Key takeaways
- Independent inspection applies to any installation whose periodic inspection interval is less than twenty years.
- The installer must hand over their initial safety report before the external inspection body intervenes.
- The complete technical file comprises up-to-date diagrams, the measurement report and the notice of completion of the works.
- Formal rectification of the defects found is a condition for final acceptance of the file by the network operator.
Determining the cases subject to inspection and organising the external inspector's visit
Under the OIBT, the installation electrician holding the general installation authorisation carries out their own final inspection and draws up an initial safety report. As soon as the works involve increased safety requirements, federal legislation withdraws the installer's right to issue the final validation alone. An independent inspection body, holding an inspection authorisation issued by the Federal Inspectorate for Heavy Current Installations (ESTI), must then verify all the work carried out.
- Independent acceptance inspection
- Mandatory technical verification carried out by an accredited inspection body or an impartial independent inspector who has taken no part in the design, execution or repair of the electrical installation inspected.
The obligation to have an external acceptance inspection depends directly on the periodic inspection interval assigned to the building or room by the OIBT. Any installation whose periodic inspection interval is less than twenty years requires this independent inspection within six months of the actual commissioning of the works.
| Use of the building | OIBT interval | Independent acceptance inspection |
|---|---|---|
| Standard individual and multi-unit dwellings | 20 years | No (final inspection by the installer) |
| Craft premises, offices, retail shops | 10 years | Mandatory within 6 months |
| Hospitals, petrol stations, premises with explosion hazard | 1 year or 5 years | Mandatory within 6 months |
| Temporary construction sites and fairground installations | 1 year | No (specific self-inspection regime) |
Compiling the technical installation file and clearing notices of defects
The external inspector's visit is prepared as soon as the wiring and apparatus work is finished. To avoid administrative refusals or additional chargeable visits, the construction site foreman gathers a complete technical file on site. The inspector begins the examination by checking the consistency between the execution documents and the physical work in the distribution boards.
- Single-line diagrams of the main and sub-distribution boards, updated with final labelling.
- Installation plans showing the actual location of loads, emergency switches and special sockets.
- Complete measurement report drawn up during the internal final inspection (continuity of the protective conductor, insulation resistance, fault loop impedance, tripping current and time of residual current devices).
- Declaration of conformity for switchgear assemblies built to order in the workshop or on the construction site.
- Provisional safety report (RaSi) signed by the holder of the company's installation authorisation.
In the field, the inspector proceeds by sampling or by exhaustive checking of sensitive components: terminal tightening to the specified torque, presence and cross-section of the main and supplementary equipotential bonding, selective tripping of circuit breakers and residual current circuit breakers, and exact rating of fuses according to the execution diagram. If non-conformities are found, the inspector draws up an official defects report notifying each disputed point.
- Receipt of the defects reportThe construction site foreman examines the deviations found, identifies whether it is a material problem, a tightening defect or a diagram error, and plans the fitters' intervention.
- Rectification on siteThe electricians correct each anomaly found: redoing labelling, replacing an unsuitable circuit breaker or restoring a faulty earth continuity.
- Certificate of defect rectificationThe holder of the installation authorisation signs the formal confirmation of defect rectification on the inspection body's form, without altering the original data.
- Administrative transmission and archivingThe external inspector validates the corrected document, signs the final safety report and sends it to the owner of the building and to the distribution network operator to close the notice of completion.
Field procedure of the acceptance inspection and technical hold points
The independent acceptance inspection is the legal stage at which an inspection body holding an authorisation issued by the Federal Inspectorate for Heavy Current Installations (ESTI), entirely independent of the installer who carried out the work and of the engineering office that designed the project, validates the operational safety of the works. Under the OIBT rules, this external verification is mandatory for installations subject to an inspection interval of less than twenty years: industrial buildings, craft businesses, premises for medical use, farms and high-output photovoltaic installations. The presence on site of the construction site foreman or the responsible installation electrician remains essential to accompany the inspector, operate the isolation devices under lockout and justify the safety provisions adopted during installation.
As soon as the independent inspector arrives, the installer makes the entire technical file available, including the initial safety report drawn up during the internal final inspection, the complete measurement reports, the up-to-date single-line electrical diagrams, the plan of the final circuits and the principle diagram of the earthing system. The inspector begins with a careful visual examination of the main and secondary distribution boards: checking the standardised conductor labelling, compliance of cross-sections with the rating of the line protection circuit breakers, absence of direct contact with busbars and conformity of the main and supplementary equipotential bonding.
| Item inspected | Measurement / test | Required compliance criterion |
|---|---|---|
| Continuity of protective conductors (PE) | Measurement with polarity reversal at a minimum test current of 200 mA | Ohmic resistance below 1 ohm, mechanical tightness ensured |
| General insulation resistance | Injection of 500 V DC between live conductors and earth | Minimum value of 1.0 megohm on low-voltage circuits |
| Residual current devices (RCDs) | Tripping under calibrated sinusoidal fault current (1x IΔn and 5x IΔn) | Disconnection time compliant with NIBT and actual tripping current within tolerances |
| Fault loop impedance (L-PE) | Measurement under load without nuisance tripping of upstream RCDs | Prospective short-circuit current ensuring automatic disconnection in less than 0.4 s |
| Equipotential bonding of structures and pipework | Checking tightness of earthing clamps and direct ohmic measurement | Uninterrupted metallic continuity to the main earth terminal |
During the metrological tests, the installer uses their own multifunction measuring instruments in parallel with those of the inspector. This direct comparison of the values recorded — in particular for loop impedances at the back of the board or at the most distant sockets — makes it possible to settle immediately any disputes over calibration or poor contact on the test probes. Any refusal of access to a flush-mounted junction box, a cable tray in a closed false ceiling or a locked technical room results in a blocking reservation being recorded in the audit report.
Clearing non-conformities, re-inspection and transmission of the safety report to the network operator
At the end of the visit, the independent inspector records all findings in a defects list classified by degree of risk. The distinction between critical defects immediately endangering people's safety and administrative non-conformities determines the intervention schedule of the installation team. The installer must organise the technical remedy of the disputed points without interrupting service to installations already live.
For ordinary defects not presenting a direct threat to life — such as incomplete labelling on circuit breaker covers, absence of a single-line diagram in the board pocket, a loose cage terminal or a loop impedance value marginally insufficient to ensure disconnection within the required time —, the independent inspector sets a formal deadline for rectification. Art. 367 CO governs the verification of the work and the notification of defects: the installer receives the written notice and promptly arranges corrective repairs with their network electricians or lead fitters.
- Receipt of the inspection report and analysis of deviationsBreak down the non-conformity items identified by the independent expert, check the installation diagrams and identify the replacement material required (circuit breaker rating, IP cable gland, engraved labelling).
- Execution of the rectification workWork physically on the cabinet or circuit: redoing connections to the specified torque with a torque wrench, replacing defective devices, readjusting equipotential bonding.
- Internal re-measurements and formalisation of the rectification noticeRepeat the loop, tripping or insulation measurements on the corrected parts. Complete the defect rectification notice with the new measured values, signed by the holder of the installation authorisation.
- Possible re-inspection and issue of the final safety reportSubmit the supporting documents to the external inspection body. After checking the documents or a re-inspection on site, the inspector issues the final safety report (RS) and sends it to the owner.
- Administrative notification to the distribution network operatorSend a full copy of the endorsed safety report to the competent distribution network operator (DNO) before the legal deadline, definitively closing the installation notification file.
Obtaining the safety report without reservations is the only legally discharging proof for the building owner and the installation electrician with regard to the requirements of the OIBT and the energy distributors. If the defects are not rectified within the deadlines set by the independent inspector, the latter automatically forwards the file to the Federal Inspectorate for Heavy Current Installations (ESTI), which then issues a formal demand accompanied by administrative costs and, where applicable, an order for the distributor to interrupt the energy supply.
Handling technical disagreements and resolving disputes
During an acceptance inspection under the OIBT regime, the intervention of an independent inspector may result in a disputed finding of non-conformity. Under art. 367 CO, after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects. In electrical practice, this finding takes the form of a notice of defects annexed to the inspection report. If the installer disputes the substance of an anomaly — for example the sizing of a protective conductor, the selectivity of a line circuit breaker or the interpretation of a protection zone in a technical room —, structured technical dialogue must take precedence over administrative deadlock.
- Immediate adversarial re-measurementCall the independent inspector to site with the company's measuring instruments (calibrated multifunction installation tester). Repeat the disputed tests — fault loop impedance, prospective short-circuit current, tripping time and threshold of residual current devices — recording the raw values and the measurement method against the distribution diagrams.
- Documentary arbitration according to recognised rulesCheck whether the disputed point stems from an explicit requirement of the NIBT in force when the installation notice was filed or from the inspector's own interpretation. The manufacturers' instructions for switchgear and the technical data sheets of the distribution boards are authoritative in proving the conformity of workshop-assembled switchgear assemblies.
- Referral to the supervisory bodyIn the event of a persistent technical deadlock preventing the issue of the safety report, the complete file is submitted for an opinion to the Federal Inspectorate for Heavy Current Installations (ESTI). The authority rules on the conformity of the installation and notifies its decision to the parties concerned.
Frequently asked questions
Who appoints and pays the independent acceptance inspector?
It is necessarily the building owner or their appointed representative who selects and pays the independent inspection body, which holds an inspection authorisation issued by the federal authority. The installation company that carried out the work may under no circumstances appoint or pay this inspector, in order to rule out any conflict of interest and guarantee the complete impartiality of the conformity verification prescribed by the OIBT.
Which works require an independent inspection on acceptance?
The independent acceptance inspection within six months of commissioning is required for all installations with an inspection interval of less than twenty years under the OIBT. This covers commercial, craft and industrial premises, administrative buildings, public assembly buildings, premises with fire hazard or damp premises, as well as farms. Standard housing with a twenty-year interval is exempt.
Which documents exactly must the installer prepare for the visit?
The installer presents the complete technical file on site: up-to-date single-line electrical diagrams, revised installation plans, the measurement report of the company's own final inspection (continuity of the protective conductor, insulation, loop impedance, residual current tripping), declarations of conformity of the distribution boards, as well as the data sheets of the overcurrent protection devices and surge arresters installed in the main cabinets.
What period is allowed for clearing the notified defects?
The independent inspector usually grants a maximum period of six months to correct the non-conformities found during the visit. Once the rectification work has been carried out by the licensed installer, the latter sends a certificate of defect rectification to the inspector. If the defects compromise people's safety, the operator must act without delay on pain of immediate intervention by the network operator.
Texts and standards cited
- CO art. 367after delivery, the client examines the condition of the work as soon as is practicable and notifies the contractor of any defects; for a building work, the client has 60 days to notify them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); either party may request an examination by experts (para. 2)