Skip to content
Website
🧱 CFC 232Installation: conduits, distribution boards and switchgearChapter 2 of 10 in the section

Cable tray: fill rate, separation and fire resistance

This chapter details the rules for installing cables on cable trays for the electrician-installer. You will learn how to calculate the fill rate to limit the permissible temperature rise according to the NIBT, how to maintain the standard spacing from extra-low-voltage cables, and how to position brackets and hangers to ensure mechanical strength without excessive deflection under maximum load.

Key takeaways

  • Bundling cables together drastically reduces their current-carrying capacity through direct mutual heating.
  • Laying cables in a single layer ensures optimal heat dissipation and prevents sheath overheating.
  • A metal partition or sufficient spacing prevents induced interference on extra-low-voltage cables.
  • The bracket spacing depends on the load per unit length, to prevent permanent deformation of the supports.

Controlling the fill rate and heat dissipation

In a heavy-current electrical installation, thermal management on a perforated cable tray or cable ladder determines the durability of the insulation and fire protection. When current flows through the copper or aluminium core, the Joule effect produces direct heat generation. In an insulated cable laid alone in free air, this heat is easily dissipated by natural convection and radiation. However, as soon as several cables run together, mutual heating sets in: the air stagnates between the sheaths and the local ambient temperature rises rapidly. The NIBT deals with this phenomenon by applying grouping correction factors that reduce the current-carrying capacity originally assigned to each conductor.

The fill rate expresses the ratio between the sum of the overall outer cross-sections of the cables and the usable cross-section of the cable tray, defined by its usable width multiplied by the height of its side rails. In site practice, the electrician-installer must never fill a tray to the brim. A physical fill rate above 40 % inevitably leads to disorderly overlapping. Stacking in multiple layers heavily penalises sizing: the derating factor can fall below 0.60, which forces the copper cross-section to be increased by one or two standard sizes to carry the same power without overheating. Large-section main power conductors must always be laid in a single layer, ideally spaced apart by a distance equal to their own outer diameter.

Impact of the installation method on the derating factor according to the NIBT
Installation configurationNIBT grouping factorDirect thermal impactConsequence for the copper
Single layer, touching0.70 to 0.80Adequate dissipation through the upper faceFrequent increase of one cross-section size
Single layer spaced by one diameter1.00Optimal natural ventilation around each sheathNominal cable cross-section preserved
Multiple stacked layers0.50 to 0.65Heat trapped at the core of the bundleVery heavy oversizing of the conductor

Spare space is the second decisive parameter. Providing a geometric reserve of 20 to 30 % on the tray base makes it possible to accommodate installation extensions without saturating the cable tray or calling into question the thermal conditions of the cables already in service.

Separating extra-low-voltage cables and sizing the mechanical fixings

Running heavy-current power cables and signal transmission cables together poses a major risk of electromagnetic pollution. Switching transients, load variations on frequency converters and harmonic currents flowing in the live conductors generate disturbing magnetic and electric fields. To prevent industrial interference from being induced in extra-low-voltage links, the heavy-current installer must observe strict rules of physical coexistence. The NIBT and the electromagnetic compatibility rules prescribe continuous spatial separation or the interposition of a conductive metal shield.

  • Maintain a clearance of at least 200 mm between power cable trays and the supports reserved for extra-low-voltage cables.
  • Install a continuous metal dividing partition mechanically fixed to the base of the shared cable tray.
  • Connect the tray and its dividing partition to the building's main equipotential bonding network at each end.
  • Make the unavoidable crossings between power lines and signal lines strictly at right angles (90 degrees).

The mechanical strength of the installation depends on the sizing of the hangers, wall brackets and pendants. Misjudging the loads leads to sagging of the profiles, dislodging of the fishplates and pull-out of the anchors from the concrete. Art. 229 CP punishes anyone who, intentionally or through negligence, breaches the recognised rules of the building trade and thereby endangers the life or physical integrity of persons. The safety of runs suspended above traffic routes and work areas directly engages the responsibility of the team leader.

  1. Assessing the load per unit lengthCalculate the total mass, including the dead weight of the galvanised steel cable tray, the weight per metre of all installed conductors and a 20 % overload reserve for future cables.
  2. Positioning and spacing of the bracketsPosition the brackets at regular spacing of 1.20 m to 1.50 m according to the manufacturer's load curves, always placing a support within 200 mm of joints and changes of direction.
  3. Anchoring into the load-bearing structureFix the stirrups and base plates to the ceiling or concrete wall with metal anchors suitable for cracked concrete, tightened with a torque wrench to the recommended torque.

Thermal derating and practical management of cable bunching on cable trays

The accumulation of insulated conductors or sheathed cables on a single carrying support restricts the natural removal of the heat released by the Joule effect. In Switzerland, the sizing of copper or aluminium cross-sections is based strictly on the rules of the NIBT. As soon as a continuous layer or a stack exceeds a single touching layer, air no longer circulates freely around the sheaths. The temperature at the core of the bundle rises, prematurely degrading the dielectric strength of thermoplastic or thermosetting insulation and increasing the linear resistance of the conductors.

Usual reduction coefficients according to the installation method on perforated cable tray (reference ambient temperature of 30 °C according to the NIBT)
Cable arrangementNumber of three-phase circuitsStacking / grouping factorEffect on minimum cross-section
Single touching layer on perforated tray1 to 30.80 to 0.85Rarely an increase of one copper cross-section size
Single touching layer on perforated tray4 to 60.72 to 0.75Frequent increase from 1.5 mm² to 2.5 mm² or from 2.5 mm² to 4 mm²
Single touching layer on perforated tray9 and more0.60 to 0.65Almost always moving up to the next standard cross-section
Cables piled loosely without spacing (multiple layers)Irrelevant0.50 to 0.60Risk of critical heating: rated current halved
Single spaced layer (spacing of at least one diameter)Irrelevant1.00No thermal derating, optimal dissipation by convection

To avoid prohibitive oversizing of the cables upstream of the distribution boards, the golden rule is to maintain a ventilated single-layer arrangement. The electrician-installer takes care never to stack heavy power cables, such as the main cabinet feeders. Polyamide or metal cable clamps must in no case crush the protective sheaths, at the risk of creating localised hot spots through mechanical constriction of the insulation.

Electromagnetic coexistence and mechanical strength of power cable layers

The physical separation between power circuits and telecommunication or control cabling meets electromagnetic compatibility requirements. Switching-on transients, the starting of heavy inductive loads and harmonics circulating in high-amperage risers induce disturbances by capacitive and inductive coupling in neighbouring circuits. Even if the heavy-current electrician does not carry out the pulling of data twisted pairs, it is their responsibility to provide an infrastructure that complies with the recognised rules of the trade.

  • Physically separate cable trays: maintain a distance of at least 200 mm to 300 mm of free air between the heavy-current infrastructure and the supports reserved for extra-low-voltage cables.
  • Use of a single compartmentalised tray: mandatory insertion of a continuous metal dividing partition, electrically connected to the profile.
  • Galvanic continuity of the support: strict equipotential bonding of all cable tray sections by means of perforated fishplates tightened to the required torque or by earth braids.
  • Connection to the main protective conductor: methodical earthing of the metal structures at both ends and at branches, in accordance with the equipotential bonding requirements.

The mechanical assembly of the wall brackets, slab pendants and threaded cross-members must absorb the dead weight of the sheet metalwork plus the cumulative load per unit length of the copper. The spans between two brackets generally range from 1.20 m to 1.50 m to ensure that there is no residual sag exceeding the manufacturer's permissible tolerance. An asymmetrical load caused by an overly massive bundle on one edge can twist and deform the support, compromising the stability of the whole.

  1. Spatial distribution across the usable widthPlace the largest-section power conductors along the outer edges to relieve the central bending moment, while reserving the middle strip for secondary control cables.
  2. Fixing the metal partitionBolt the intermediate shielding plate without any break in contact with the perforated base to screen the low-frequency radiation generated by the heavy current.
  3. Final visual check and balancingCheck that there is no unplanned overlapping, that there is thermal clearance under the fixing clamps and that the installation is stable before the final fitting of the protective covers where they are required.

Handling non-conformities: thermal overload, proximity and mechanical sagging

When an existing or newly installed cable tray shows a disorderly pile-up, the risk of critical heating and premature deterioration of the insulation requires immediate action. According to the NIBT, the reduction factors for grouping of conductors collapse as soon as the cables are piled loosely on top of one another instead of lying in a single ventilated layer. If a construction site inspection reveals an excessive fill rate preventing any convective dissipation, the site foreman must refuse the addition of new links and record the anomaly in the site diary.

  1. Geometric and mechanical findingsCheck the residual sag of the brackets and suspension rails. If the sag exceeds the tolerances or if the spacing between brackets is excessive, the mechanical strength is degraded. At workstations and passages, art. 17 OTConst requires measures to be taken so that workers are not endangered by falling materials.
  2. Derating calculation and thermographyRecord the temperatures of the cable layer at nominal load. If the temperature rise exceeds the permissible limits set by the NIBT, the feeders must be reassigned to an auxiliary run or the ratings of the upstream circuit breakers recalculated.
  3. Reinforcing the supports and compartmentalisingAdd threaded rods or intermediate brackets to bring the span between supports below 1.50 m. Install a continuous metal partition fixed with self-drilling screws to maintain the required distance from third-party cabling and restore reliable physical separation.

Any structural modification or rework of a cable layer requires rigorous consultation with the site management before additional cables are pulled. The electrician-installer takes care to distribute the masses evenly across the usable width of the cable tray, thereby preventing any asymmetrical torsional moment on the wall brackets. Controlled tightening of the clamps and systematic earthing of every assembly element guarantee protection continuity and adequate heat dissipation of the whole.

Frequently asked questions

What should be done if an existing cable tray is already 100 % full?

Adding new conductors to a saturated cable layer is strictly prohibited. According to the NIBT, stacking cables cancels heat dissipation and leads to destructive overheating. The installer must lay a second cable tray in parallel or above, observing a minimum vertical clearance of 200 mm between profiles. This clearance guarantees the air circulation needed for convective cooling and preserves the accessibility required for the building's future cable pulling.

What minimum distance must be maintained between power cables and control cables?

Where power conductors run alongside signalling cables without a common shield, a minimum distance of 50 mm in air is required. Where there is not enough space on the profile, installing a continuous metal dividing partition connected to the protective conductor is mandatory according to the NIBT. This physical separation prevents parasitic induction caused by peak currents while also preventing direct heat transfer from a hot cable layer to the weak circuits.

How should you react if a cable tray support begins to sag visibly?

Visible sagging signals an excessive weight load or an excessive span between brackets. At workstations and passages, art. 17 OTConst requires measures to be taken so that workers are not endangered by falling materials. The installer must put up temporary shoring to secure the area. Then the supports must be doubled by reducing the spacing to below 1.20 m, and threaded hangers must be anchored to the ceiling before any new cable pulling.

Why is it prohibited to tie heavy power cables with simple plastic cable ties?

Standard plastic cable ties quickly degrade under the combined effect of the heat given off by the cables and thermal ageing. In the event of a short circuit, the electrodynamic forces snap these fragile ties instantly, violently throwing the conductors out of the cable tray. For large-section cables, the NIBT and the recognised rules of the trade require the use of metal stirrups or reinforced clamps that guarantee mechanical retention under stress.

Texts and standards cited

  • OTConst art. 17protection against the collapse of building elements or the fall of objects and materials: at workstations and passages, measures must be taken so that workers are not endangered.

In the same section