Key takeaways
- The overall power balance determines the sizing of the service cable and of the building's main overcurrent protective devices.
- Diversity avoids unnecessary oversizing but must preserve the peak consumption of fixed loads.
- Dynamic load management makes it possible to install several charging stations without saturating the overall authorised contracted capacity.
- Submitting the application early to the distribution network operator prevents delays linked to reinforcements of the public network.
Assessing the connection capacity: diversity and impact of charging stations
The sizing of the connection capacity of a new or converted building directly determines the cross-section of the service cable, the rating of the building's main overcurrent protective devices and the upstream infrastructure of the distribution network operator. The electrical installer draws up the power balance by adding up the installed rated powers, then applying the simultaneity and diversity factors accepted by the rules of the art and the NIBT. Neglecting diversity leads to prohibitive oversizing of the switching equipment and of the connection fees. Conversely, underestimating load demands exposes the installation to nuisance tripping of the service circuit breaker or to abnormal voltage drops on the main feeders.
| Type of load | Usual simultaneity factor | Impact on overall sizing |
|---|---|---|
| Standard residential apartments | 0.3 to 0.5 depending on the number of units | Applied to cooking circuits, sockets and domestic appliances. |
| Collective heat pump | 0.8 to 1.0 (winter operation) | Inrush current at start-up must be taken into account. |
| Charging stations without regulation | 1.0 (long-duration continuous charging) | Massive oversizing of the connection required. |
| Stations with dynamic management | 0.2 to 0.4 depending on the overall setpoint | Strict capping of the current drawn upstream. |
The integration of charging stations for electric vehicles fundamentally changes this traditional calculation. Unlike household appliances, which operate intermittently, a charging station can draw 11 kW or 22 kW continuously for several hours at full current. In an underground car park with twenty spaces, connecting stations without regulation would require an unrealistic power reserve on the local distribution network. The installer must therefore specify and implement dynamic load management. This system measures the overall consumption of the building in real time and allocates the residual power to the stations, ensuring that the overall demand never exceeds the rated value of the main overcurrent protective device.
Submitting the application to the distribution network operator and controlling administrative lead times
In accordance with the OIBT requirements, only holders of a general installation permit are authorised to submit the official notices to the distribution network operator. Processing a connection is divided into two distinct phases: the network connection application, submitted at the master plan stage, then the official installation notice before the start of the cable-pulling and connection work. Too often, these steps are relegated to the end of the finishing work phase. This tactical error blocks the installation of the meter and the energising of the building, forcing the construction site to needlessly extend a costly and limited temporary connection.
- Compiling the file and the power balanceGather all the technical data sheets of the major consumers, calculate the overall current required in amperes after diversity and define the planned route of the service cable.
- Submitting the network connection applicationSend the distribution network operator the official form, the site plan and the schematic diagram to obtain the technical connection conditions and the point of supply on the low-voltage network.
- Validating the conditions and connection agreementAnalyse the network operator's assessment. If the neighbourhood transformer or the underground line proves to be saturated, include the network reinforcement lead times in the overall works schedule.
- Submitting the installation notice and installing the meteringSubmit the formal installation notice before the works. Coordinate the opening of the trench, the pulling of the service cable, the delivery of the building's cabinet and the ordering of the metering unit.
The distribution network operator's processing time varies from three weeks for a simple increase in rating without roadworks to more than four months when a line extension or a modification of a substation is required. If the public distribution transformer reaches its thermal limit because of the requested contracted capacity, the distribution network operator must plan a replacement of the unit or a reinforcement of the underground network on public land. During this processing period, no permanent cable may be energised. The electrical installer is responsible for immediately comparing the needs of the building with the capacity available at the point of supply, in order to fix the contractual sizing from the time of the award.
Technical trade-off: dynamic load management and sizing of the overcurrent protective device
The massive integration of electromobility in residential or commercial buildings calls into question the traditional simultaneity calculations. Without regulation, the plain addition of rated powers leads to rated currents of the main overcurrent protective device that are incompatible with the capacity of the existing service cable. When several 11 kW or 22 kW stations are connected to the same distribution board, theoretical diversity is no longer enough to guarantee the absence of overload at peak hours. The implementation of a dynamic load management (DLM) system becomes the technical prerequisite imposed by the distribution network operator to authorise the installation without requiring the immediate replacement of the underground supply line.
| Configuration | Diversified power of dwellings | Power allocated to charging | Overcurrent protective device required | Consequence for the service connection |
|---|---|---|---|---|
| Without charging stations | 28 kW (diversity 0.4) | 0 kW | 63 A | Existing cable retained |
| 10 stations of 11 kW without management | 28 kW | 88 kW (diversity 0.8) | 200 A | Cable replacement and network reinforcement |
| 10 stations of 11 kW with dynamic management | 28 kW | 18 kW (modulated cap) | 80 A | Service connection retained or minor adaptation |
The dynamic management controller measures in real time the current flowing through the current transformers placed immediately after the main overcurrent protective device. When the building's priority uses — cooking, heating or ventilation — increase their power demand, the system reduces the current setpoint sent to the stations via the communication bus. Under the OIBT safety rules, this device must be backed up by an independent emergency cut-off and configured in a safe fallback mode (fail-safe): in the event of loss of signal with the stations, the total current delivered must immediately drop to the minimum value permitted by the selectivity calculation of the switchboard.
Distribution network operator lead time and coordination of the connection on the construction site
Obtaining the technical connection agreement from the distribution network operator (DNO) is one of the major bottlenecks of the finishing work. As soon as the balance of diversified powers is finalised, the official submission of the connection application and of the installation notice must be started. Between the analysis of the neighbourhood transformer by the operator's engineers, the short-circuit study and the formal validation of the technical connection conditions, processing times commonly range between eight and sixteen weeks. If the calculation shows saturation of the medium-voltage network or of the public low-voltage section, roadworks for reinforcement may push back the final connection by several months.
This scheduling constraint directly affects the management of live tests and the commissioning of the building's safety installations. According to art. 365 CO, if a circumstance jeopardises the proper or timely performance of the work, the contractor informs the client. The installer therefore reports in writing any extension of the network operator's lead times. The absence of permanent power blocks the issuing of the safety report required by the OIBT and delays the acceptance of the electrical work.
- Submitting the complete technical fileSubmission on the distribution network operator's portal: application form, schematic diagrams, power balances with diversity and the technical data sheet of the load management.
- Receiving the technical connection conditionsAnalysis of the distribution network operator's quote, confirmation of the point of supply, of the rating of the network overcurrent protective device and of the ripple control requirements.
- Coordinating the civil engineering and laying the conduitsCarrying out the private excavation in accordance with the DNO's directives, laying the standardised conduits and the service entrance cabinet at the property boundary.
- Pulling the cable and final energisingInstalling the service cable, connecting it to the terminals of the main overcurrent protective device, installing the metering by the DNO and final OIBT inspection.
Connection blockages and network delays: procedures and emergency measures
When the distribution network operator (DNO) announces a refusal of capacity or requires an unforeseen reinforcement of the upstream line, the construction site schedule is thrown off. The electrical installer finds himself on the front line facing a blocking situation: without an increase in the rating of the main overcurrent protective device, the tests of the technical installations, the permanent supply of the main switchboard and the commissioning of the charging infrastructure become impossible on the agreed date.
If the distribution network operator is slow to process the installation notice or to install the service entrance cabinet, the delay directly affects the delivery of the work. The contractor then applies the contractual rules of the Code of Obligations. In accordance with art. 102 CO, the debtor is put in default by a demand from the creditor, or by the mere expiry of the day where the day of performance has been determined by mutual agreement. The electrician immediately informs the client in writing of this external circumstance that jeopardises the timeliness of the work.
- Formal notification to the clientImmediately send a reasoned notice specifying the network constraints notified by the DNO, the impact on the phasing and the revised deadline.
- Technical negotiation of a transitional connectionAsk the distribution network operator for the temporary retention of the construction site cabinet or for a reduced contracted capacity dedicated solely to technical tests.
- Reconfiguring the dynamic load managementTemporarily set the controller managing the charging stations to a capped setpoint value, avoiding any exceeding of the existing capacity.
In the event of a financial deadlock over the cost of extending the network on public land, the electrician provides the client with the calculation note demonstrating the real diversity of the loads. This documented trade-off often makes it possible to reduce the requested rating without penalising final operation.
Frequently asked questions
How should one react if the DNO refuses the requested capacity for the charging stations?
The installer recalculates the power balance by integrating dynamic load management with strict real-time load shedding. This technical solution makes it possible to guarantee to the distribution network operator a power demand capped at the existing overcurrent protective device, even if several vehicles are plugged in simultaneously. An updated schematic diagram and a descriptive sheet of the load controller are then submitted in addition to the initial installation notice to obtain the formal authorisation.
Can the construction site meter be used to start the tests of the permanent installation?
The distribution network operator generally allows the temporary construction site connection to be kept for insulation checks, phase rotation tests and no-load tests of the loads. However, commercial operation of the installations or heavy loading of the stations remains prohibited until the permanent overcurrent protective device has been installed, sealed by the DNO and validated under the notification procedures prescribed by the OIBT.
What impact does photovoltaics have on the sizing of the main overcurrent protective device?
Photovoltaic generation does not increase the connection capacity required for night-time draw or draw in low sunlight: the main overcurrent protective device remains sized to cover the total contracted capacity drawn from the network. From the point of view of feed-in, the inverter on the other hand makes it necessary to check the thermal withstand of the service cable and the breaking capacity of the main disconnecting device in the case of feed-back to the distribution network.
Who bears the cost of a cable reinforcement on public land required by the distribution network operator?
The costs of reinforcing the upstream network up to the supply point are covered by a fixed-price quote or a connection contribution issued by the distribution network operator directly to the client, according to the local general conditions of distribution approved by the ElCom. The electrical installer does not bear these public infrastructure costs, but has a duty to warn the customer from the preliminary design phase to avoid any unforeseen budgetary blockage.
Texts and standards cited
- CO art. 102default of the debtor: the debtor is put in default by a demand from the creditor; by the mere expiry of the day where the day of performance has been determined by mutual agreement or fixed by a regular notice.