW (16 A single-phase)230 V single-phase16 A circuit breaker, curve C3 x 2.5 mm²RCD Type A + RDC-DD 6 mA DC or Type B
11 kW (16 A three-phase)400 V three-phase16 A circuit breaker, curve C5 x 2.5 mm² (5 x 6 mm² if l > 25 m)RCD Type A + RDC-DD 6 mA DC or Type B
22 kW (32 A three-phase)400 V three-phase32 A circuit breaker, curve C5 x 6 mm² (5 x 10 mm² if l > 30 m)RCD Type A + RDC-DD 6 mA DC or Type B

The critical phenomenon specific to EV charging is the potential occurrence of smooth DC components in the event of an insulation fault in the on-board charger. A DC leakage current above six milliamperes saturates the magnetic core of a standard Type A residual current device, neutralising its ability to trip on AC faults. To comply with the NIBT, protection must be provided either by a Type B residual current device, or by a Type A residual current device combined with a DC fault detection device (RDC-DD 6 mA DC), whether this module is integrated in the electronics of the charging point or added in the distribution board.

Dynamic load management and coordination with the network operator

In most older residential buildings, the service entrance has a limited rated current, generally between 25 and 40 amperes per phase at the main house overcurrent protective device. Simultaneous switching on of an 11 kW (16 A) or 22 kW (32 A) charging point, an electric cooker and a water heater exposes the service line to an immediate overload with blowing of the service fuses. Installing a load shedding device or dynamic power control avoids disproportionate costs for reinforcing the network and preserves the continuity of supply of the internal installations.

  1. Measurement of the instantaneous current at the head of the installationPosition split-core current transformers (toroids) directly downstream of the building's main overcurrent protective device to measure in real time the overall consumption phase by phase.
  2. Setting the load shedding set pointConfigure the management controller or the master charging point by entering the maximum permissible value of the main overcurrent protective device, less a safety margin of ten per cent.
  3. Communication and modulation of the charging currentConnect the shielded bus link between the measuring module and the charging point to control the vehicle's PWM set-point current according to the available power reserve.
  4. Checking response timesTest the immediate drop of the charging current when a purely resistive load equivalent to large household appliances on the sub-distribution board is switched on.

Any connection of an EV charging device is subject to strict formalities towards the local distribution network operator (DNO). The requirements of the Romandy network operators impose the submission of an installation notice before the work as soon as the power of the device exceeds 3.7 kW. For charging points with a power above 11 kW, a prior technical connection authorisation request is systematically required to verify the capacity of the neighbourhood's low-voltage distribution network. The operator may make its authorisation subject to the obligation to lock the charging during daily peaks or to integrate a ripple control receiver.

Specific residual current protection and thermal constraints in the board

Adding an EV charging point radically changes the thermal balance and the fault regime of a main distribution board. Unlike ordinary household appliances which operate in intermittent cycles, charging a vehicle imposes a sustained current of 16 A or 32 A continuously for several consecutive hours. According to the NIBT requirements, the diversity factor and the load factor assigned to this line are set at 1. This severe thermal constraint requires the installation electrician to recalculate the Joule losses inside the enclosure and to prohibit crowding modular devices together without ventilation space.

Selection matrix of protective devices according to the type of charging infrastructure
Charging modeRated currentProtective circuit breakerResidual current device (RCD)Minimum copper cross-section
Single-phase 3.7 kW16 A continuousThermal-magnetic circuit breaker 16 A, curve CType A combined with RDC-DD 6 mA DC (or Type B)3 x 2.5 mm² (if routed without derating)
Single-phase 7.4 kW32 A continuousThermal-magnetic circuit breaker 32 A, curve CType A combined with RDC-DD 6 mA DC (or Type B)3 x 6 mm² (or 3 x 10 mm² depending on voltage drop)
Three-phase 11 kW3 x 16 A continuousThermal-magnetic circuit breaker 3P+N 16 A, curve CType B 30 mA or Type EV (Type A + RDC-DD 6 mA DC)5 x 2.5 mm² (5 x 4 mm² recommended thermally)
Three-phase 22 kW3 x 32 A continuousThermal-magnetic circuit breaker 3P+N 32 A, curve CType B 30 mA 4-pole, independent5 x 6 mm² (5 x 10 mm² recommended when flush-mounted)

Beyond the line itself, adding an 11 kW or 22 kW feeder in an existing cabinet requires a rigorous check of upstream selectivity. The fuse links of the subscriber's main overcurrent protective device (often rated 25 A, 40 A or 63 A in residential buildings) cannot always absorb the charging load without premature tripping of the main protection when other large thermal loads are switched on at the same time.

Dynamic load management, load shedding and procedures with the network operator

To avoid costly reinforcement of the main service entrance or replacement of the underground supply cable, implementing dynamic load management is the standard technical solution. This system relies on installing current transformers (measuring toroids) or an energy meter connected at the head of the installation, directly downstream of the distribution network operator's (DNO) meter. The load shedding controller continuously measures the current flowing through each phase of the main service entrance.

  1. Reading of the overall instantaneous currentThe management module scans the three phases at the head of the distribution. It subtracts the building's consumption from the maximum power subscribed with the DNO in order to define the residual power that can be allocated to the vehicle.
  2. Transmission of the set-point signalThe controller dynamically adjusts the maximum permitted current set point transmitted to the charging point via an industrial wired link. Modulation takes place in real time with a response time of less than one second.
  3. Preventive physical load sheddingIn the event of an unforeseen demand peak (simultaneous start-up of several powerful household appliances), the system immediately reduces the charging current of the charging point or temporarily suspends the session before the fuse of the main overcurrent protective device enters its thermal melting zone.

Any charging point exceeding a rated power of 3.6 kVA is subject to a prior notification obligation to the local energy distributor. The installation electrician holding the general installation authorisation submits the official Installation Notice (AI) form before the cables are pulled. The DNO assesses whether the local supply network can bear the unbalanced load or the overall peak, and may impose switch-on limitations or a dry contact for tariff blocking during peak demand hours.

If the sizing of the existing service entrance proves manifestly insufficient to support the charging point despite any dynamic control, art. 365 CO requires the installer to warn the client before proceeding with the connection, failing which the installer assumes liability for recurring faults.

Handling non-conformities, network blocks and thermal overloads

Tripping of the main overcurrent protective device or excessive heating of the main board after a charging point has been added almost always results from an underestimation of the continuous load. Unlike ordinary household appliances which are switched on intermittently, charging a vehicle imposes a permanent load factor of 1.0 over several consecutive hours. At the first thermal incident or nuisance tripping, the operator and the installer must take the installation out of service to eliminate any risk of irreversible damage to the busbars and the conductor insulation.

  1. Thermal diagnosis and checking of trippingMeasure the load of each phase with a clamp ammeter while simulating a complete charging cycle. Check the mechanical tightness of the terminals under maximum load with a thermal camera: localised heating indicates an abnormal contact resistance on the overcurrent protective device or the dedicated switchgear.
  2. Resolving network operator restrictionsIf the operator rejects the installation notice because the capacity of the service entrance enclosure is exceeded, implement a dynamic management module measuring the total current at the head of the installation. Automated limiting or load shedding of the charging point makes it possible to comply with the limits imposed by the operator without paying for a costly connection reinforcement.
  3. Correcting insulation faults and DC blindingIf an upstream residual current device trips, isolate the DC residual component. A DC leakage current above 6 mA saturates the core of a Type A RCD. A dedicated device with compliant DC detection must be inserted, or the device must be replaced with a Type B residual current device.

When the existing infrastructure is unable to absorb the subscribed power and the owner refuses the refurbishment of the distribution board, the installer applies the professional rules of diligence. According to art. 365 CO, if another circumstance compromises the proper or timely execution of the work, the contractor informs the client. The charging point must then be physically limited via its internal controller to a safe current value, before carrying out the final insulation measurements and drawing up the official safety report.

Frequently asked questions

Why is a Type A residual current circuit breaker insufficient for connecting an EV charging point?

The on-board chargers of electric vehicles generate leakage currents with a DC component when rectifying the alternating current. If a DC leakage exceeds 6 mA, it saturates the magnetic core of a standard Type A residual current device, making it completely blind to subsequent AC faults. The NIBT therefore requires either the installation of a Type B residual current device, or a 6 mA DC detection device combined with a Type A.

When does notification to the distribution network operator become mandatory?

Every charging point is a fixed consumer requiring an installation notice submitted to the network operator before the work. In Switzerland, the operators' requirements call for prior authorisation as soon as a charging point exceeds a defined power, commonly 3.7 kW single-phase or 11 kW three-phase. This procedure allows the operator to analyse the network capacity and to impose a dynamic load shedding system to protect the neighbourhood transformer.

How does dynamic load management work in practice in an existing building?

Measuring toroids or a communicating meter continuously record the total current at the main overcurrent protective device. The control compares this instantaneous value with the maximum permissible current of the service entrance. When priority consumers switch on, the controller modulates the current set point transmitted to the charging point. The charging power decreases or stops without cutting the line, preventing the main rating from being exceeded and ensuring continuity of supply in the building.

Can a charging point be connected to an existing circuit supplying other sockets?

No. According to the NIBT rules, each EV charging point must be supplied by its own dedicated final circuit. No other appliance, lighting or socket may be connected to it. This requirement prevents continuous heating of the existing junction boxes and ensures suitable overcurrent protection, thereby providing safe insulation of the vehicle without affecting the rest of the electrical infrastructure.

Texts and standards cited

  • CO art. 365materials and ground: contractor's responsibility and duty to inform the client if a circumstance compromises the proper or timely execution of the work (para. 3)