Key takeaways
- The permissible current dictates a minimum cross-section to prevent destructive heating of the insulation.
- The maximum permitted voltage drop dictates the required cross-section over long distances.
- The nominal cross-section selected for the installation must necessarily be the highest normative value.
- Each thermal or grouping correction factor reduces the current-carrying capacity of the conductors.
Determining the minimum cross-section according to permissible current and installation method
In a low-voltage installation, the first constraint follows directly from the rated load of the circuit and of the overcurrent protective device. The insulation of copper conductors (PVC or XLPE) must never exceed its maximum continuous operating temperature, set at 70 °C or 90 °C respectively by the recognised NIBT rules. The design current of the load determines the rated current of the overcurrent protective device, which must be less than or equal to the current-carrying capacity of the cable under actual installation conditions.
The thermal capacity of a cable run depends entirely on its immediate environment and on its ability to dissipate the heat generated by the Joule effect. Installation in conduit embedded in an insulating wall drastically limits heat transfer compared with a perforated cable tray in a technical basement. The installation electrician applies the NIBT reference tables to define the basic permissible current, before applying the essential correction factors.
- The standardised installation method: embedded under plaster, in corrugated conduit in concrete, in plastic trunking or on perforated cable tray.
- The actual ambient temperature: a reduction factor applies as soon as the temperature exceeds the standard value of 30 °C.
- Grouping of circuits: placing several cables side by side in a bundle or in the same conduit requires a derating of the permissible current.
- The type of insulation: cross-linked polyethylene tolerates a higher current density than polyvinyl chloride.
| Conductor cross-section | Installation in embedded conduit (A) | Surface installation on cable tray (A) | Typical protection rating |
|---|---|---|---|
| 1.5 mm² | 15.5 | 19.5 | 10 A / 13 A |
| 2.5 mm² | 21.0 | 26.0 | 16 A |
| 6.0 mm² | 37.0 | 46.0 | 32 A |
| 16.0 mm² | 68.0 | 85.0 | 63 A |
Balancing thermal constraint and voltage drop on long runs
As soon as a load is located far from the secondary distribution board, the thermal criterion often ceases to be the determining factor. The ohmic resistance of copper causes a voltage drop proportional to the length of the cable run and to the current carried. To ensure the correct operation of the loads and limit network losses, the NIBT recommends not exceeding a maximum voltage drop threshold between the origin of the installation and the point of use.
In practice, in commercial and residential installations, the design office or the installer distributes this margin: 1 % to 1.5 % between the service entrance box and the sub-distribution board, then 2.5 % to 3 % on the final circuit. For a single-phase 230 V outgoing circuit loaded at 16 A, a run of only 25 metres in 1.5 mm² already reaches the permissible limit. To cover 40 metres without excessive loss, oversizing the cross-section to 2.5 mm², or even 4 mm², becomes mandatory, even though the circuit breaker remains rated at 16 A.
- Calculating the minimum thermal cross-sectionDefine the rated current of the protective device and apply the installation coefficients to identify the theoretical cross-section needed to withstand heating.
- Calculating the expected voltage dropApply the single-phase or three-phase formula, taking into account the exact length of the route and the nominal operating current.
- Comparing and oversizingCompare the two results. The highest standardised nominal cross-section always prevails, to guarantee safety and compliance at the same time.
- Adapting the physical connectionIf the calculation requires 4 mm² to supply a standard 16 A final socket outlet, provide reducing terminal blocks or compatible quick connectors in the flush-mounting box.
Practical calculation of voltage drop and cross-section trade-off
In the field, the cross-section of a cable is never chosen solely on the basis of the rated current of the overcurrent protective device. The basic rule requires a systematic double check: the conductor must dissipate its heating without degrading its insulation (thermal criterion linked to the installation method) and guarantee a sufficient voltage level at the terminals of the load (voltage drop criterion linked to distance). As soon as the run extends beyond a few tens of metres, the voltage drop constraint almost systematically outweighs the thermal constraint.
For final lighting and general-purpose circuits, the NIBT sets strict limits on relative voltage drop to ensure the correct operation of the appliances and avoid excessive line losses. As a general rule, the aim is a drop of less than or equal to 3 % for lighting and 4 % to 5 % for other uses, from the main overcurrent protective devices to the points of use.
| Voltage / System | Rated protection | Calculated cross-section | Maximum permissible length |
|---|---|---|---|
| 230 V single-phase | 10 A | 1.5 mm² | 25 m |
| 230 V single-phase | 16 A | 2.5 mm² | 29 m |
| 400 V three-phase | 16 A | 2.5 mm² | 58 m |
| 400 V three-phase | 25 A | 4.0 mm² | 62 m |
| 400 V three-phase | 40 A | 10.0 mm² | 96 m |
If the voltage drop calculation reveals a loss exceeding the limit set by the NIBT for the actual length measured along the route (taking into account vertical risers and passages through technical shafts), the installation electrician must select the next larger cross-section in the standardised series, even if the permissible current linked to the installation method was amply satisfied by the original cross-section.
Effects of increasing the cross-section on the switchgear and the construction site
Increasing the cross-section because of line length also changes the phase-protective conductor fault loop resistance (L-PE). This parameter has a favourable effect on the overall impedance, but obliges the foreman to recalculate compliance of the automatic disconnection time according to the NIBT, verifying that the prospective short-circuit current at the furthest point operates the magnetic release of the circuit breaker within the allowed time.
- Rigorous measurement of the routeMeasure the actual path of the KRFWG or KRFMX conduits or of the cable trays, including pulling reserves, slab drops and minimum bending radii.
- Preliminary thermal checkIdentify the most unfavourable installation method along the whole route (for example a passage through mineral wool or a bundle grouped under screed) to determine the permissible cross-section Iz.
- Calculating the voltage drop Delta UApply the standard single-phase or three-phase formula with the actual design current or the nominal current In of the circuit breaker.
- Trade-off and mechanical validationSelect the larger cross-section obtained between the thermal and length criteria. Check the outer diameter of the cable for sizing the conduit and for compatibility with the connection terminals.
During the final checks and the drafting of the measurement record for the safety report (RSB) prescribed by the OIBT, the actual measurement of the loop impedance confirms the validity of the sizing selected on long outgoing circuits.
Voltage drop non-compliance: rework and construction site trade-off
On heavy-current installation construction sites, the sizing error often shows up late, during the final inspection before the safety report is drafted. An actual route longer than on the drawing, an unanticipated congestion in a cable tray requiring thermal derating, or a measured voltage drop outside tolerance are major defects within the meaning of the NIBT.
When the calculation or measurement shows an excessive voltage drop on a final connection or a distribution cable, the installation electrician must act rigorously. If the cable run is installed but not yet connected, replacing the cable with the next larger cross-section is the soundest technical solution to guarantee the durability of the work without altering upstream selectivity.
A contractor who finds a discrepancy in the setting-out or erroneous starting data supplied by the site management refers to the obligations of art. 365 CO. Under art. 365 CO, the contractor informs the client if a circumstance jeopardises the proper or timely execution of the work. This written communication formalises the consequences for the conductor cross-sections and the execution deadlines.
- Findings and recalculationRecord the exact length installed and measure the loop impedance. Recalculate the cumulative voltage drop from the point of entry to the final load according to the NIBT.
- Formal noticeNotify the site management in writing if the deviation results from a change of route imposed during the course of the construction site work.
- Technical trade-offAssess the feasibility of re-pulling a larger cable against the possibility of reducing the rated current of the upstream circuit breaker, if the actual load allows it.
- Adapting the connectionsIf the cross-section is increased, fit intermediate transition terminals if the terminal cages of the final switchgear do not accept the core of the new conductor.
Frequently asked questions
What should be done if a conductor oversized for voltage drop does not fit into the circuit breaker terminals?
It is prohibited to cut strands of the conductor core to force it under the terminal cage of a device. This practice degrades the thermal capacity at the clamping point and creates a hot spot. The electrician must install stepped feed-through terminals or a transition busbar in the distribution board, allowing the cross-section to be reduced over a few tens of centimetres up to the circuit breaker, in accordance with the NIBT installation rules.
How should one choose between increasing the cross-section and reducing the upstream protection current on a line that is too long?
The decision depends exclusively on the operating needs of the load. If the cable supplies a known fixed load whose nominal current remains clearly below the rating of the planned circuit breaker, lowering the protection value makes it possible to meet the permissible voltage drop without replacing the line. If the equipment requires the full power originally planned, replacing the cable with a larger cross-section remains the only trade-off compliant with the NIBT.
What voltage drop tolerance applies between the main overcurrent protective device and a socket outlet?
According to the NIBT rules, the overall permissible voltage drop between the origin of the low-voltage installation and the final use must not disturb the operation of the loads. The usual maximum permitted value is 4 % for final lighting and socket outlet circuits, taking into account the upstream distribution between the main board and the sub-distribution board. Any excess found during measurements requires immediate correction.
Does grouping conductors in a corrugated conduit affect the voltage drop?
Grouping several circuits in the same conduit mainly affects thermal heating and lowers the permissible current through the correction factors. This heating increases the linear resistance of the copper in service, which indirectly increases the actual voltage drop. The installer must therefore first check the thermal withstand linked to the installation method, then calculate the ohmic loss using the conductor resistance value under steady-state conditions.
Texts and standards cited
- CO art. 365materials and ground: the contractor is responsible for the good quality of the materials he supplies; if the materials supplied by the client or the ground designated by him are found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).
