🧱 CFC 215Corrosion protection and fire resistanceChapter 1 of 10 in the section

Corrosivity category: read the environment to choose paint system

The durability over time of a steel framework or load-bearing structure depends directly on the analysis of its exposure environment. This chapter provides steel constructors with the rigorous method to qualify the corrosivity category of the structure, set the targeted lifespan before first major maintenance, and specify the total dry film thickness of the required paint system.

Key takeaways

  • Environmental analysis according to standard ISO 12944 dictates the choice of the anti-corrosion system.
  • The classification from C1 to C5 defines the severity of atmospheric attacks on bare steel.
  • Expected durability sets the required interval of years before the first major paint refurbishment.
  • Total dry film thickness is expressed in micrometres and guarantees the physical barrier against rust.

Assess the atmospheric environment according to standard ISO 12944 to classify the site

In load-bearing steel construction, applying the same anti-corrosion protection to a framework sheltered in a heated industrial hall and to a facade structure exposed to de-icing salt spray alongside a motorway constitutes a serious error. Steel degradation depends on moisture ingress, condensation, the presence of chlorides, or industrial pollutants. Standard ISO 12944 establishes a strict classification of atmospheric environments in order to guide coating dimensioning.

Site corrosivity category
Standardised classification ranging from C1 to C5 (and CX for extreme environments) that measures the aggressiveness level of the atmosphere on unprotected structural steel, assessed by the loss of mass or metal thickness after one year of exposure.

To determine the site corrosivity category, the site foreman or the site manager analyses two distinct parameters: the internal microclimate of the building and the direct external environment. A steel structure located inside a dry building with regular heating falls under class C1 (very low), where the risk of oxidation remains negligible. On the other hand, as soon as the structure crosses the thermal envelope to form a canopy, a composite facade column, or a covered walkway, the category shifts at least to C3 (medium) in a Swiss urban environment, or even to C4 (high) along heavily trafficked road axes where chlorides deposited by winter gritting remain suspended in the air.

Classification of exposure environments according to standard ISO 12944
CategoryAggressivenessExample of indoor environmentExample of outdoor environment
C1Very lowHeated buildings with clean atmosphere (offices, schools)None
C2LowUnheated buildings with condensation (storage depots, halls)Rural or low-pollution atmosphere, low humidity
C3MediumProduction rooms with high humidity (dairies, breweries)Moderate urban and industrial atmospheres
C4HighChemical plants, indoor swimming poolsIndustrial areas, roadside areas with heavy gritting
C5Very highBuildings with permanent condensation and high pollutionVery humid areas, structures exposed to aggressive sea spray

Select the paint system according to durability and total dry film thickness

Once the aggressiveness category is identified, the steel constructor defines the liquid paint or powder coating system by combining the expected durability of the system and the total dry film thickness (NDFT) measured in micrometres. Durability within the meaning of standard ISO 12944 is not a legal guarantee period, but a predictable technical service life before the structure requires a first major maintenance intervention for rust.

The standard subdivides durability into four ranges: low (L, up to 7 years), medium (M, 7 to 15 years), high (H, 15 to 25 years), and very high (VH, over 25 years). On Swiss building and load-bearing facade construction sites, the minimum durability required by the client is generally class H or VH, in order to avoid costly scaffolding during maintenance. To achieve this performance, the choice of resin (zinc epoxy primer, polyurethane finish) and the number of coats must imperatively provide the required total dry film thickness.

  1. 1. Surface preparation by blast-cleaningBlast-clean bare steel until surface preparation grade Sa 2.5 is achieved according to standard ISO 8501-1. An appropriate roughness is mandatory for the mechanical adhesion of the primer.
  2. 2. Application of anti-corrosion primerApply a zinc-rich or two-component epoxy primer in the workshop immediately after blast-cleaning to prevent any flash re-rusting.
  3. 3. Application of intermediate and finishing coatsApply a high-solids epoxy intermediate coat followed by a UV-resistant polyurethane topcoat to stabilise colour.
  4. 4. Inspection of total dry film thickness (NDFT)Check using a magnetic thickness gauge on dry steel that the specified minimum value is achieved across all sections.

In a C1 atmosphere with low durability, a total dry film thickness of 80 micrometres in one or two coats may suffice. Conversely, for an outdoor structure exposed to a C4 environment with very high durability (VH), the total dry film thickness frequently exceeds 280 to 320 micrometres, distributed over three coats. If the delivered substrate or surface condition does not allow the necessary adhesion to be achieved, the contractor relies on the Code of Obligations (CO) regarding material quality and the duty to notify.

If the material supplied by the client or the ground designated by the client is recognized as defective, or if another circumstance jeopardises the regular or punctual execution of the work, the contractor shall inform the client thereof immediately, on pain of bearing the consequences.

art. 365 CO

Qualification of corrosivity categories and environmental analysis

Designing corrosion protection for steel frameworks and composite facade load-bearing structures requires a rigorous characterisation of the exposure environment. An identical S350 steel beam installed in a heated industrial hall with low relative humidity undergoes virtually zero chemical aggressiveness, whereas it suffers accelerated degradation when positioned along a roadway subjected to de-icing salts or in a humid industrial atmosphere. Standard ISO 12944 defines atmospheric environment classes from C1 to C5, allowing classification of the degradation risk for the steel installed by the steel constructor.

For the site foreman and the site manager, site analysis is not limited to overall geographical conditions. Local microclimates play a predominant role: ponding chloride-laden runoff water at the base of a composite facade column exposed to a main road locally alters the corrosivity category. The choice of the anti-corrosion system depends directly on matching the observed corrosivity category with the durability class required by the specifications.

Correspondence between ISO 12944 corrosivity categories and typical steel construction environments
Corrosivity categoryTypical exposure examples (Switzerland)Mass / thickness loss (mild steel, 1st year)
C1 (Very low)Heated buildings with clean atmosphere (offices, schools, dry storage halls).≤ 10 g/m² (≤ 1.3 µm)
C2 (Low)Unheated buildings with possible condensation (warehouses, sports halls), rural areas.> 10 to 200 g/m² (> 1.3 to 25 µm)
C3 (Medium)Manufacturing halls with high humidity, moderate urban and industrial areas.> 200 to 400 g/m² (> 25 to 50 µm)
C4 (High)Industrial areas, structures along major road axes exposed to de-icing salts.> 400 to 650 g/m² (> 50 to 80 µm)
C5 (Very high)Aggressive industrial atmospheres, service ducts, heavily saturated underpasses.> 650 to 1500 g/m² (> 80 to 200 µm)

Expected durability and determination of total dry film thickness (NDFT)

The choice of paint system does not aim for indefinite protection but guarantees a technical service life before the first major refurbishment. Standard ISO 12944 qualifies durability according to four distinct ranges: low (L, up to 7 years), medium (M, 7 to 15 years), high (H, 15 to 25 years), and very high (VH, over 25 years). This durability is not a legal guarantee period granted by the contractor, but a technical planning period intended for maintenance operations on the steel structure.

Total dry film thickness (NDFT - Nominal Dry Film Thickness) constitutes the fundamental quality control parameter in the application workshop and on the erection construction site. To achieve the targeted durability in a given corrosivity category, the anti-corrosion system combines a primer coat (zinc-rich epoxy or alkyd depending on constraints), one or more intermediate coats (high-build epoxy), and a UV-resistant finish coat (polyurethane). If the substrate or steel structure delivered by the client presents surface preparation non-conformities, the steel constructor refers to the duty to notify detailed in CFC 201.

  1. Site identification and atmospheric classificationAnalyse the location of the steel structure (heated interior, exterior, direct exposure to road salt spray) and assign the ISO 12944 corrosivity category (C1 to C5).
  2. Definition of targeted durability with the project managerSet the expected effective service life of the protection system (L, M, H, or VH) based on future accessibility of the structure for maintenance work.
  3. System composition and calculation of total dry film thicknessSelect the chemistry of the coats (zinc primer, epoxy intermediate, polyurethane topcoat) and check the sum of individual thicknesses to achieve the required NDFT.
  4. Acceptance inspection on framework componentsMeasure dry film thickness on sections and connections prior to erection, then record magnetic gauge readings in the quality control report.

During site execution, the contractor remains liable for the conformity of the executed work with the contractual terms. In the event of a dispute or litigation over the execution of steel construction works or delivery deadlines for painted structures, the rights and obligations of the parties are governed by the contract for work under art. 363 CO. Strict adherence to the thickness and preparation specifications provides the enterprise with the best protection against the risks of premature rust appearing on facade sections.

Management of application non-conformities and dry film thickness disputes

On a steel construction site (CFC 215), deviations in total dry film thickness (NDFT) from the requirements of standard ISO 12944 directly compromise the durability of the fabricated structure. When a thickness reading on a framework or composite framing reveals localised under-thickness or excessive over-thickness outside tolerances, the enterprise's response must be immediate and documented. In accordance with the general principles of the Code of Obligations (CO) relating to the execution of the work, the steel constructor must have relative humidity conditions and the surface roughness profile verified before any remedial work.

  1. Mapping non-compliant areasMeasure dry film thicknesses on the framework according to the inspection protocol (80/20 rule of standard ISO 12944) and precisely delineate under-dimensioned areas or those exhibiting curing defects.
  2. Mechanical surface preparationCarry out light sanding or localised abrasive blast-cleaning to abrade the topcoat without damaging the anti-corrosion primer. Remove all dirt, dust, or salt deposits by pressure washing.
  3. Application of the build-up coatApply the compatible finishing system under controlled ambient conditions (steel temperature at least 3 °C above the dew point) to achieve the required total thickness.

When defects result from an inappropriate initial choice of corrosivity category in the tender specification (for example an underestimation of the road or industrial exposure factor), the contractor relies on the general duty of disclosure to notify the client of the risks. For aspects relating to contractual execution liabilities, reference should be made to the Code of Obligations (CO). In the event of persistent disagreement regarding the conformity of the anti-corrosion protection applied to the load-bearing structure, the intervention of an independent industrial coatings expert allows arbitration of the necessary corrective actions.

Frequently asked questions

How should one react if the total dry film thickness measured on the framework is below the specified minimum value?

If the average remains within tolerances but isolated spots fall below 80% of the NDFT required by standard ISO 12944, an additional coat must be applied. The steel constructor dusts off, abrades the surface, verifies the compatibility of the touch-up product, and applies the paint to achieve the specified overall thickness.

Can the anti-corrosion paint system be applied directly on the construction site under freezing temperatures?

No. Outdoor application at low temperatures or high relative humidity compromises the cross-linking and adhesion of the film. Steel temperature must exceed the dew point by 3 °C. In winter, steel framing components must be treated in a heated workshop or under a temporary ventilated enclosure.

What is the difference in requirements between a framework inside a heated hall and a structure exposed to de-icing salts?

A heated hall generally falls under category C1 or C2, requiring low protection with a reduced dry film thickness. A structure exposed to roadside salt spray is classified as C4 or C5, demanding thorough blast-cleaning, a zinc-rich primer, and a significantly higher total NDFT.

Who approves the final choice of paint system in the event of a change in building use?

The project manager and the anti-corrosion specialist revalidate the corrosivity category according to standard ISO 12944. If the environment becomes more aggressive, the steel constructor prepares a technical addendum outlining the new system, the necessary extra thicknesses, and the financial impact, prior to any workshop implementation.

Texts and standards cited

  • ISO 12944Paints and varnishes - Corrosion protection of steel structures by protective paint systems
  • code des obligationsGeneral rules on the execution and defects of the work in the contract for work