🧱 CFC 232Earthing, equipotential bonding and lightning protectionChapter 10 of 10 in the section

Periodic earth testing: intervals, traceability and change over time

An earth electrode suffers oxidation, ground settlement and moisture variations without any visible external sign. This chapter shows you how to plan periodic testing campaigns, record readings in a reliable technical register, methodically compare the measured resistance with the initial value and trigger the essential corrective measures as soon as drift compromises the automatic disconnection of the protective devices.

Key takeaways

  • Testing intervals range from one to twenty years depending on the usage category of the building.
  • The register records each ohmic value, the measurement method used and the soil moisture conditions.
  • A rigorous comparison with the initial acceptance value reveals corrosion or drying-out of the electrode.
  • Any unexplained increase requires opening the disconnection link, checking the connections and adding supplementary electrodes.

Plan periodic measurements and record the parameters in the technical register

The earthing connection, whether a foundation earth ring connected by the electrician or electrodes driven into the ground, gives no visual sign of wear when it deteriorates. Yet soil conductivity varies with the groundwater regime and metallic connections oxidise under the chemical action of their surroundings. In accordance with the requirements of the Ordinance on Low-Voltage Installations (OIBT), the owner must have their installations checked periodically by an independent controller or an independent inspection body. Testing intervals depend on the use of the building: they are set at one year for construction sites, five years for premises open to the public or presenting particular fire risks, ten years for administrative and craft buildings, and twenty years for standard individual and rented dwellings.

Earth testing intervals according to the use of the site
OIBT intervalBuilding useWhat the earth test is for
1 yearConstruction sites and temporary structuresCheck the earth loop exposed to the severe mechanical stresses of structural work.
5 yearsPremises open to the public and damp roomsDetect early oxidation and ensure instant dissipation of fault currents.
10 yearsOffices, commercial premises and workshopsMonitor the stability of the impedance as new technical cabinets are added.
20 yearsIndividual and multi-occupancy residential buildingsConfirm the continuity of the foundation earth electrode and the absence of mechanical breaks.

To make these measures last, the installation electrician keeps an earthing register up to date, stored in the main distribution board. This booklet brings together the successive readings and states the method applied: the three-spike method at 62 % for electrodes that can be isolated, fault-loop measurement between phase and protective earth for live networks, or double-clamp measurement for closed loops. The register must record the identifier of the test instrument, the date of its last calibration and the moisture state of the soil at the time of measurement. Dry or frozen ground skews results upwards, whereas heavy rain temporarily lowers them. Art. 3 OPA requires the employer to take protective measures that comply with the recognised rules of technology; during measurement, the operator must therefore wear insulating gloves when handling the open disconnection link.

Interpret the change in ohmic values and correct earth drift

An earth resistance value cannot be judged satisfactory on its absolute figure alone. It must always be compared with the reference value established at initial acceptance, recorded in the safety report (RaSO). If an earth measured at 4 ohms at commissioning reads 14 ohms ten years later, the installation is suffering critical degradation, even if the measured value remains theoretically compatible with the tripping threshold of a residual-current circuit breaker. This abnormal increase signals internal deterioration: corrosion of the galvanised steel connection lug, partial break of the earth conductor under its sheath, or lasting drying-out following recent perimeter drainage. According to the NIBT, any drift above 50 % of the initial resistance requires an in-depth diagnosis and the immediate implementation of corrective measures.

  1. Visual inspection and mechanical cleaning of the disconnection linkOpen the disconnection link after lock-out or after checking with a clamp meter that no residual current is present. Brush the clamping surfaces, remove any trace of scale or rust and replace corroded cadmium-plated steel fixings with new bolts tightened to the specified torque.
  2. Splitting the measurements between ground and networkCarry out a separate measurement directed only at the buried earth electrode, then a measurement towards the main earth collector. This separation isolates the source of the drift, whether it lies in the ground loop or in a loosened equipotential connection.
  3. Adding vertical rods in parallelIf the resistance of the existing electrode exceeds the tolerances, drive copper-clad steel rods using an electric hammer drill. Space them at least twice their driven length apart to prevent mutual interference between their potential cones.
  4. Final connection and end-of-works recordingInterconnect the electrodes using a bare copper conductor of suitable cross-section and stainless steel clamps. Repeat the overall measurement, close the disconnection link again and immediately enter the new characteristics in the technical register.

Building up the operating register and comparing with reference values

Monitoring an earth electrode relies on consistent metrological follow-up. A buried conductor or an electrode embedded in blinding concrete cannot be examined directly by eye. The measurement register is therefore the only objective witness to the ageing of underground connections. This technical document, kept with the installation drawings and attached to the safety report, gathers the history of every periodic test carried out on the building.

Typical recording grid for the earthing test logbook
Recorded parameterMeasured data / ConditionTest conditionDeviation found
Overall earth resistance (RA)Value in ohms (3-wire or loop measurement)Disconnection link open / closedDeviation in % from initial acceptance
Continuity of the main conductorResistance in ohms (threshold < 0.2 ohm)Minimum test current of 200 mAChange since the last test
Soil moisture conditionDry, damp, waterloggedWeather over the previous 15 daysSeasonal correction factor
Mechanical integrity of the terminalsOxidation, tightening torqueVisual inspection and torque wrenchTraces of galvanic corrosion

A rigorous comparison with the original values requires repeating the same test protocol as at the initial acceptance of the installation. Any change in the position of the auxiliary spikes during a measurement by the voltmeter-ammeter method (62 % method) distorts the analysis of the change over time. If the measured resistance rises by more than 20 % to 30 % without extreme drought to explain it, degradation of an underground connection or corrosion of the reinforcing steel is established.

Methodical diagnosis and technical actions when resistance drifts

When a periodic test reveals abnormal drift in earth impedance or a break in continuity, the electrician carries out an investigation procedure by elimination. The aim is to locate whether the failure comes from the measuring link, from the transition point between copper and steel in the concrete, or from the surrounding soil. The employer ensures that the prevention measures required by art. 82 LAA are applied to protect the fitter against any risk of electric shock while the disconnection link is temporarily opened.

  1. Isolating the earth disconnectorCheck that there is no leakage current using a clamp ammeter on the earth conductor before opening the disconnection link. Open the connection to separate the building earth from the distribution network.
  2. Continuity test of the equipotential connectionsMeasure the continuity between the main earth bar and the raft reinforcement left connected in waiting. A resistance above 0.2 ohm reveals a loosened connection or a mechanical break under the sheath.
  3. Checking the above-ground transition zonesRemove the galvanised steel or copper connection lug. Remove any trace of oxidation from the contact surfaces, replace corroded fixings with A4 stainless steel bolts and apply a neutral conductive grease.
  4. Countermeasure using a substitute electrodeIf the circuit built into the foundations shows a degraded, irreversible ohmic value, drive one or more vertical copper-clad steel earth rods outside the raft, then connect them in parallel to the main bar.

If drift in a foundation earth electrode is confirmed — often following external waterproofing work, a lowering of the water table or a break due to galvanic corrosion — the only corrective solution is to recreate a contact surface with the loose soil. The installation electrician sizes a set of driven vertical piles or an external perimeter trench loop, laid in bare copper cable of at least 50 mm². Connection to the main earth terminal then requires an immediate update of the schematic diagrams and entry of the corrective work in the technical register.

Emergency protocol and remedial work on a failed earth

A mechanical break in an earth conductor or a sudden jump in loop impedance during a periodic test immediately turns the installation into a critical source of danger. When the measured resistance departs from the initial values in the technical file to the point of compromising automatic disconnection by the protective devices, the technician must suspend all approval. Under art. 365 CO, the contractor informs the client immediately when circumstances compromise the proper execution of the installations. On site, the electrician records the abnormal value on the test report, notifies the operator in writing without delay and posts a danger notice on the earth disconnector.

  1. Isolation and metrological verificationCheck the connections of the disconnection link and repeat the measurement with the earth tester or by live loop measurement to rule out a contact fault on the test probes or a weak instrument battery.
  2. Searching for a physical discontinuityCheck the continuity between the main collector and the foundation electrode using a milliohmmeter. Visually inspect the steel-copper clamping splices, which are prone to galvanic corrosion.
  3. Installing a substitute earth electrodeIf the foundation reinforcement is cut or inaccessible, drill at the foot of the building to bury vertical copper-clad steel rods or lay a strip in a trench until a compliant value is obtained.
  4. Updating the operating registerEnter the date of the work, the repair method, the materials used and the new ohmic value measured in the technical register handed over to the owner.

In the case of progressive degradation without a clear break, due for example to geological drying-out or slow corrosion, the electrician must not wait until the disconnection threshold prescribed by the NIBT is exceeded before proposing remedial work. The operating register serves precisely to demonstrate this rate of wear to the property management. Continuous drift over two successive tests requires the preventive driving of a supplementary electrode in parallel, restoring lasting equipotentiality before an insulation fault appears on the network.

Frequently asked questions

How should you react if the original earthing register cannot be found during the test?

Immediately reconstitute an operating technical file. Carry out an accurate measurement of the earth resistance with the disconnector open and of the continuity of the main equipotential connections. Record the current results, the visual condition of the protective conductors, the details of the test instrument and the date. This contradictory record will serve as the official zero reference for the subsequent periodic tests required by the Ordinance on Low-Voltage Installations.

What technical action should be taken if the earth value doubles during a summer drought?

Drying-out of the soil mechanically increases the resistivity of the surface ground. If the measurement remains below the threshold that triggers the protective devices according to the NIBT, note the climatic factor in the register. If the value exceeds the safety limit, the existing electrode is too shallow. Driving vertical rods deep down is necessary to reach the damp geological layers and stabilise the value all year round.

Can a supplementary rod be connected to a foundation earth without opening the link?

The disconnection link must absolutely be opened before any additional connection. This avoids stray currents during measurement and allows the failing electrode and the new supplementary earth to be characterised separately. Once the rod is connected with bare copper of suitable cross-section, close the link again and measure the overall combined resistance so that it can be recorded in the technical register.

What testing interval applies to the earth of a craft building with a workshop?

The testing interval depends on the use of the premises under the OIBT requirements. A building for craft use with workshops or stores presenting specific risks is generally subject to a testing interval of ten or five years, compared with twenty years for purely residential use. The installation manager must appoint an independent inspection body at each due date to inspect the equipotential bonding.

Texts and standards cited

  • CO art. 365material and ground: immediate notice to the client if a circumstance compromises proper execution