🧱 CFC 232Installation: conduits, distribution boards and switchgearChapter 3 of 10 in the section

Fire-rated wall penetration: certified firestopping, marking and documentation

After this chapter, you will be able to select and install a firestopping system compliant with Swiss fire protection requirements. You will learn how to restore the fire resistance rating of a wall crossed by heavy-current cables, how to fit the mandatory identification plate and how to assemble the conformity certificates for the final as-built file.

Key takeaways

  • Standard polyurethane foam immediately destroys the thermal and fire-resistant sealing of the partition it passes through.
  • The approved firestopping system must match exactly the fire resistance rating of the wall.
  • Each sealed penetration must receive an indelible, numbered and dated metal or synthetic label.
  • The certificate of execution and the technical approval must be added to the revised drawings file.

Restoring fire-tightness in accordance with the recognised approval

Drilling through a wall or slab separating two fire compartments directly weakens the passive safety of the building. In heavy-current work, the passage of cable trays, bundles of conductors or rigid conduits creates a breach that favours the spread of toxic smoke and flames. Under the Swiss fire protection regulations of the VKF (AEAI) and the provisions of the NIBT, every penetration must be sealed to restore the full performance of the structural work.

Fire resistance rating of the wall
Standardised capacity of a building separation (load-bearing wall, lightweight partition or slab) to ensure mechanical resistance (R), tightness against flames and gases (E) and thermal insulation (I) for a defined duration in minutes (EI 30, EI 60, EI 90).

A common mistake is to fill the annular gap of a core-drilled hole with ordinary expanding foam from the retail trade. This highly combustible material degrades within seconds under the effect of heat, releases asphyxiating gases and ruins fire-tightness. Only a firestopping system approved by the VKF (AEAI) guarantees the insulation and integrity criteria. The electrical installer must choose a product compatible with the mineral substrate or dry-lining partition and suited to the fill ratio of the power cables.

Choice of firestopping systems according to the penetration configuration
Sealing technologyTypical area of applicationAchievable fire resistance ratingInstallation constraint
Intumescent sealant and stripsInsulated conduits, single penetration or small bundleEI 30 to EI 90Joint depth and mineral wool packing to be observed
Rock wool boards and ablative coatingLarge openings, heavy cable traysEI 60 to EI 90Complete coating of the cables over 150 to 250 mm
Intumescent bricks or cushionsModular penetrations, passages subject to changeEI 60 to EI 90Tight stacking under mechanical tension with no residual void
Certified two-component fire-resistant foamNarrow core-drilled holes, tight bundles with difficult accessEI 30 to EI 60Static mixer mandatory, very fast reaction time

Before applying the system, the installer cleans the core-drilled hole, removes dust from the plastic conduits and fits a suitable backing material for the joint. If the dimensions of the existing opening are incompatible with the requirements of the sealant or board manufacturer, art. 365 CO requires the tradesperson to notify site management if any circumstance compromises the durability of the work. Final conformity depends entirely on strict compliance with the manufacturer's installation details.

Label each penetration and record the approval evidence

Physically sealing the opening does not complete the electrician's job. An unidentified fire-rated penetration is immediately challenged during the acceptance inspections of the cantonal fire protection authority or the building control office. Labelling the penetration is the legal act certifying that the products used strictly comply with the scope of application validated by the VKF (AEAI).

  1. Visual and dimensional check of the sealingCheck the continuity of the intumescent joint, the absence of gaps between the power cables and the flatness of the mineral board coated on both sides of the wall.
  2. Filling in the identification plateWrite in indelible marker the VKF (AEAI) approval number, the fire resistance achieved (e.g. EI 60), the name of the installation company, the date and the installer's signature.
  3. Mechanical fixing of the labelRivet or screw the plate onto the load-bearing wall or the slab in the immediate vicinity of the opening, in a visible location protected from mechanical impact.
  4. Georeferenced photographPhotograph the finished penetration and its legible label so that the picture can be added to the building's technical register of fire seals.

The evidence in the as-built file comprises the installer's certificate of conformity, copies of the currently valid VKF (AEAI) approvals and the summary table of penetrations. These documents protect the company in the event of a later incident. Art. 229 CP punishes anyone who, in directing or carrying out a construction, intentionally or through negligence breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons. A defective seal directly engages the criminal liability of the person in charge of the construction site.

Installing certified systems and preserving the fire resistance rating

On heavy-current installation construction sites, the use of standard polyurethane expanding foam to fill technical openings is a serious fault. These assembly foams ignite quickly, release toxic smoke and destroy the integrity of the work within the first minutes of a fire. The fire compartmentation of the building, which prescribes a rating of EI 30, EI 60 or EI 90 depending on the fire protection concept, requires the thermal resistance and tightness of the wall that has been penetrated to be restored exactly. This performance is recognised only for a complete system, tested to recognised standards and covered by a certificate of use from the Association of Cantonal Building Insurers (VKF/AEAI). The NIBT also reminds installers of the obligation to maintain the integrity of walls against the spread of fire and smoke along electrical conduits. Any improvised sealing with ordinary mortar or plaster is prohibited.

The choice of solution depends on the substrate and the type of power cables. Solid concrete or masonry walls accept shrinkage-compensated fire-resistant mortars or rigid high-density mineral wool boards with an ablative coating that is tight against hot gases. Lightweight plasterboard partitions require certified metal intumescent collars or fire-resistant strips. In each case, the electrical installer observes the spacing between cables and the minimum peripheral clearance. For high-power cables, thermal expansion under rated load requires sealants that remain flexible after curing. Certified expanding foam, which must be two-component and registered with the VKF (AEAI), is restricted to small-diameter core-drilled holes for single cables, within a strictly defined wall thickness.

Selecting approved firestopping according to the wall
Wall and target ratingPower cables and conduitsVKF (AEAI)-certified systemApplication rules
Concrete wall or masonry (EI 90)Power cables on cable traysHigh-density rock wool boards (> 150 kg/m³) with ablative coatingCoating of cables and brackets over 20 cm on each side
Lightweight framed partition (EI 30 to EI 60)Rigid and corrugated halogen-free conduitsMetal collars or intumescent strips with fire-resistant sealantDirect fixing to the framing with no residual void
Concrete slab or technical floor (EI 90)Mixed penetration of power cables and conductorsFire-resistant mortar or re-enterable intumescent bricksSealing formwork and compliance with the permissible load
Core-drilled hole in solid wall (EI 60 to EI 90)Single supply cableIntumescent sealant or two-component foam approved by the VKF (AEAI)Guaranteed depth with mineral wool backing for the joint

On-site signage, responsibilities and compilation of the as-built file

The conformity of a penetration does not end when the materials have hardened. On the construction site, a penetration without an identification plate is an immediate non-conformity during inspection by the cantonal fire protection authority or at technical acceptance. As soon as the work is completed, the electrical installer permanently fixes an identification plate next to each opening. This marking states the name of the executing company, the date of the work, the exact commercial reference of the materials installed, the VKF (AEAI) certificate-of-use number and the fire resistance rating guaranteed for the wall (in particular EI 30, EI 60 or EI 90). Without this durable physical marking, the work is deemed not to be fire-tight during fire insurance audits, forcing the company to carry out destructive investigations at its own expense.

  1. Mapping of penetrationsAssign a unique identification number to each penetration and transfer it to the electrical installation diagrams in the as-built file.
  2. Time-stamped photographic recordTake two clear photographs per penetration: the arrangement of the cables before sealing, then the sealed work with its legible identification plate.
  3. Compilation of VKF (AEAI) certificatesFile the manufacturers' technical data sheets and the currently valid VKF (AEAI) certificates of use corresponding to the systems installed.
  4. Declaration of conformityDraw up the formal certificate signed by the technical manager, certifying strict compliance with the application instructions and fire safety rules.

Together, these documents form the register of fire-rated penetrations, an essential document included in the as-built file handed to the client for operation and maintenance. Archiving the evidence of execution in the as-built file also guarantees traceability during later alterations to the building, preventing third parties from drilling through the seals without precautions. Art. 364 CO provides that the contractor's liability is subject to the same rules as that of the employee and that he carries out the work under his personal direction. Negligence regarding compartmentation exposes the installer to serious consequences: art. 229 CP punishes with a custodial sentence of up to five years or a monetary penalty anyone who, in directing or carrying out a construction, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons; if through negligence, the penalty is a custodial sentence of up to three years or a monetary penalty. This documented file protects the electrical installer by demonstrating the strict conformity of the seals.

Managing non-conformities, re-sealing and as-built survey

Finding ordinary yellow or grey expanding polyurethane foam injected into a technical opening on the construction site is a major non-conformity. This flammable material destroys the integrity of the fire separation and spreads toxic gases through the compartmentation. As soon as this is found, or if a third party has carried out an unauthorised intervention in an opening that has already been sealed, the foreman applies the rules for handling defects under the Code of Obligations (CO). In accordance with art. 365 CO, the contractor immediately informs the client when any circumstance compromises the proper or timely execution of the work.

  1. Complete removal and remediationClear out all the non-certified material down to the bare concrete or masonry. Remove dust from the power cables and check that the sheaths show no sign of melting or thermal damage.
  2. Reinstating the approved systemInstall an approved firestopping system matching the fire resistance rating of the wall (high-density mineral wool boards coated with ablative sealant, intumescent bricks or specialist fire-resistant mortar) in accordance with the manufacturer's VKF (AEAI) certificate.
  3. Fitting the identification plateMechanically fix the riveted or glued label stating the approval number, the fire resistance class, the name of the electrical installer and the date of installation.
  4. Archiving the documents in the as-built fileDraw up the self-inspection record, attach the photographs taken before and after closing, then add the declaration of conformity to the electrical installation file handed to site management.

The evidence in the as-built file must include the technical data sheets of the products installed, a copy of the valid VKF (AEAI) certificate and the precise location plan of each cable penetration. Without this rigorous marking, the cantonal fire protection authority or the cantonal building insurance (ECA) refuses acceptance of the work, blocking the occupancy permit for the whole building.

Frequently asked questions

Is fire-resistant foam from an aerosol can sufficient to re-seal a cable tray?

No. Certified foams in cartridges or aerosol cans are generally approved by the VKF (AEAI) only for narrow linear joints between solid elements or for single penetrations of rigid conduits. For a layer of cables or a complete perforated cable tray, only a system made of rock wool boards with ablative coating or intumescent bricks guarantees that the compartmentation is maintained.

What mandatory information must appear on the signage label of a penetration?

Labelling the penetration requires an indelible marking adjacent to the opening. It must state the company name of the executing electrical installation company, the exact designation of the sealing system used, the Swiss approval certificate number issued by the VKF (AEAI), the fire resistance rating achieved (for example EI 60 or EI 90) and the month and year of execution.

How should the later addition of a power cable in an already sealed opening be handled?

The electrician must never punch through a fire-resistant board without immediately re-sealing it. The provided passages (flexible brick systems or re-enterable collars) must be used. As soon as the new conductor is introduced, the residual space must be sealed with the compatible intumescent sealant from the same approved manufacturer, and the signage plate must then be updated with the new date.

Who is responsible for sealing if the mason has core-drilled the fire-rated wall?

The electrical installer is responsible for the openings he uses for his electrical conduits under standard SIA 118, unless the contract assigns the firestopping package to a specialist company. If the opening exceeds the maximum dimensions permitted by the manufacturer's certificate, the electrician must require site management to have the masonry opening reduced to a compliant size before applying his certified system.

Texts and standards cited

  • CO art. 365Materials and ground: the contractor is responsible for the good quality of the materials he supplies; if the materials supplied by the client or the ground designated by him are found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).
  • norme SIA 118General conditions for the execution of construction work governing the rights, obligations and services of the contracting parties on Swiss construction sites.