Erection and lifting of a steel structure: execution standard
Intended for steelwork team leaders, site foremen and site managers (CFC 215), this section details the erection on the construction site of steel structures in accordance with standard SIA 263. From the lifting plan to final tightening, it delivers practical methods to ensure the temporary stability of the load-bearing framework, secure erectors working at height and achieve millimetre-accurate adjustment of connections prior to final grouting.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
2 bolts
Minimum required per connection before unhooking the lifting sling
2 m
Fall height triggering mandatory collective protection
50 cm
Minimum clear distance to the edge of a supported trench for machinery
100 cm
Minimum height of the top rail of a temporary guardrail
Scope of work: from anchoring to final bolting
Erecting a steel frame cannot be improvised at the crane base. It forms the physical meeting point between workshop fabrication and the raw environment of the construction site. For the steel fabricator under CFC 215, this stage engages the overall structural liability for the building right from the first lift. The golden rule consists in mastering each intermediate phase: a steel structure achieves its design stiffness only once fully braced, assembled and anchored onto its foundations.
Every crane manoeuvre requires rigorous coordination between the crane operator, the slingers on the ground and the erectors receiving the sections aloft. Operations require strict enforcement of occupational health and safety rules. In accordance with LAA, the employer takes all necessary measures shown by experience and permitted by technology, in particular by providing suitable protective equipment and enforcing safe lifting procedures.
- Guaranteed autonomous stability at every stage through the priority creation of a rigid braced bay.
- Safety of erectors ensured from ground level by pre-installing lifelines and temporary access ladders.
- Millimetre precision in levelling and plumbing before any mechanical locking or injection of non-shrink mortar.
- Systematic verification of bolt connection tightening according to the property classes specified by civil engineers.
Method and reading pathway: securing the erection sequence
Successful steel erection relies on a millimetre-accurate chronology. An inverted installation sequence or premature release of the crane hook can lead to local failure or the overall collapse of the framework. Site organisation must therefore follow a logical sequence ranging from logistical planning through to the formal handover of the steel frame.
- Stage 1: Preparation, setting out and shimmingSetting out begins with checking the baseplates and anchor studs left by the structural work. Chapters [C3-01] and [C3-02] detail the erection sequence for the first non-deformable bay, the precise shimming under baseplates using wedge shims and the preparation of the grouting gap.
- Stage 2: Lifting, handling and accessSetting up the mobile crane on outrigger pads ([C3-07]) precedes any lifting. Chapters [C3-03] and [C3-08] cover slinging techniques adapted to heavy sections and the trade-offs between pre-assembly on the ground and piece-by-piece handling.
- Stage 3: Assembly aloft and personnel safetyChapters [C3-04] and [C3-05] govern work at height: minimum number of bolts before releasing the crane hook and continuous use of temporary lifelines. Moreover, OTConst imposes strict measures at workstations against the collapse of components and the fall of materials.
- Stage 4: Adaptation, inspection and finishesChapters [C3-06], [C3-09] and [C3-10] complete the process: managing tolerances when connecting to existing buildings, drawing up joint geometric inspection records and applying anti-corrosion touch-ups to damaged or site-welded areas.
📘 Chapters in this section 10
Erection sequence: the order that keeps the frame stable at every stage
Erect the initial braced bay to secure the framework against wind from day one.
Erection and lifting of a steel structureAdjusting the frame: baseplate shimming, levelling, and final grouting
Adjust the elevation under baseplates with wedge shims before injecting the non-shrink mortar.
Erection and lifting of a steel structureSlinging a section: lifting points, balancing and certified tackle
Select certified textile slings or chains to lift sections without slippage or deformation.
Erection and lifting of a steel structureTemporary then final bolting: how many bolts before unhooking the crane
Tighten the essential temporary connections before authorising safe unhooking of the crane hook.
Erection and lifting of a steel structureSteel erector: ground-installed lifeline and beam traversal
Attach lifelines on the ground to ensure continuous safety for the erector at height.
Erection and lifting of a steel structureFitting to existing fabric: preliminary survey, deviations to absorb and adaptation components
Record the tolerances of the existing structural work to design bespoke pack plates.
Erection and lifting of a steel structureMobile crane: ground bearing capacity, outrigger pad spreading and excavation proximity
Check ground bearing capacity and crane outrigger shimming at the edge of excavations.
Erection and lifting of a steel structurePre-assembling on the ground: gaining safety, losing lifting flexibility
Bolt trusses together on the ground to reduce MEWP hours and make the construction site safer.
Erection and lifting of a steel structureChecking geometry after erection: plumb, level, diagonals, and handover record
Measure plumb and diagonals with a total station to approve the geometric handover record.
Erection and lifting of a steel structurePost-erection touch-ups: welded zones, lifting damage and system continuity
Touch up handling damage and site welds in accordance with the original paint system.