🧱 CFC 232Lockout/tagout, dead working and arc flash riskChapter 4 of 10 in the section

Working near a live installation: distances and de-energisation

By the end of this chapter, you will be able to identify the risk of flashover near overhead conductors or busbars, determine the applicable safety distance according to the actual voltage confirmed by the network operator, draw up a priority switch-off request, and have certified temporary protection installed where this is technically impossible.

Key takeaways

  • The exact voltage of the line determines the minimum approach distance prescribed by SUVA.
  • The network operator must confirm the voltage level in writing before any work begins.
  • Obtaining de-energisation and lock-out remains the absolute priority prevention measure.
  • Temporary protection of the conductor with insulating profiles requires the agreement of the electricity distributor.

Determine the exact voltage and comply with the SUVA safety zones

On a building construction site, approaching an overhead power line or bare conductors is a fatal hazard of electric shock and electric arc. The rules of good practice and the SUVA guidelines require a strict hierarchy of safety measures. To prevent any direct contact or flashover at a distance, the electrician must never rely on the visual appearance of a line to deduce its voltage. Bare or poorly insulated cables may be operated at low voltage (230/400 V) or at medium and high voltage (from 1 kV to several tens of kilovolts). The limit approach distance varies radically according to this voltage level. In accordance with art. 82 LAA, the employer takes all the measures necessary that the state of the art makes it possible to apply in order to protect the integrity of the fitters.

Caution approach zone (guard zone)
Space surrounding bare live parts within which the risk of flashover or accidental contact requires the implementation of technical or distancing measures prescribed by SUVA and the operating standards.

To define the organisation of the construction site, the foreman or team leader must contact the distribution network operator (DNO) or the owner of the electrical installation. This step makes it possible to obtain a written statement certifying the nominal operating voltage of the line concerned. As long as this official confirmation is not recorded in the technical file of the construction site, the line is deemed to be live and is classified by default in the most restrictive voltage category. The technical rules distinguish direct approach by a worker from indirect approach through the handling of loads, metal ladders, profiles or aerial work platforms.

Minimum safety distances according to the nominal voltage of the line
Nominal voltage of the lineDirect approach distance (person and hand tools)Distance with machinery, platforms or handling of bars
Low voltage up to 1,000 V (1 kV)No approach closer than 0.5 m (contact distance)1.5 m minimum
High voltage from 1 kV to 36 kV1.5 m minimum3.0 m minimum
High voltage from 36 kV to 110 kV2.0 m minimum4.0 m minimum
High voltage above 110 kV3.0 m minimum (+ flashover zone)5.0 m minimum

Require de-energisation or have temporary insulating covering installed

The presence of a live installation in the immediate vicinity of an active work area requires radical preventive action: working de-energised must always be sought before any compensating measure is considered. The company's first step is to send the network operator a formal request for switch-off and lock-out for the required duration of the operations. In accordance with art. 3 OPA, the employer takes the protective provisions and measures that meet the recognised rules of technology. Working at a distance without switch-off when a switch-off is technically feasible is an unacceptable operating choice under the safety guidelines.

  1. Submitting the request to the distributorSend the written request for intervention to the network operator at least two to three weeks before the planned start, stating the land-register location, the nature of the installation work and the estimated duration.
  2. Checking the switch-off certificateRequire the official notice of de-energisation and lock-out issued by the network operator, which states that the five vital safety rules have been applied on the section concerned.
  3. Validating the condition of the installation on siteVisually check for the presence of earthing and visible short-circuiting where the installation requires it, and mark the physical limits of the neutralised zone.

Where the network operator formally refuses de-energisation for incompressible public supply requirements or major technical constraints, temporary protection of the conductor becomes mandatory. This covering operation may under no circumstances be carried out by the building site electricians. It is entrusted exclusively to the specialised teams of the network operator or to a company authorised for live working (TST).

Once the temporary covering is in place, the team leader records acceptance of the device, informs each worker of the residual constraints during the daily safety briefing and sets up physical barriers or crossing gauges to prohibit lifting machinery from entering the sensitive perimeter.

Coordination with the network operator and switch-off procedure

Carrying out work on a facade, a roof or a technical infrastructure in the immediate vicinity of overhead conductors or service lines requires the risk to be interrupted at the source. The installation electrician must never assume the voltage level of an overhead structure on the basis of its visual size: some public medium-voltage distribution networks have spans and arrangements close to those of low voltage. The request for exact identification of the structure must be sent in writing to the competent distribution network operator (DNO) from the construction site preparation phase.

  1. On-site survey and identification of the operatorNote the identification number of the pole, roof bracket or nearest support, photograph the conductor configuration and locate the section concerned on an extract of the land-register plan. Send these items to the local DNO.
  2. Formal request for de-energisationSend a switch-off request stating the exact nature of the work, the footprint of the scaffolding or platforms, and the target dates and time slots. This step is generally taken several weeks in advance so that the distributor can organise any network loop closures or notify third parties supplied by the section.
  3. Switch-off certificate and application of the five vital rulesRequire written confirmation of switch-off and earthing issued by the distributor's authorised personnel. Never start the work on the strength of a verbal communication or an indicative time agreed by telephone.

According to art. 82 LAA, the employer takes, to prevent occupational accidents and diseases, all the measures for which experience has shown the necessity, which the state of the art makes it possible to apply and which are adapted to the given conditions. In the context of a heavy-current installation construction site, this obligation requires the complete cutting of the electrical supply to be systematically preferred over the setting up of makeshift arrangements under voltage. The presence of an active conductor within reach of a hand or tool is a fatal hazard of flashover or direct electrocution.

Minimum approach distances and protection zones according to the SUVA guidelines
Nominal voltage of the installationMinimum approach distance (instructed personnel)Safety distance (machinery, scaffolding, conductive elements)
Low voltage up to 1,000 V (bare wires)No-contact exclusion zone (0.5 m)1.50 m minimum from any moving element or structure
High voltage up to 30 kV (distribution network)1.50 m around live parts3.00 m minimum with controlled trajectory maintained
High voltage from 30 kV to 132 kV (regional transmission)2.50 m around live parts4.00 m minimum with dedicated supervision
High voltage above 132 kV (extra-high voltage)3.00 m to 5.00 m depending on voltage level5.00 m minimum for any construction site activity

Temporary conductor protection and supervision of workstations

Where the network operator demonstrates that complete de-energisation is technically impossible for reasons of essential supply, installing mechanical and insulating protection becomes the only permitted alternative to allow the construction site to continue. This temporary covering operation is strictly reserved to the DNO or to a company holding a specific authorisation for live working on heavy current. The building installation electrician must under no circumstances handle, fix or adjust insulating sheaths on a live external network himself.

  • Insulating sleeves and split profiles: clipped onto bare low-voltage conductors to eliminate the risk of direct accidental contact during sheet-metal work, cable pulling or renovation of service entry boxes.
  • Reinforced insulating sheets and cloths: applied to pole heads, insulators or roof penetrations to physically delimit the residual live zone.
  • Impassable physical barriers: installation of dry timber decking, solid non-conductive partitions or rigid retaining nets preventing tools from falling or a pole from touching the active installation.

In accordance with art. 3 OPA, the employer takes the protective provisions and measures that meet the requirements of the ordinance, the other applicable occupational safety provisions and the recognised rules of safety technology and occupational medicine. In practice, this means that even where temporary protection has been installed by the distributor, the work area must be subject to strict operating instructions given to the team.

Managing incidents, flashovers and refusal of lock-out

When actual conditions on the ground deviate from the safety plan, the team leader stops operations immediately. The unexpected approach of a machine, the swinging of a suspended load or the deterioration of a temporary conductor protection sheath is a fatal danger situation. In accordance with art. 82 LAA, the employer takes all the necessary measures adapted to the given conditions, and the workers support him in this prevention. As soon as the guard distance is inadvertently breached or an electrical flashover occurs, work must be stopped without delay.

  1. Freeze the situation and break the arcIf a crane jib or scaffolding touches an overhead conductor or comes close enough to create an arc, the operator must stay in his cab to avoid step voltage. If the machine is mobile and can be manoeuvred without increased risk, try to move the equipment carefully out of the flashover zone.
  2. Establish an exclusion perimeterImmediately prohibit access to anyone on the ground within a minimum radius of twenty metres around the fault zone. A medium- or high-voltage conductor fallen to the ground generates a critical potential gradient that makes any non-insulated approach fatal.
  3. Alert the control centre and the DNOContact the emergency services (144/118) and the control room of the distribution network operator (DNO) without delay. Require emergency switch-off, locking of the line and formal confirmation of switch-off before any clearing or evacuation manoeuvre.

The second frequent pitfall is the refusal or unexpected postponement of de-energisation by the network operator for operational reasons. In this situation, the installation electrician must never improvise by forcing the issue or compensate for the absence of switch-off with makeshift, unapproved screens. In accordance with art. 3 OPA, the employer takes the provisions that meet the recognised rules of technology. If the line remains live without approved covering, work in the approach zone remains strictly prohibited. The team leader records the event in the construction site log and notifies the stoppage to the site management.

Frequently asked questions

What should be done if the network operator refuses to de-energise a medium-voltage line?

The installation electrician categorically refuses to send personnel into the approach zone without prior switch-off. If the network operator cannot lock out the line for operational reasons, it must be asked to install certified insulating covering on the cables itself. Failing a technical agreement guaranteeing approved physical separation, the team leader immediately stops the operations concerned and notifies the construction site management that intervention is impossible.

How should you react when a temporary protection sheath on a low-voltage line has come off?

All work nearby is suspended immediately and the perimeter is marked out on the ground to prevent workers from gaining access. Fitters must under no circumstances attempt to refix or reposition the insulating protection themselves with makeshift tools. Restoring the covering is the sole responsibility of the electricity distributor or a qualified company with the specific live-working equipment required under the applicable guidelines.

What should be done if a worker feels tingling in the ground near an overhead line?

This phenomenon indicates step voltage caused by a current leakage or a fallen conductor nearby. The worker must immediately stop walking with long strides. He must move away from the area by taking small shuffling steps, feet together and touching each other, or by hopping with both feet together, without ever touching the ground with both hands, while alerting the other trades.

Who authorises the resumption of work on the construction site after an emergency switch-off caused by an electric arc?

Only the distribution network operator is authorised to reopen the work area. Even if the arc has stopped and the machine has been cleared, the line may be automatically reclosed remotely by the network protection devices. Resumption requires an operator's agent to be present on site, a thorough inspection of the affected cables and a formal notice to resume activity.

Texts and standards cited

  • LAA art. 82General prevention rules: the employer takes all the necessary measures that the state of the art makes it possible to apply and that are adapted to the given conditions; the workers support him.
  • OPA art. 3Protective measures and installations: the employer takes the measures that meet the requirements and the recognised rules of safety technology.