Cutting an opening in a steel beam for a duct: allowable zone and trimmer reinforcement

Cutting an opening in a steel beam to pass a building services duct must never be improvised with an angle grinder. This chapter details the precise location of allowable web zones, the limit dimensions without reinforcement according to standard SIA 263, as well as the design of trimmer reinforcements subject to approval by the civil engineer.

Key takeaways

  • Openings in the span must imperatively respect low-shear zones.
  • The opening height must not exceed one third of the web height without calculation.
  • Any cut in the support zones requires reinforcements approved by the civil engineer.
  • Corners of cuts are systematically rounded to eliminate any stress concentration.

Locating the allowable web zone and calibrating limit dimensions

In steel framing or composite floors, integrating ventilation, heating, or sanitary installations frequently requires passing through load-bearing rolled sections or welded plate girders. Uncontrolled core drilling or oxy-cutting on the construction site constitutes serious misconduct that jeopardises the overall stability of the structure. Cutting an opening alters the stress flow: the shear force must be resisted by the residual web sections, while the bending moment generates a local secondary couple known as the Vierendeel effect.

The structural design and verification of the structural safety of steel beams with web openings must incorporate cross-sectional reductions as well as local instabilities due to buckling.

norme SIA 263

To set out an opening without immediately resorting to heavy stiffeners, the steel fabricator targets the zone where the shear force is minimal. On a simply supported beam subject to a uniformly distributed load, this favourable zone is located in the central third of the span. Conversely, support zones, which are subject to maximum shear, and the point of application of a heavy point load are strictly prohibited for unreinforced openings.

Indicative geometric criteria for unreinforced openings according to standard SIA 263
Geometric parameterStandard allowable limitMain mechanical impact
Opening height (h0)≤ 0.35 to 0.50 of the total height hLocal bending in residual chords
Opening length (l0)≤ 1.5 to 2.0 times the height h0Vierendeel effect and risk of lateral-torsional buckling
Distance to supports≥ Total height h of the beamPreservation of shear resistance
Clearance to flanges (tees)≥ 0.15 of height h (min. 50 mm)Capacity of the compression or tension chord
Spacing between two openings≥ Height h0 of the largest openingPrevention of web post buckling

Designing the trimmer reinforcement and approving execution with the engineer

Whenever the opening exceeds standard proportions, is located near a support, or excessively weakens the compression zone, providing reinforcement becomes unavoidable. The role of this steel reinforcement is to replace the missing material in order to transfer shear and resist local moments without excessive deformation.

  • Continuous horizontal flat bars welded above and below the opening, parallel to the flanges, to restore the moment of inertia of the tee chords.
  • Vertical stiffeners positioned at the ends of the cutout to prevent web buckling at stress concentration corners.
  • Complete frame formed of peripheral flat bars welded around the opening perimeter, an ideal solution for large rectangular ventilation ducts.
  • Tubular sleeves welded into the solid web for isolated circular pipe penetrations.

Executing weld runs on reinforcements requires strict thermal control to prevent restraint and geometric distortion of the beam. Longitudinal welds connecting reinforcement flats to the web must not stop abruptly at the end of the flat, but extend beyond the opening by a sufficient length to ensure load dispersion into the undamaged section.

  1. Transmission of opening drawingsThe site manager or the site foreman transmits the precise dimensions, shapes, and elevation coordinates of the technical duct to site management and the engineering office.
  2. Calculation note and approvalThe civil engineer responsible for the structure verifies the performance according to standard SIA 263, approves feasibility, and specifies the steel grade, geometry of flat bars, and weld throat thickness.
  3. Workshop fabricationThermal cutting, laser cutting, and welding of stiffeners are carried out in the workshop under certified factory production control, guaranteeing assembly quality.
  4. Restoration of corrosion protectionAfter cutting or welding, exposed surfaces are ground, degreased, and protected by a paint or metallisation system compatible with the structure's original coating.

On-site cutting procedures and cut geometry

Cutting an opening in an already installed steel beam requires a strict operating procedure to preserve the structural resistance of the element according to standard SIA 263. In-situ cutting must not be improvised with a blowtorch without preparation: the surface finish of the cut edges and corner profiling directly govern fatigue resistance and the risk of brittle fracture of the web.

  1. Marking out and pre-drillingPosition the opening centre lines using a marking gauge or centre punch according to the approved drawing. Carry out the four corner drillings with a hole saw or stepped drill bit to ensure the minimum transition radius without stray notches.
  2. Cutting straight segmentsCut out the web between pilot holes using a guided reciprocating saw or manual oxy-cutting/plasma cutting, leaving a machining allowance of 2 to 3 mm relative to the finished line.
  3. Finishing and grindingRework all cut edges with an angle grinder fitted with an abrasive disc to eliminate mill scale, burrs, and any notch initiations. The final surface must feel completely smooth to the touch.

In the case of workshop fabrication prior to lifting, mechanised oxy-cutting or automated thermal cutting directly ensures compliant geometry. On the construction site, manual cutting requires qualified erectors to prevent thermal grooving in the structural steel.

Installation of reinforcements, welding, and technical sign-off

When cutting weakens the beam's resistance to shear or web buckling beyond allowable tolerances, the civil engineer specifies localised reinforcement. The standard arrangement combines horizontal framing plates welded above and below the opening, or vertical stiffeners aligned with the vertical edges of the opening.

Typical configurations of web reinforcements according to applied load
Type of load effectSpecified reinforcement arrangementWelding detailVisual inspection / NDT
High shear force (near support)Double-sided full-height vertical stiffenersContinuous fillet welds on web and flangesMagnetic particle testing of weld ends
Predominant bending moment (mid-span)Continuous external longitudinal flat barsContinuous fillet weld, smooth 45° run-outDye penetrant inspection on weld ends
M-V interaction (intermediate zone)Complete steel frame surrounding the openingButt or fillet welds according to designDimensional check and full dye penetrant inspection

The installation of reinforcements complies with welding requirements for structural steels according to standard SIA 263. Surfaces must be cleaned by grinding down to bright metal over a minimum strip of 50 mm on either side of the joints to remove rust-inhibiting primer, rust, and grease before striking the arc.

The steel fabricator may only release the zone for MEP service installation after formal sign-off of the reinforcement. According to CO, the contractor shall report without delay any non-conformity regarding openings or unaccounted-for forces that would jeopardise the structure. The engineer records their approval in the site minutes, subsequently authorising the application of the corrosion protection system to the ground and heated zones.

Management of cutting non-conformities and remediation under engineering supervision

On a steel structure construction site, cutting an uncoordinated or out-of-tolerance opening in the web of a rolled section threatens overall stability through localised buckling or shear stress concentrations. When the MEP trade carries out unauthorised core drilling or when the cut deviates from approved workshop drawings, the first step is to immediately close off the affected bay. Prohibiting loading of the floor above and installing heavy propping directly beneath the defect prevents any irreversible plastic deformation.

The erection foreman logs the non-conformity through a precise dimensional survey: position relative to supports, diameter or dimensions of the cutout, transition radii, and edge condition. This technical dossier is sent to the civil engineer responsible for structural design according to standard SIA 263. According to CO, if any circumstance arises which compromises the proper or timely execution of the work, the contractor shall inform the client thereof. Any uncoordinated structural modification engages the liability of the parties involved: CP punishes anyone who intentionally or through negligence breaches the recognised rules of the trade while directing or executing construction work, thereby endangering the life or physical integrity of persons.

  1. Propping and load relief of the sectionInstall shoring towers under the beam to temporarily neutralise shear forces and bending moments prior to any remedial boilermaking work.
  2. Infilling or structural reinforcementIf the hole must be sealed, insert a bevelled web plug welded with inspected full-penetration welds. If the duct must pass through, weld longitudinal stiffening plates or a peripheral frame sized by the engineer.
  3. Non-destructive testing and corrosion treatmentVerify the absence of cracks by dye penetrant or magnetic particle inspection, grind flush weld crowns, then reinstate corrosion protection (zinc primer system and topcoat).

Frequently asked questions

Can the web of a steel beam be cut directly adjacent to a support?

No. The zone in the immediate vicinity of a column or base plate concentrates maximum shear force. Cutting an opening in this location weakens shear resistance and creates a high risk of web buckling according to standard SIA 263. Openings must be located within the central third of the span, or be fitted with heavy reinforcements that must be calculated and approved by the civil engineer prior to any cutting operation.

Why is it forbidden to execute sharp 90-degree corners on rectangular openings?

Sharp corners create extreme mechanical stress concentrations, promoting spontaneous cracking of the steel under dynamic or cyclical service loads. Standard SIA 263 imposes a minimum fillet radius, commonly executed by pre-drilling the four corners before cutting the opening. This smoothed geometry enables fluid redistribution of tensile and compressive lines of force within the remaining web material of the section.

What is the maximum allowable size for an unreinforced opening in a beam?

As a general rule, the diameter or clear height of the opening must not exceed one third of the clear web height of the rolled section. Furthermore, a minimum distance must be maintained from the flanges to preserve the compression or tension chord. Any exceedance of this geometric ratio reduces the section's inertia and requires the installation of stiffeners or longitudinal reinforcement plates validated by structural calculations.

What procedure must be followed when an MEP installer cuts a flange without authorisation?

Tampering with the flange of a section immediately compromises bending moment resistance and lateral-torsional buckling stability. The site foreman must close off access to the zone, install propping under the beam, and notify the damage to site management. The civil engineer must determine the feasibility of a welded or bolted fishplate reinforcement, or require the complete replacement of the steel span in accordance with the recognised rules of the trade.

Texts and standards cited

  • CO art. COMaterials and site conditions: the contractor is liable for the satisfactory quality of materials supplied by him; if the material supplied by the client or the building ground designated by him is found to be defective, or if any other circumstance arises which compromises the proper or timely execution of the work, he shall inform the client immediately, under penalty of bearing the consequences (para. 3).
  • CP art. CPBreach of the recognised rules of building: whoever intentionally breaches the recognised rules of the trade while directing or executing construction or demolition work, and thereby knowingly endangers the life or physical integrity of persons, shall be liable to a custodial sentence not exceeding five years or to a monetary penalty; in the case of negligence, to a custodial sentence not exceeding three years or to a monetary penalty.
  • norme SIA 263Steel structures: design principles, dimensioning and verification of steel structures.