Fitting to existing fabric: preliminary survey, deviations to absorb and adaptation components

Erecting a steel frame or load-bearing steel structure on an existing building requires anticipating geometric discrepancies in the structural work. This chapter details the methodology for dimensional surveys prior to fabrication, the design of baseplates with slotted holes, and the sizing of adjustment pieces planned directly in the workshop to ensure smooth assembly on the construction site.

Key takeaways

  • A systematic three-dimensional survey of the existing fabric validates actual dimensions before launching fabrication.
  • Execution tolerances in concrete and masonry require absorbing deviations of several centimetres.
  • Slotted holes and adjustable baseplates enable height and longitudinal adjustment during bolting.
  • Workshop-machined adaptation components prevent any improvised machining or unqualified welding on the construction site.

Carrying out the dimensional survey before fabrication to identify geometric discrepancies

In an older building or even on a recent reinforced concrete structure, actual dimensions systematically deviate from theoretical drawings. Wall positioning, out-of-plumb walls, slab deflections, and render thickness variations create massive geometric discrepancies for steel construction. The erection team cannot rectify components machined to the nearest millimetre on the construction site if the preliminary survey has not been carried out rigorously.

  1. Establishing the reference gridEstablish a general datum line (typically at +1.00 m from finished floor level) and reference axes marked with a chalk line or laser across the work area.
  2. Three-dimensional data captureSurvey embedment and bearing points using a 3D laser scanner or a total station. Measure squareness, actual bearing surface levels, and out-of-plumb values.
  3. Modelling and comparisonImport the point cloud into the steelwork BIM or CAD model to overlay the proposed structure and visually identify clashes and voids.

If the existing substrate presents major defects in flatness or strength that do not comply with the bearing requirements of the steel structure, the steel fabricator applies the provisions of the Code of Obligations (CO) regarding notification of defects in the ground or material provided by the client, in accordance with art. 365 CO.

Incorporating slotted-hole plates and adaptation pieces right from the workshop design stage

To absorb assembly tolerances without altering the mechanical strength of the connection, the design must incorporate multidirectional adjustment devices. The systematic use of slotted holes in connection plates makes it possible to compensate for the cumulative tolerances of the structural work and the steel.

Methods for absorbing erection deviations on existing structures
Connection deviceAdjustment directionAbsorption rangeSite implementation
Horizontal slotted holesLongitudinal / transverse axis± 15 mm to ± 30 mmThick structural washers and tightening to specified torque
Slotted shimsLevel / Bearing thickness2 mm to 20 mm (stacking)Slid under the baseplate before final tightening of the anchor
Welded adjustment piecesThree dimensions (3D)Discrepancies > 40 mmPre-machined angles or splice plates with trimming allowance

Slotted holes must always be used in conjunction with thick washers (minimum 8 to 10 mm) under the bolt head or nut to prevent any deformation of the plate during pre-tightening. In the event of significant shear forces, the residual gap in the slotted hole after final alignment is blocked with fitted shims or a washer-locking tack weld, in accordance with the timber-and-steel engineering firm's specifications.

Tolerance analysis and compensation strategy on existing structures

Comparing the workshop digital model with the reality of the existing building almost systematically reveals significant geometric discrepancies. Reinforced concrete frequently displays surface offsets, out-of-plumb deviations of several centimetres, and slab thickness variations, while historic masonry suffers from chronic out-of-squareness. For the steel erector, the challenge consists of neutralising these inaccuracies without disrupting the erection sequence, by applying the allowance principles established during setting out.

Comparison of construction tolerances and adjustment allowances
Supporting structureTypical observed deviationAbsorption methodAdjustment margin
As-cast reinforced concrete wall15 to 30 mm (plumb)Connection plate with slotted holes± 25 mm horizontal
As-built concrete slab10 to 25 mm (level)Machined steel packing shims5 to 40 mm vertical
Existing steel column or beam5 to 15 mm (alignment)Fixing bracket with oversized holes± 15 mm three-dimensional
Clay brick / stone masonry20 to 50 mm (flatness)Custom welded adaptation pieceUp to 60 mm

Execution tolerances for steel structures governed by SIA 263 require millimetre precision, which contrasts with the wider tolerances of the structural work governed by the Code of Obligations (CO) and customary building practice (pursuant to art. 365 CO, the contractor must report any defect in the substrate designated by the client). The steel fabricator must therefore create an interface zone capable of decoupling the rigid geometry of the steel from the imperfections of the mineral substrate.

Installation of adaptation components and final locking

Absorbing deviations on the construction site relies on three key elements integrated into the fabrication chain: slotted holes, stepped thick washers, and angle adjustment plates. Strategic use of slotted holes allows controlled sliding during temporary bolting, facilitating the overall plumbing of the structure using turnbuckles or hydraulic jacks.

  1. Positioning and pre-boltingOffer up the interface component against the existing structure. Insert anchor bolts or standard bolts into the slotted holes without final tightening, allowing travel.
  2. Height and plumb adjustmentAdjust the precise position of the component using a total station or laser level. Insert stainless steel or galvanised steel shims beneath the baseplate to achieve design level.
  3. Safety tightening and washer weldingAfter full geometric verification of the bay, tighten bolts to the specified torque. To prevent any subsequent slip in the slotted hole under dynamic load, thick square washers are welded to the baseplate.
  4. Installation of custom-made closing piecesMeasure residual dimensions at critical points to fit flashing, edge trims, or packing strips intended for the finishing work.
  • Always use steel shims of descending thickness (10, 5, 2, 1 mm) to adjust the level without residual play.
  • Check galvanic compatibility between adaptation components and existing members to prevent electrolytic corrosion.
  • Ensure immediate corrosion protection on adjustment areas reworked by site welding using a zinc-rich paint.
  • Record all absorbed deviations on the 'as-built' drawing for subsequent facade and finishing work.

Management of out-of-tolerance deviations and erection blockages on existing structures

When lifting on site reveals a geometric discrepancy exceeding the planned absorption capacity (slotted holes bottomed out, shims of insufficient thickness, or major masonry axis offset), basic safety principles strictly prohibit forcing with drift pins or improvised cutting on the construction site. Forcing steel components into place generates uncalculated parasitic stresses that compromise the overall stability of the structure as well as the capacity of preloaded bolting.

  1. 1. Halt erection and carry out additional surveyAs soon as a deviation exceeds the adjustment range of the plates (generally ±20 mm to ±30 mm), the erection team secures the suspended element or supports it on temporary propping. A precise total station survey is immediately carried out to measure the actual position of the existing support relative to the theoretical gridlines.
  2. 2. Notification to the site management and engineerIn accordance with works contract rules governed by the Code of Obligations (CO), the contractor reports the defect in the existing support without delay. The deviation report, accompanied by point clouds or axis measurements, is submitted to the timber or steel engineer for approval of the remedial solution.
  3. 3. Fabrication of bespoke adjustment piecesRemediation is carried out by fabricating welded backing plates, tapered shims, or workshop-machined adaptation plates according to revised drawings. No modification by torch or gouging is permitted on load-bearing structural members without written approval from the engineering department.

Once the adaptation piece is in place and alignment has been verified by laser, final locking is carried out to the specified tightening torque. Corrosion protection touch-ups using zinc-rich primer and finish paint are immediately applied to any damaged friction or shimming areas.

Frequently asked questions

How do you size the adjustment allowance on a steel structure anchored into historic masonry?

On historic masonry, structural work tolerances are very wide. Slotted holes should be provided both perpendicular and parallel to the facade (up to 3 times the bolt diameter), combined with machined thick washers and certified steel stacking shims 2 to 10 mm thick.

Can an adaptation piece be welded directly onto a wrought iron or early steel beam?

The weldability of historic steels (produced before 1950) is highly questionable due to their high carbon, sulphur, and phosphorus content. Any connection to an existing profile requires sampling for metallurgical analysis or should preferably be designed using through-bolts or mechanical clamping.

Who covers the machining cost of an adaptation component not included in the original quote?

If the preliminary survey could not detect a concealed defect and the substrate provided by the client deviates beyond the tolerances of SIA 414, the adaptation piece constitutes extra work to be approved via a daywork sheet or a contractual addendum prior to fabrication.

What protection should be applied to adaptation shims inserted between two galvanised plates?

Steel shims must provide the same level of galvanic protection as the main connection (hot-dip galvanising to SIA standards). If adjustments are made on site with cut raw plate, the shims must be descaled, degreased, and coated with a high-build single-component zinc primer prior to tightening.

Texts and standards cited

  • SIA 414Tolerances in building construction
  • SIA 263Steel structures
  • CO art. 365Immediate notice by the contractor in the event of defects in the support provided by the client