Key takeaways
- An insufficient separation distance causes a destructive lateral flashover to the metal pipes of the building.
- The number of down conductors depends on the roof perimeter and the selected class of installation.
- Each down conductor is connected at its base to the foundation earth via a test joint.
- Early coordination with the structural work and the sheet-metal worker guarantees the continuity of the provision connections.
Down conductor routing and control of the separation distance
During a direct lightning strike, the steep-fronted current wave flows through the air-termination network and descends towards the ground. This pulse creates a sudden inductive voltage drop along the conductor. If a metal mass connected to the internal earth, such as sanitary piping, concrete reinforcement or a ventilation duct, runs too close to this down conductor, the transient potential difference exceeds the dielectric strength of the medium. The air or the building material gives way, triggering a dangerous lateral flashover by sparking, a source of fire or electrocution inside the building.
- Separation distance (s)
- Minimum physical insulation gap required between a lightning conductor and an internal or external conductive element of the building to prevent any disruptive flashover.
The routing of the down conductors must follow the shortest, most direct and straightest possible path to earth. Tight bends are prohibited: a minimum bending radius of 20 centimetres is required to prevent excessive parasitic induction. The total number of down conductors is determined by dividing the projected outer perimeter of the roof by the standardised unit spacing. Installation at the projecting corners of the structure is always preferred, where the concentration of electromagnetic fields and the discharge of natural charges are optimal.
| Protection class (LPS) | Average spacing between down conductors | Minimum number of down conductors |
|---|---|---|
| Class I (major risks) | 10 metres | 2 interconnected down conductors |
| Class II (sensitive buildings) | 10 metres | 2 interconnected down conductors |
| Class III (multi-family housing, standard commercial buildings) | 15 metres | 2 interconnected down conductors |
| Class IV (simple buildings) | 20 metres | 2 interconnected down conductors |
Equipotential bonding at the facade base and interface coordination
At the base of the run, each down conductor must absolutely reach the earth electrode of the building. To prevent dangerous potential differences at ground level, all the down conductors are connected to the foundation earth strip or loop. A test joint, often referred to as a disconnection terminal or measuring spark gap, must be inserted on each down conductor. This device makes it possible to disconnect the conductor locally in order to isolate the earth electrode during the periodic ohmic resistance measurements prescribed by the NIBT.
- Locating and exposing the provisionAt the facade base, locate the flat bar or stainless steel round bar projecting from the foundation slab left by the masonry contractor, then brush the surface to remove any concrete laitance.
- Installing the test jointInstall the standardised disconnection terminal between 1.50 m and 1.80 m above the finished ground level in surface-mounted form, or in a watertight flush-mounted box at ground level if architectural constraints require it.
- Mechanical connection and protectionTighten the connection with stainless steel bolts to the required torque, apply an anti-corrosion protective sleeve on the buried metals and fit a mechanical protection tube against impacts over the first two metres.
The success of the work depends on a rigorous interface between the trades. The reinforcement of the foundation slab serving as the foundation electrode is the responsibility of the mason (CFC 211.1), who installs the provisions in austenitic stainless steel of grade 1.4404. The electrician accepts these provision bars before the perimeter insulation is installed. If the steel is non-conforming, cut or missing, art. 365 para. 3 CO requires the client to be informed immediately so that the defect can be remedied before backfilling. Continuity on the roof also requires precise coordination with the sheet-metal worker for the connection to the gutters or the roofing.
Perimeter distribution and routing of down conductors according to protection class
Installing a lightning protection system requires a symmetrical distribution of the down conductors around the outer perimeter of the building. The lightning protection class (I to IV), set by the AEAI protection concept and the engineering study, determines the permissible average spacing between each conductor. The down conductors must be installed as a priority at the projecting corners of the structure, where electric field concentrations and the probability of impact are highest. For a standard rectangular building, a minimum of two separate down conductors is required, providing a parallel path to the earth electrode in order to divide the current wave and attenuate the magnetic fields induced in the building. The route favours the most direct and vertical line from the roof air-termination network to the ground, without forming closed loops that would increase the self-inductance of the conductor.
| Protection class | Average spacing between down conductors | Usual standardised conductors |
|---|---|---|
| Class I | 10 metres | Hard-drawn copper round bar Ø 8 mm or copper flat bar 25 x 3 mm |
| Class II | 10 metres | Aluminium round bar Ø 8 mm or aluminium flat bar 30 x 3 mm |
| Class III | 15 metres | V4A stainless steel round bar Ø 8 mm |
| Class IV | 20 metres | Galvanised steel round bar Ø 8 mm or flat bar 30 x 3.5 mm |
The routing on the facade must absolutely avoid re-entrant corners and go around bands or balconies with a minimum bending radius of 20 centimetres. Any sharp loop generates a localised inductive overvoltage likely to cause a dielectric breakdown towards the concrete reinforcement or the internal pipework. The down conductors can be installed surface-mounted with supports suited to the perimeter insulation, or integrated under the render in fireproof sleeves. Where reinforced concrete pillars serve as natural conductors, the electrical continuity of the reinforcing bars must be validated by an impedance measurement below 0.2 ohm over the entire height of the building.
- Rigid fixing of the conductor every metre on the facade to withstand the electrodynamic stresses generated by the lightning strike.
- Ban on routing through internal technical shafts shared with power or telecommunication cables.
- Systematic connection of metal roof elements such as gutters and verges at the top of each down conductor.
- Maintaining a straight route that avoids any mechanical constriction when passing through window sills and cornices.
Control of the separation distance and connection at the facade base
When a lightning strike is discharged, the inductance of the down conductor instantly raises its electrical potential to several hundred kilovolts. If an internal metal pipe — drinking water pipe, heating riser or sanitary piping — runs too close to the facade, the dielectric strength of the intervening materials is exceeded. A dangerous flashover by sparking then occurs through the masonry, creating an immediate risk of fire or perforation of the pipes. The installer-electrician must check compliance with the separation distance. Where this distance cannot be technically guaranteed, a direct equipotential bond must interconnect the pipe with the down conductor, with suitable surge arresters integrated into the internal installation.
- Positioning the disconnection jointInstall a measuring terminal at the base of each down conductor, fitted between 0.3 and 0.5 metre above the ground or in a watertight box on the facade, making it possible to isolate the earth electrode for periodic checks.
- Connection to the foundation reinforcementConnect the lower part of the measuring joint to the V4A stainless steel or copper provision bars coming from the foundation slab, installed in coordination with the structural work contractor.
- Main equipotential interconnectionConnect the down conductor base loop to the main equipotential bonding bar of the building in the basement, ensuring potential balance between the metal masses and the lightning rod.
Interdisciplinary coordination is essential to avoid layout conflicts. The electrician must check the position of the pipes installed by the plumber or the sheet-metal worker before the perimeter insulation is installed. Under art. 365 CO para. 3, the contractor informs the client if a circumstance jeopardises the proper or timely execution of the work. As soon as a metal pipe is installed without respecting the required separation distance, the installer records the non-conformity and proposes the modification of the route or the appropriate equipotential bonding.
Managing routing conflicts, non-conformities and remedial work at the base
On the construction site, critical non-conformities often arise late: a metal ventilation or rainwater pipe installed in the thickness of the thermal insulation without consultation, or a connection tab to the reinforcement cut off by the mason during formwork removal. As soon as a conductive pipe comes closer to a down conductor than the calculated separation distance, the risk of dielectric breakdown through the insulation becomes immediate. The installer-electrician must never validate such a situation by a simple visual check without formalised corrective action.
- Finding and stop of work stageMeasure the actual gap between the down conductor and the metal mass in question. If the measured distance remains below the prescribed value, notify site management in writing of the stoppage of work on this section.
- Choice of compensatory measureTwo technical solutions are available: divert the route of the down conductor to restore the required insulation distance, or integrate the metal pipe into the protection system by a calculated direct equipotential bond, provided that this mass can discharge a fraction of the lightning current without danger to the structure.
- Repairing a damaged earth provisionIf an earth provision is missing or torn from the foundation slab, chip out the concrete down to sound reinforcement in order to crimp a certified cross connector onto it, or drill at the facade base to drive a dedicated vertical copper-clad steel earth rod connected to the measuring terminal.
Art. 365 CO para. 3 provides that if a circumstance jeopardises the proper or timely execution of the work, the contractor informs the client immediately. In the event of a structural obstacle or encroachment by another trade, the electrician records the reservation in the site diary and sends a formal notice before the ventilated facades are closed. Route modifications and the continuity values measured at the disconnection joints are then entered on the as-built drawings handed over to the inspection.
Frequently asked questions
How should you react if a metal rainwater downpipe runs alongside the lightning conductor at less than 30 cm?
If the calculation of the separation distance shows a risk of flashover, the installer must either divert the copper or aluminium conductor to regain the required spacing, or bridge the gutter and the downpipe in order to use them as a continuous natural conductor. This latter option requires a systematic equipotential bond at the base connected directly to the earth loop.
What should be done when the connection tab from the foundation slab was cast in the concrete without protruding?
Leaving the down conductor unconnected at its base is prohibited. The electrician carefully chips out the concrete locally to expose the foundation earth steel over ten centimetres, then fits a clamp tightened under control. If the reinforcing bars cannot be accessed, installing a dedicated external earth rod remains the mandatory alternative solution.
Can the number of down conductors be reduced if the facade has many glazed openings?
The perimeter distribution must respect the maximum spacings imposed by the protection level of the installation. If glazed bays block a direct vertical route, the electrician goes around the openings with horizontal or oblique deviations while keeping an overall downward path. Arbitrarily reducing the number of down conductors overloads the network and requires a complete recalculation of the separation distances.
Which trade is responsible for installing the disconnection joint on the facade?
Installing the disconnection joint or the measuring terminal is contractually the responsibility of the installer-electrician. He coordinates its positioning with the facade contractor or the mason in order to integrate the removable flush-mounted box between one metre and one metre fifty above the finished ground level, ensuring the physical separation for periodic earth resistance measurements.
Texts and standards cited
- CO art. 365material and ground: the contractor is responsible for the good quality of the material he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he informs the client immediately, failing which he bears the consequences (para. 3).