Key takeaways
- Earth measurement requires opening the disconnecting link to isolate the electrode from the upstream network.
- The three-stake method at sixty-two per cent guarantees an electrode measurement with no overlapping zones of influence.
- In a TT system the target value depends on the residual current circuit breaker, whereas in TN the meshed earthing prevails.
- Soil dried out in midsummer multiplies the measured resistance by two to five compared with spring.
Connection to the isolator, stake method and NIBT acceptance criteria
Before any precise measurement of the building's earth electrode — whether it is a connection to the foundation slab reinforcement carried out by the mason or a loop under the foundation — the electrician must open the earthing isolator (disconnecting link). Measuring with the link closed distorts the analysis by including the PEN conductor or the public water network, thus measuring the overall impedance of the distribution network rather than the performance of the local electrode itself. Visually checking that the main earthing conductor is de-energised before opening it is a basic safety rule.
- Opening the circuitOpen the measuring link with the power off to separate the local electrode from the main earthing busbar (BPT) and the building's equipotential bonding.
- Aligning the probesRun out the injection line to the outer current stake, driven in a straight line into loose soil at a minimum distance of about forty metres from the building.
- Positioning at 62 %Drive the intermediate potential probe at exactly sixty-two per cent of the total distance between the earth electrode and the current stake.
- Validating the flat zoneMove the intermediate probe ten per cent forward and then backward; the displayed value must remain strictly constant to ensure there is no overlap of the zones of influence.
According to the NIBT, the requirements differ fundamentally depending on the system earthing applied on the Swiss distribution network. In a TN system, safety relies on the instantaneous tripping of overcurrent protection in the event of a phase-to-frame insulation fault; the value of the local earth resistance does not directly determine the disconnection, but it maintains the earth potential and limits voltage rises on the neutral. In a TT system, rare in Switzerland but found on some rural networks or construction site installations, the local earth value must ensure a touch voltage below fifty volts when the highest-rated residual current device trips.
| System / Application | NIBT disconnection rule | Usual field target value |
|---|---|---|
| TN system (foundation slab or loop) | Loop impedance ensuring the circuit breakers trip | < 10 Ω (Swiss practical recommendation for a good connection) |
| TT system (without neutral earthing) | Touch voltage RA ≤ 50 V divided by IΔn | < 20 Ω (for a 300 mA selective RCD: max 166 Ω) |
| Lightning protection (CFC 232) | Discharge of atmospheric currents according to specific requirements | < 10 Ω (measured outside the general interconnection) |
Seasonal soil fluctuations and correction margin for the safety report
The earth is not a stable metallic conductor: electrical conduction in the ground is purely electrolytic in nature, provided by the mineral salts dissolved in the interstitial water. The resistivity of a soil varies dramatically with its moisture content and temperature. A measurement taken in March in water-saturated soil reflects temporarily optimal conditions. Conversely, after three consecutive weeks of summer heatwave, the top fifty centimetres of soil lose their water through evaporation. If the electrode is shallow, its measured resistance can double, or even increase tenfold in the stony or sandy ground of the Swiss Plateau.
| Ground type | Resistivity, wet soil (spring) | Resistivity, dry soil (late summer) | Recommended margin |
|---|---|---|---|
| Topsoil / clayey silt | 30 to 50 Ω·m | 80 to 150 Ω·m | Factor 1.5 to 2 |
| Sandy gravel / alluvium | 100 to 300 Ω·m | 500 to 1500 Ω·m | Factor 2 to 3 |
| Rocky ground / dry moraine | 500 to 1000 Ω·m | 2000 to 4000 Ω·m | Factor 3 to 5 |
To avoid these climatic drifts, the electrician must make sure the electrodes are positioned below the frost and desiccation zone, i.e. at least eighty centimetres below finished ground level. In recent buildings where the concrete slab is laid on a continuous perimeter thermal insulation layer (slab on foamed glass or extruded polystyrene), the reinforcement no longer communicates with the moist soil at all. The foundation earth must then be replaced by a closed loop buried under the blinding layer or supplemented by copper-clad steel earth rods driven deep to reach groundwater or stable moist layers.
Measurement protocol on dry ground and hygrometric compensation
Carrying out an earth resistance measurement in a low-water period or after a prolonged drought considerably alters the resistivity profile of the surface soil. When the auxiliary current electrode and the potential probe are driven into a sandy-gravel backfill or topsoil dried out over the first forty centimetres, the contact resistance of the test stakes can reach values that saturate the earth tester's injection circuits. To ensure the validity of the 62 % method, the operator must make sure that the earth resistance of the auxiliary stakes does not distort the potential gradient around the main earth electrode.
- Targeted wetting of the auxiliary stakesIf the installation tester indicates too high a noise level or refuses to start the measurement because of excessive probe resistance, saturate the area immediately around the potential stake and the current stake with clean water. This reduces the local contact resistance without artificially altering the overall resistance of the building's earth electrode, which lies at depth.
- Checking the equipotential plateauMove the intermediate potential probe to 52 % and then to 72 % of the total distance between the earth electrode and the current stake. In very dry soil, the bell curve widens; the measurement is validated only if the difference between the three readings remains below 10 % of the central value taken at 62 %.
- Applying the seasonal increase factorA satisfactory measurement recorded on waterlogged ground at the snowmelt or in late winter can degrade drastically in the heart of summer if the electrode is not buried deep below foundation level. Conversely, a value obtained on dry soil provides a conservative safety margin for the whole hydrological year.
| Geological nature of the soil | Average resistivity, wet soil [Ω·m] | Average resistivity, dry soil [Ω·m] | Precautions when placing the probes |
|---|---|---|---|
| Topsoil and silty alluvium | 30 to 80 | 150 to 400 | Drive the stakes in at least 50 cm to get through the dehydrated surface crust. |
| Compact clayey-sandy moraine | 80 to 200 | 300 to 800 | Water the insertion points of the auxiliary spikes to stabilise the injection impedance. |
| Gravel and sand of fluvio-glacial terrace | 300 to 1000 | 1500 to 4000 | Space the stakes at least 40 m apart to clear the zone of influence and find a plateau. |
| Fractured limestone rock or schist | 500 to 2500 | > 5000 | Prefer direct connection to the concrete slab rather than to artificial electrodes. |
Expected values according to the distribution system and recording
The permissible resistance level depends directly on the earthing system implemented at the building's service entrance. In Switzerland, the vast majority of low-voltage distribution networks of the network operators use the TN system, mainly in the TN-C-S form with protective neutral earthing according to the NIBT. In this system, automatic disconnection of the supply in the event of a solid insulation fault is ensured by the metallic fault loop formed by the live conductors and the protective conductor or PEN, and not by the earth loop through the ground. The resistance of the local earth electrode nevertheless plays a key role in stabilising the neutral potential and limiting surges transmitted by the external network or of atmospheric origin.
For the rare local configurations operated in a TT system, for example on specific construction sites, temporary excavation installations or certain particular rural distributions, the earthing resistance must absolutely comply with the fundamental relationship linking the maximum permissible touch voltage of 50 V to the rated residual operating current of the residual current protective device. If a 300 mA residual current circuit breaker protects the whole installation head, the electrode resistance may not exceed 166 Ω, even under severe summer drought conditions.
- TN system (neutral earthing): the NIBT does not impose a strict minimum numerical value for the building's earth, but the local technical requirements of the energy distributors usually recommend an overall value below 10 Ω, tolerated up to 20 Ω in very resistive ground.
- Lightning protection according to the building insurance guidelines: where an external lightning protection system is required, the overall resistance to ground must be as low as possible, typically aimed at below 10 Ω for all the down conductors coupled to the foundation slab.
- Recording in the safety report: the test record must state the moisture condition of the ground at the time of the reading, the measuring instrument used with its serial number and calibration date, and the exact configuration of the electrode at the time the disconnecting link was opened.
Corrective measures for a non-compliant value and final validation
When the earthing resistance measurement exceeds the permissible criteria set by the NIBT for the chosen distribution system, or if the summer calibration reveals a critical moisture drift, the electrician cannot validate the test record. According to art. 364 CO, the contractor carries out the work in accordance with the recognised rules of the art. It is then up to the site team to diagnose the failure and implement immediate remedial measures before the safety report required by the OIBT is drawn up.
- Physical inspection of the contact interfacesOpen the main earthing isolator with the general power off. Inspect the connection lug fixed to the steel starter bar coming from the slab reinforcement. Remove mill scale, laitance residues or surface corrosion on the copper flat or round with a wire brush. Retighten the stainless-steel bolting to the specified torque before any new measurement with the earth tester.
- Validating the placement of the test probesRepeat the three-stake method according to the 62 % rule. Move the intermediate measuring stake ten per cent towards the earth electrode and then towards the auxiliary current-injection electrode. If the measured value varies by more than five per cent between these points, the zones of influence overlap: the line distances must be lengthened to reach a stable equipotential plateau.
- Driving additional deep electrodesIf the concrete slab is isolated from the ground by a waterproofing membrane or if the rocky ground remains too resistive after the low-water period, drive one or more vertical copper or copper-clad steel earth rods at the foot of the excavation. Bury them below frost level, at a depth ensuring a connection with the permanently moist geological layers.
- Laying an external bare copper loopWhere the loose ground allows it, lay in an external perimeter trench a bare copper conductor of at least 50 mm², backfilled with compacted fine soil free of rubble. Connect this conductor in parallel to the building's main earth terminal to lower the overall impedance.
Frequently asked questions
What safety margin should be applied to a measurement taken in very dry soil?
In gravelly or sandy soil after several weeks without rain, the apparent resistivity increases sharply. If the installation depends on this electrode for the discharge of fault currents, increase the measured value by a correction factor of 1.2 to 1.5, or plan a follow-up check in a wet period before the safety report is definitively signed in accordance with the OIBT.
Why measure the earth in a TN-S system when the fault current returns via the neutral?
In a TN-S system, automatic disconnection relies on the impedance of the phase-PE fault loop. However, the NIBT requires an effective earth connection to fix the neutral potential relative to the ground, to discharge surges of atmospheric origin and to limit step or touch voltages in the event of an accidental break of the PEN conductor upstream of the service entrance box.
How do you apply the 62 % method on a cramped urban plot?
If a straight linear run-out is impossible because of fences or asphalt, lay the auxiliary stakes out diagonally or apply the triangular method while keeping a minimum angle of sixty degrees between the two auxiliary circuits. Where there is no planted area to drive the probes into, using an earth clamp on a closed loop remains an accepted alternative.
Can the earth electrode be connected to the metal sanitary pipework?
No. The NIBT expressly prohibits using metal water, gas or district-heating pipes as main earth electrodes. These networks are frequently partly replaced with insulating synthetic materials such as polyethylene. They may only be part of the main equipotential bonding connected to the building's earth bar.
Texts and standards cited
- CO art. 364obligations of the contractor: liability subject to the same rules as that of the employee; he carries out the work in person or under his personal direction; unless otherwise customary or agreed, he procures at his own expense the means, equipment and tools required.