Key takeaways
- Every metallic pipe entering the building envelope must be connected to the main busbar.
- The minimum cross-section of the copper main equipotential bonding conductor is six square millimetres.
- The connection to the foundation slab earth electrode is made outside the concrete using a suitable clamp.
- The disconnection busbar must remain accessible without heavy tools to allow periodic inspection.
Identify and connect all conductive parts and incoming pipework
The function of the main equipotential bonding is to eliminate dangerous potential differences between electrical exposed conductive parts and conductive parts foreign to the building. According to the NIBT, this fundamental protective measure prevents the appearance of a touch voltage in the event of an insulation fault or potential rises coming from outside. The working principle on the construction site is exhaustive: every metallic part entering the built volume or forming the primary framework must be connected to the main earthing busbar.
- Metallic drinking water pipes as soon as they enter the building, immediately upstream of the meter or with a flexible bridging connection around it.
- Steel-tube internal gas pipes, immediately after the insulating inlet fitting prescribed by the gas distributor.
- Risers and main headers of central heating, as well as chilled-water or air-conditioning circuits.
- Main elements of the steel structure, accessible reinforcement of lift shafts and load-bearing metal frameworks.
- Connection stub left by the mason for the foundation earth electrode embedded in the concrete slab.
For gas networks, the position of the equipotential bonding clamp requires strict attention. The bonding conductor is always connected on the inside of the building, directly downstream of the dielectric insulating piece installed by the gas distributor. Connecting upstream would inject fault or stray currents into buried networks under cathodic protection, which breaches the operating rules for underground networks. On water risers, the connection must bypass the water meter and filters with a braid or a green-yellow conductor to prevent any break in the circuit when they are removed for maintenance.
The slab reinforcement, installed as an earth electrode by the structural work trade, comes out in the technical room as a galvanised or stainless steel strap. The electrician makes the junction between this stub and the main busbar using a lug clamped with stainless steel bolting or a dedicated clamp, checking that there is no paint or residual laitance on the contact surface.
Size the bonding conductors and install a compliant disconnection busbar
The sizing of the main equipotential bonding conductors follows the NIBT requirements on thermal and mechanical withstand. These cables are not sized to carry a continuous service current, but to discharge fault currents instantly without melting or harmful heating of the walls they pass through.
| Cross-section of the installation's main PE (copper) | Minimum cross-section of the main equipotential bonding conductor (copper) | Condition of application on the construction site |
|---|---|---|
| Up to 16 mm² | 6 mm² | Absolute minimum value permitted by the NIBT, typical for a detached house. |
| 25 mm² or 35 mm² | 10 mm² or 16 mm² | Calculated as half the PE cross-section, without going below 6 mm². |
| 50 mm² and above | 25 mm² | Maximum ceiling required for copper main equipotential bonding. |
The conductor used is systematically an insulated copper conductor with a green-yellow sheath, or solid bare copper if the route runs along continuous metal cable trays. Its route must be direct, without unnecessary loops, and mechanically protected in rigid conduit in areas exposed to impact up to a minimum height of one metre fifty above finished floor level.
- Mechanical fixing of the busbarInstall the main earthing busbar on a solid wall, in the basement or in the electrical technical room, at a height between 0.40 m and 1.20 m above the floor.
- Connecting the conductorsCrimp suitable tubular lugs onto each stranded copper cable before tightening under a cap nut or metric screw with a serrated washer.
- Individual markingLabel each conductor on the busbar with an indelible sleeve clearly indicating the connected part: Earth, Water, Gas, Heating, Slab.
- Checking the disconnectionMake sure the measuring link or earth disconnector can be opened with a tool in order to carry out the loop or resistance measurement.
Location, fixing and marking of the main earthing busbar
In new buildings or heavy renovations, the main equipotential bonding busbar is the central safety node of the earthing network. According to the NIBT, this component must remain accessible at all times to allow visual checks, separation measurements and periodic tests. It is always installed in the immediate vicinity of the main electrical entry or in the main technical room, protected from the risk of mechanical impact and corrosion from water splashes or chemical fumes.
The busbar is firmly plugged and screwed onto a masonry wall or fixed to the supporting structure of the main distribution board. The electrician must ensure an ergonomic working height, generally between 0.40 m and 1.20 m above finished floor level. The main equipotential bonding conductors, with a green-yellow sheath or as solid tinned copper conductors, must converge on the busbar without unnecessary loops, along straight routes and mechanically protected in rigid conduit up to the entry to the terminal block.
Marking of each connection is a strict maintenance and safety requirement. An undocumented main busbar prevents safe operation and complicates the drafting of the safety report required by the OIBT. Each screw terminal, clamp or connection pad must bear an engraved plate or an indelible label stating unambiguously the pipe or structural element connected.
| Connected element | Origin / Interface trade | Recommended conductor type | Usual minimum cross-section |
|---|---|---|---|
| Foundation earth (slab) | CFC 211.1 (galvanised/stainless steel flat or round stub) | Bare or tinned copper, direct connection | 16 mm² Cu (or 75 mm² steel) |
| Drinking water entry | Incoming metallic pipe (after meter/valve) | Flexible or rigid green-yellow insulated copper | 10 mm² Cu to 25 mm² Cu |
| Natural gas entry | Incoming metallic pipe (insulating joint bridged) | Green-yellow insulated copper | 10 mm² Cu to 25 mm² Cu |
| Heating risers | Metallic flows and returns in the boiler room | Green-yellow insulated copper | 10 mm² Cu to 16 mm² Cu |
| Steel structure or metal sections | Load-bearing structural elements of the building | Green-yellow insulated copper or flat strip | 16 mm² Cu to 25 mm² Cu |
Mechanical connection procedures and continuity measurements before commissioning
Connecting the foundation earth stub — placed in the concrete by the CFC 211.1 masons — requires careful cleaning of the transition piece. If the stub is galvanised or stainless steel, the electrician uses a bimetallic crimp lug or a specially profiled clamp connector to avoid any galvanic couple between copper and steel. The employer ensures that the general occupational safety rules prescribed by art. 82 LAA are applied to prevent the risks of cuts or strain when forming these large-section conductors.
On incoming metallic pipes (water, gas, industrial pipes), the connection must be made as close as possible to the point where the pipe enters the slab or exterior wall. The earthing clamps must be sized to the exact diameter of the pipe. Before tightening, the pipe is mechanically stripped to remove paint, protective varnish or oxidation deposits, ensuring perfect metal-to-metal contact. For mains gas, the equipotential bridging is made strictly downstream of the dielectric insulating piece installed by the fluid distributor, unless local regulations state otherwise.
- Preparing the support and fixing the clampsStrip the metallic pipe down to bare metal on the clamp seating area. Fit the clamping strap or solid clamp without crushing the pipe and tighten the fasteners to the recommended torque.
- Routing the bonding conductorsPull the conductors in protective conduits. Avoid sharp edges to preserve the green-yellow insulation and crimp ring lugs suited to the terminals of the main busbar.
- High-current continuity measurementCarry out the low-resistance measurement with a test current of at least 200 mA between the main busbar and each metallic contact point.
- Tightening the disconnection busbar and recordingRetighten the removable measuring link of the earth busbar. Record the overall earth resistance value obtained in the internal inspection report.
The NIBT requires rigorous verification of electrical continuity before the installation is handed over to the client. This measurement is carried out with a calibrated installation tester capable of delivering an open-circuit voltage between 4 V and 24 V and a direct current of at least 200 mA. Any result above the practical threshold of 0.2 Ω must be examined immediately: faulty mechanical tightening, oxidation of the clamp or internal break of a strand. Compliance of the whole conditions the issue of the final safety report required for first commissioning.
Handling equipotential bonding non-conformities and rework on the construction site
On new construction sites or heavy renovations, defects in the main equipotential bonding often result from late interventions or poorly coordinated interfaces. The most frequent case is a main earthing busbar made inaccessible: boxed in behind a service duct without an access hatch, hidden by a distribution cabinet or sealed behind basement thermal insulation. The electrician must refuse this situation. The equipotential busbar must imperatively remain accessible without tools for the periodic inspections and insulation measurements required by the ordinance on low-voltage electrical equipment and the ordinance on low-voltage electrical installations (OIBT).
Another common setback is the unexpected appearance of plastic sections (PE, multilayer) on incoming metallic water or gas pipes, installed by the plumber or heating engineer. As soon as an insulating sleeve or dielectric fitting interrupts the galvanic continuity, the connection downstream becomes ineffective against touch voltages introduced from outside. The electrician must then fit the clamp immediately upstream of the insulating break, as close as possible to where the pipe enters the building envelope, and bridge if necessary the internal conductive sections connected to the distribution network.
When the continuity measurement with a milliohmmeter (test current of at least 200 mA according to the NIBT) exceeds the limit value of 0.2 ohm between the busbar and a conductive part, the cause is almost always a poorly prepared contact surface. Earthing clamps fitted directly onto oxidised copper pipes, painted steel or rusty slab reinforcement generate excessive contact resistances. The metal should be wire-brushed to bright metal and the clamps tightened mechanically with suitable stainless steel bolting.
If the foundation earth stub from the slab has been sheared off or forgotten by the mason when pouring, the electrician records the defect in writing to the site management. He then installs a replacement earth electrode using a conductor buried in an external loop or copper-clad steel vertical rods, before connecting everything to the main busbar and drawing up the final safety report.
Frequently asked questions
Where should the earthing clamp be placed if the water supply enters in PE and then continues in copper?
If the public service pipe arrives in PE, it is not an external conductive pipe within the meaning of the NIBT. Main equipotential bonding does not apply to PE. However, as soon as the internal distribution switches to metallic pipe (copper, steel), this internal pipework must be connected to the main busbar to prevent any accidental energisation, fitting the clamp directly on the first metallic header after the meter.
What minimum copper conductor cross-section must be installed for the main bonding?
According to the NIBT, the minimum cross-section of the copper main equipotential bonding conductor is half that of the main protective conductor of the installation, with an absolute minimum cross-section of 6 mm² and no obligation to exceed 25 mm² of copper. In practice, on houses and small rental buildings, a 16 mm² copper cross-section in rigid conduit protects against mechanical damage and covers most standard installations.
Is it permitted to loop heating and water pipes onto a single cable?
Tapping from one pipe to the next without cutting the conductor is mechanically accepted using specific through-type clamps. However, the breaking or removal of a clamp during later maintenance must never interrupt the continuity of the bond to the other elements. For collective installations, it is strongly recommended to run a dedicated continuous copper line from the main busbar to each major conductive element (water, gas, heating risers).
How do you identify and mark the main earthing busbar in the technical room?
The main busbar must carry clear, indelible labelling bearing the wording 'Earthing busbar / Main equipotential bonding'. Each connected conductor must be marked by a sleeve or label identifying its exact destination: cold water, gas, heating flow, slab reinforcement, surge arrester. This rigorous identification avoids erroneous disconnections during periodic OIBT inspections and allows the inspection body to verify the presence of all prescribed conductors.
Texts and standards cited
- CP art. 229breach of the rules of the art of construction: anyone who, while directing or carrying out a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or physical integrity of persons faces a custodial sentence of up to five years or a monetary penalty; if through negligence, up to three years or a monetary penalty.