Installation: cable routes, switchboards and wiring accessories: the execution reference
Aimed at team leaders, site foremen and electrical installers, this section brings together the execution practices for heavy-current work on Swiss construction sites. From casting conduits into slabs to equipotential bonding, including torque-tightening of busbars and sealing of fire-stop penetrations, it details NIBT-compliant implementation, with no compromise on safety or on coordination with the structural work.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
1 m 50
Maximum trench depth without mandatory shoring or sloping
0,60 m
Minimum burial depth of a power cable under ground not subject to traffic
30 mA
Maximum rated residual current for terminal socket outlets and construction sites
20 %
Minimum modular space reserve to be provided in a distribution board
2,25 m
Height of the upper limit of volumes 1 and 2 above the finished floor in a bathroom
Technical scope of the installation work and construction site interfaces
This section deals exclusively with the physical deployment of heavy-current networks in accordance with the NIBT rules. It covers the embedding of conduits in load-bearing elements, the horizontal and vertical routing of power cables, the mounting of distribution boards and the positioning of terminal wiring accessories. The rules apply to trades and crafts, multi-unit housing, commercial buildings and industrial infrastructure.
- Pulling and laying conduits in slabs before pouring, wall chases and openings, in coordination with the structural work.
- Installation of cable trays, ladders, screen separators and fire-stop sealing with approval marking.
- Assembly, fixing and torque-tightened connection of main or secondary switchboards, including temporary distribution.
- Positioning of wiring accessories in special zones: bathroom volumes, technical rooms and outdoor areas.
The first requirement remains operational safety and maintainability. Any recessed or concealed device must remain identifiable, accessible and protected against mechanical and thermal damage in accordance with the recognised rules of electrical engineering.
Execution path: from the bare structure to energisation
The logical organisation of the construction site calls for the section to be read in order. The installer starts with the heavy interactions with masonry and reinforced concrete, continues with the main feeders in technical shafts, then completes the secondary distribution and the sensitive connections.
- Structural work phase and openingsIntegration of conduits into slab reinforcement in accordance with the engineering instructions, and marking out of the permissible chases to preserve the structural strength of the masonry.
- Infrastructure and compartmentationInstallation of cable trays respecting the fill ratio, then certified sealing of fire-rated partition penetrations with the required labelling.
- Switchboards, branch connections and specific wiring accessoriesFixing of enclosures, modular spare capacity, torque-tightening of terminal blocks, accessibility of junction boxes and strict compliance with the volumes in wet rooms.
- Outdoor networks and temporary installationsBurial in a secured trench, weather-protection ratings and rigorous management of temporary supply boxes.
📘 Chapters in this section 10
Embedding: conduits in slabs, permissible chases and coordination with structural work
Secure your conduits under reinforcement and control wall chases without weakening the structural stability of the structural work.
Installation: conduits, distribution boards and switchgearCable tray: fill rate, separation and fire resistance
Calculate the correct fill of cable trays to prevent overheating and harmful interference.
Installation: conduits, distribution boards and switchgearFire-rated wall penetration: certified firestopping, marking and documentation
Carry out approved fire-stop sealing to ensure compliance with the requirements of the building insurer.
Installation: conduits, distribution boards and switchgearTightening connections: prescribed torque, re-tightening and the resulting heating
Tighten your conductors with a torque screwdriver to eliminate any risk of overheating or electrical fire.
Installation: conduits, distribution boards and switchgearSiting a switchboard: accessibility, expansion reserve and environment
Position distribution boards so as to maintain technical accessibility and the planned modular reserves.
Installation: conduits, distribution boards and switchgearJunction boxes: staying accessible, and the connections that must never be buried
Arrange your junction boxes so that they can be inspected, to avoid inaccessible and non-compliant connections.
Installation: conduits, distribution boards and switchgearBathroom: safety zones and the equipment permitted in each
Delineate the shower or bath volumes precisely so as to install only authorised equipment.
Installation: conduits, distribution boards and switchgearBuried cable: depth, bedding layer, warning mesh and mechanical protection
Dig, lay the sand bed and unroll the warning mesh to ensure the durability of your outdoor supplies.
Installation: conduits, distribution boards and switchgearOutdoor lighting: protection rating, condensation and fixing
Choose the right protection ratings for your outdoor luminaires and drain off destructive condensation.
Installation: conduits, distribution boards and switchgearSite distribution board: residual-current protection, periodic inspection and extension leads
Check the residual current devices and the condition of the cables to secure the construction site power distribution on a daily basis.