Renovation: diagnosis and rework of the existing installation: the execution framework
Working on an old electrical installation demands absolute rigour in order to modernise without taking on the defects of the existing installation. Intended for electrical installers, foremen and safety officers, this section details the operational method: examining the circuits, identifying degraded or asbestos-containing materials, contractually defining the scope of the work, fitting the appropriate protection in accordance with the NIBT and formally recording reservations before handing over the safety report under the OIBT.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
1.0 MΩ
Minimum insulation resistance required for new or refurbished circuits at 500 V DC
30 mA
Maximum rated residual operating current of protective devices for socket outlets up to 32 A
0.4 s
Maximum rated disconnection time in a TN system for final circuits up to 63 A
14 days
Usual notice period for announcing a planned power cut to occupants in an occupied building
Technical scope and responsibilities of the installer
Reworking an existing installation is the most delicate exercise in CFC 232. The electrical installer must never be drawn into a global recommissioning without having precisely defined the boundary between the new works and the retained parts. The work is confined exclusively to power circuits: distribution boards, wiring, overcurrent protection, residual current devices and the earthing system. Any connection related to low-voltage communication systems, whether IT cabling, optical fibre or home-automation bus, falls under CFC 238 and is excluded from this scope of work.
In contractual and technical terms, the electrician is responsible for the circuits they connect, modify or re-energise. In accordance with art. 365 CO, if the material supplied by the client or the site designated by them is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, failing which they bear the consequences. In older buildings, this means objectively establishing the condition of the conductors by insulation measurements before any bridging or extension. Heating equipment such as the heat pump falls under CFC 241 for its internal control, just as the air-handling unit belongs to CFC 244: the electrician's mandate ends at the local isolator or at the power supply terminals.
| Existing element | CFC 232 responsibility | Trade boundary or third party |
|---|---|---|
| Building riser | Rework downstream of the service entrance box | Distribution network operator for the upstream part |
| Asbestos-containing fibre-cement ducts | Visual finding and stopping the chasing | Asbestos removal company recognised under OTConst |
| Heat pump supply | Power wiring and dedicated circuit breaker | CFC 241 technician for control and internal components |
| Multimedia and bus cabling | Installation of empty flush-mounted conduits | CFC 238 specialist for cable pulling and network connection |
Step-by-step method for approaching an upgrade construction site
To modernise a building without taking on liability for unmodified, worn-out elements, the professional must structure the work in a logical order. The approach must begin with a thorough examination of the existing installation: opening the main junction boxes, identifying the type of insulation, testing the continuity of the protective conductor and measuring the insulation resistance. These preliminary checks avoid nuisance tripping when a residual current device is fitted and immediately reveal any wiring with impregnated paper or degraded cotton insulation.
- Initial diagnosis and identificationOpen the boards and boxes to record the ratings, trace the phases and identify separate or shared neutrals where no original diagram exists.
- Detection of hazards and pollutantsVisually inspect slab penetrations and old ducts to rule out any risk of asbestos exposure before drilling.
- Securing the installation and continuity of servicePlan the general power cut, install a temporary site distribution board and methodically switch over the priority feeders.
- Implementation and NIBT testsRework the retained circuits, adapt the overcurrent protection, fit 30 mA RCDs and measure the short-circuit current.
- Formal demarcation and reportDraw up the measurement record and state on the OIBT safety report the exact limits of the renovated circuits in relation to the existing installation.
The chapters in this section guide the electrician from the minimally destructive audit through to the handover of the legal documents. They specify the strict criteria for refusing to reuse a deteriorated conductor, the physical limits of a simple circuit extension, and the rules for coordination with the network operator when working on a riser. In heritage contexts or where budgets are phased, progress must be documented point by point to ensure the safety of people while limiting the legal exposure of the installation company.
📘 Chapters in this section 10
Diagnosing an old installation: what you open, what you measure, what you write down
Master the strategic opening points and insulation measurements to precisely assess an outdated switchboard.
Renovation: diagnostics and remediation of existing structuresOld wiring with degraded insulation: recognising it, measuring it and refusing to reuse it
Identify perished textile insulation and technically justify its complete replacement without taking on liability.
Renovation: diagnostics and remediation of existing structuresExtending an existing installation: how far to go without redoing everything
Define the normative boundary between simply adding a socket and heavy rework of a complete circuit.
Renovation: diagnostics and remediation of existing structuresReplacing a switchboard in an occupied building: planned shutdown, temporary supply and reconnection of circuits
Switch over a main distribution board in an occupied building using a rigorous temporary supply method without a prolonged power cut.
Renovation: diagnostics and remediation of existing structuresAsbestos in older buildings: recognise the risk before drilling and stop work
Spot asbestos-containing ducts and fire-resistant boards before drilling so as to stop the construction site in full compliance.
Renovation: diagnostics and remediation of existing structuresPhased compliance upgrade: where to start when the budget is limited
Plan the priority safety steps so as to protect the user effectively when the budget is limited.
Renovation: diagnostics and remediation of existing structuresInstallation without plans: tracing circuits without opening everything up
Trace hidden connections and isolate shared neutrals using injection techniques without demolishing the walls.
Renovation: diagnostics and remediation of existing structuresRising main: boundary between distributor and owner, and who may work on it
Clarify the legal demarcation between the main overcurrent protective device and the network operator before touching the riser.
Renovation: diagnostics and remediation of existing structuresProtected building: install without altering, and obtain approval from the competent authority
Integrate modern wiring into a listed building by negotiating invisible routes with the heritage authorities.
Renovation: diagnostics and remediation of existing structuresAcceptance of a renovation: what the report covers and what it expressly excludes
Write an unimpeachable OIBT safety report by precisely delimiting the new installations and the excluded parts.