Defect discovered after façade installation: opening, recording, and who bears the remediation

Discovering an out-of-plumb condition or slab misalignment once the metal façade framework has been installed creates a major technical and financial crisis. This chapter guides you to freeze the situation without worsening the damage, conduct an irrefutable joint inspection record, mandate an impartial technical expert appraisal and allocate remediation costs according to Swiss recognised rules of the trade.

Key takeaways

  • Immediately halt final fixings as soon as a geometric drift outside tolerances appears.
  • Establish a three-dimensional joint inspection survey with site management and the bricklayer.
  • Distinguish the initial substrate defect from the metal contractor's own compensation tolerance.
  • Refer the financial assessment of dismantling or adaptation variants back to the tender bills of quantities.

Open up, measure and record the disorder via a joint inspection record

Discovering an out-of-plumb deviation, an out-of-level slab edge or an axis offset when façade mullions or frames are already craned into place and bolted constitutes the worst construction site scenario. The reflex of forcing shims, slotting clearance holes with a blowtorch or hoping to hide the offset beneath sheet-metal flashings inevitably leads to mechanical binding, water ingress or glazing breakage under the effect of thermal expansion.

As soon as permissible installation tolerances are exceeded, the golden rule requires suspending installation progress on the bay concerned. The metal contractor must record the facts without delay in the site journal and issue a formal notification to site management. For details relating to the contractor's duty to notify when detecting a non-compliant substrate before or during the intervention, the complete contractual process is addressed in the silo dedicated to CFC 201.

  1. Technical shutdown and securingHalt the final tightening of fixings on drifting areas. Leave elements suspended or temporarily propped to avoid inducing parasitic stresses into the steel load-bearing structure.
  2. Convening on siteOrganise a site visit within 24 to 48 hours bringing together the installation manager for the metal package, the structural work site manager (CFC 211.1) and site management.
  3. Targeted destructive probingLocally remove claddings, insulation or plates as necessary to clear the view of the concrete substrate and anchor channels without weakening the mechanical stability of the assembly.
  4. Three-dimensional joint surveyPerform cross-measurements using a laser total station relative to the building's main gridlines, in the presence of the parties. Record actual deviations observed relative to the approved execution drawings.

The minutes drawn up following this visit form the central piece of the file. They must be signed on the spot by all representatives. This document freezes the raw geometry of the concrete, the exact progress state of the façade framework, the absence or presence of abnormal shimming and induced defects (such as pinched glazing or joints compressed beyond acceptable limits).

Mandating technical expert appraisal and arbitrating financial allocation

When the extent of geometric drift exceeds the adjustment range provided on fixing brackets or requires modifying the framework, disagreement over the cause of the damage frequently arises. The bricklayer blames thermal deformation or an assembly defect in the steel structure, while the façade contractor blames excessive deflection or a bulged formwork. Resorting to a neutral technical expert appraisal then becomes essential to determine root causes.

After delivery, the employer inspects the state of the work as soon as feasible and notifies defects to the contractor; for an immovable work, he has 60 days to report them and a shorter contractual period is void; each party may request an examination by experts.

art. 367 CO

The mandated expert, often from an engineering consultancy specialising in building envelopes and structures, analyses the complete tolerance chain. They compare permissible tolerances of reinforced concrete structural work according to current construction standards with the residual adjustment range offered by metal brackets. If the concrete deviation remained within permissible structural work margins but the façade fixing system did not include sufficient compensation range, the metal contractor bears the remediation. Conversely, if the concrete wall exceeds contractual tolerances and the metal package was formally ordered to proceed despite reservations, liability shifts to the structural work.

Liability allocation matrix for an interface geometric defect
Established technical findingPrimary originDefault allocationRequired corrective action
Slab edge outside raw tolerance (> 20 mm)Defective concrete setting-out or pouringStructural work contractor (CFC 211.1)Concrete planing or supply of bespoke plates
Slotted holes at maximum travel (< 5 mm play)Design defect of fixing bracketsMetal contractor (CFC 215)Replacement of brackets and framework realignment
Slab sagged after installation under self-weightStructural design error or premature striking of formworkCivil engineer / BricklayingJacking, steel reinforcements and recalculation of supports
Forced installation without prior reservation noticeNegligent inspection when taking over the substrateShared (loss of the façade contractor's right of notification)Partial dismantling at costs shared between both packages

Determining liabilities leads directly to negotiating remediation costs: extra crane time, careful removal of modules, machining of tapered shims, or even remanufacturing deformed elements. These unforeseen works must never be improvised under uncontrolled daywork. To establish detailed quantity surveys, value dismantling operations and price addenda based on the schedules of unit prices agreed in the contract, project managers will refer directly to the pricing methods presented under /soumissions/.

Traceability of liabilities and qualification of cross interfaces

Discovering an out-of-plumb or alignment deviation after complete installation of the façade load-bearing structure immediately places interface boundaries under strain. When structural glazing, steel hollow sections and cladding sheets are fixed, determining the exact origin of the defect requires separating concrete structural work tolerances from metal framework installation tolerances.

The metal contractor faces a cascade of contractual interfaces. If the geometric deviation stems from an out-of-tolerance slab edge or a twisted concrete wall, but the façade framework was fixed without prior written reservation, site management systematically attempts to allocate full damages to the metal package installer. As a reminder, the formal procedures and notification deadlines relating to the contractor's duty to notify regarding a non-compliant substrate are detailed in the CFC 201 trade guide.

Distribution of checks and liabilities for a deviation discovered beneath a finished façade
Element concernedFrequent technical originInitially responsible trade packageDirect impact on the metal framework
Concrete slab edgeDifferential deflection or plastic shrinkageBricklaying / Reinforced concrete (CFC 211.1)Fixing toe out of travel, increased shear stresses
Cast-in anchor channelsInstallation drift or tilting during pouringBricklaying / Reinforced concrete (CFC 211.1)Eccentricity of T-head bolts, loss of effective bearing
Steel brackets and mullionsOut-of-square defect or asymmetric tighteningMetal construction (CFC 215)Battering at edge, distortion of glazing gridlines
Primary load-bearing structureInsufficient precamber under loadCivil engineer / Structural frameCrushing of vertical expansion joints

The contractor applies the rules of the trade and checks data as well as preparatory work carried out by third parties before undertaking his own works.

Norme SIA 118

Remediation protocol, pricing and claims management

Once the joint inspection record and the technical expert report have identified the source of the defect, intervening on the installed façade requires a rigorous methodology. Local opening of the weatherproofing and thermal envelope must preserve the overall mechanical performance of load-bearing mullions while releasing access to the implicated anchor connections.

  1. Selective removal and securingRemove adjacent glazing or metal cassettes using a vacuum lifting beam. Temporarily prop vertical load-bearing profiles if the connection to slab brackets must be disconnected.
  2. Three-dimensional survey after unloadingMeasure the actual state of the relieved framework using a laser total station to quantify the elastic deformation portion and the residual concrete geometry portion.
  3. Modification of fixings and shimmingMachine metal brackets by milling compliant slotted holes or install machined steel tapered shims to restore strict verticality of the edge line.
  4. Reinstatement of weatherproofing barriersReinstate air- and water-tightness membranes, then reposition glazing, checking gap tolerances prior to torque tightening to specification.

Under art. 367 CO, after delivery, the employer inspects the state of the work as soon as feasible and notifies defects to the contractor, having a period of 60 days to report them when an immovable work is concerned. This framework governs exchanges between the end client and the contractors involved. When remediation requires joint intervention by the bricklayer and the metal contractor, disputes over additional costs must never jeopardise façade front safety.

The overall cost of the operation includes cherry picker time, protective measures, verification engineering and replacement steel parts. For a geometric remediation intervention on a completed composite façade, sums incurred frequently range from 15,000 to 45,000 CHF depending on external accessibility and the complexity of the glazing to be handled. Detailed analysis of dismantling, machining and weatherproofing reinstatement items is covered in a specific bill of quantities detailed under /soumissions/ for pricing.

Interface dispute management and remedies after dismantling

Discovering a major dimensional deviation on the metal framework or slab edges after complete curtain wall installation places the metal contractor in a critical situation. When assembly tolerances are exceeded and prevent the alignment of façade elements, on-site discussions sour rapidly. If site management refuses to issue a change order or if the bricklayer disputes the origin of the misalignment, the intervention approach must be formalised without severing contractual relations.

  1. Formal notification and reservationsImmediately notify the suspension of works on the disputed area via formal notice to site management. Reiterate the provisions of standard SIA 118 concerning the recording of facts and the joint inspection of the work prior to any modification of the premises.
  2. Instrumented joint inspection recordConvene the civil engineer, façade contractor and site management on site for a joint total station survey. Record in signed minutes the actual coordinates of anchor points, framework deflections and axis offsets relative to approved execution drawings.
  3. Independent technical expert appraisalIf disagreement on the origin of the defect persists, request a neutral technical expert jointly or via legal proceedings. In accordance with art. 367 CO, each party may request an examination by experts to analyse the origin of defects.
  4. Remediation agreement under reservationIf the schedule dictates intervening without awaiting final arbitration, establish a technical remediation protocol "without prejudice to rights and financial allocation", approved in writing by the client before opening up structures.

For detailed pricing of removal operations, on-site machining, fabricated adaptation pieces and reinstallation, refer to the /soumissions/ section. The financial evaluation must incorporate specialised lifting equipment, cherry pickers, as well as idle time for installation crews.

Frequently asked questions

Who pays for the cherry picker or crane required to open up the façade and inspect the deviation?

Access equipment required for inspection remains initially ordered by the contractor carrying out the check or by site management, according to site agreements. If the joint inspection record proves that the defect stems from a non-conformity in structural work or coordination drawings, plant hire and opening-up costs are back-charged to the party responsible for the defect in the final claim account.

Can one refuse to dismantle the façade until financial allocation is signed?

A total shutdown exposes the contractor to the consequences of site delay under the Code of Obligations (CO). Swiss practice involves formally recording one's disagreement in writing, then agreeing to execute remediation work subject to subsequent cost allocation. Site management agreement on the principle of the intervention guarantees financial settlement without paralysing the general schedule.

What must imperatively be recorded in the minutes upon discovering the defect?

The minutes must state the date, persons present, weather conditions and measuring instruments used. They describe the observed deviation relative to workshop drawings, precise setting-out dimensions of brackets, condition of existing fixings and any deflections. Joint signing by the metal contractor, site management and the structural work package representative secures the evidential value of the document.

How should one react if site management demands direct grinding of fixing plates?

The metal contractor must never alter a structural element without written approval from the civil engineer responsible for the structure. Grinding a plate or slotting a hole reduces its mechanical strength and alters corrosion protection. A justifying structural calculation note or an adaptation detail approved by the engineering office must be issued prior to any physical modification of steel assemblies.

Texts and standards cited

  • norme SIA 118General conditions for construction work
  • CO art. 367Inspection of the work and notice of defects; examination by experts