Key takeaways
- The technical coordination meeting freezes suspended loads and blockouts prior to fabrication.
- The permitted fixings drawing strictly delimits drillable zones and prohibited zones.
- Channel rails integrated in the workshop eliminate the need to drill on the construction site.
- Any drilling not approved by the engineer immediately releases the steel fabricator from liability.
Locking down interfaces during coordination meetings and via the fixings drawing
On a building construction site, the steel frame represents the ideal support for all technical installations and interior finishes: electricians' cable trays, ventilation ducts, heating pipes, drywall studs or suspended ceilings. Without rigorous arbitration prior to fabrication, the finishing work trades arrive on the construction site equipped with self-drilling screws or masonry drill bits, piercing flanges and beam webs in defiance of structural analysis calculations and the durability of the corrosion protection. Interface control rests on a clear principle: structural steel is not a universal support left at the free disposal of the secondary trades.
The process begins during technical coordination meetings held under the auspices of the site management. The steel fabricator requires comprehensive disclosure of the schedule of suspended loads, their points of application and the clearance envelopes required by the building services engineers (heating, ventilation, electrical, plumbing). These requirements are synthesised in a contractual document: the permitted fixings drawing. This drawing, approved by the civil engineer responsible for the overall structural design of the work, distinguishes the zones where secondary loads are tolerated from those where any load application or material reduction is strictly prohibited.
| Section zone | Intervention status | Provisions and technical constraints | Authorised fixing methods |
|---|---|---|---|
| Tension flange (mid-span zone) | Red zone: total prohibition | Risk of crack initiation due to stress concentrations; no holes or welding. | No direct contact; removable non-drilling clamping collars subject to load checks. |
| Compression flange (top chord) | Yellow zone: subject to approval | Verification of lateral-torsional buckling and combined stresses; reserved for fixings planned during design. | Shop-welded studs or certified flange clamps on the flange tip. |
| Section web (neutral axis) | Green zone: tolerated subject to agreement | Drilling possible only within the middle third of the depth, outside maximum shear zones. | Calibrated bolting drilled in the workshop or specific beam clamps for light loads. |
| Frame nodes and splices | Red zone: total prohibition | Areas subjected to high bending moments; critical structural integrity. | No secondary fixings permitted on end plates, gussets or bolted connections. |
Anticipating hangers using channel rails and banning uncontrolled drilling
To reconcile finishing work requirements with the preservation of the structure, the best technical solution consists of integrating steel anchor channels during workshop fabrication. These cold-formed or hot-rolled channels, fitted with anchor lugs or welded directly onto the frame before hot-dip galvanising or the application of intumescent paint, create adjustable fixing lines. Installers attach their brackets and threaded rods to them using dedicated hammer-head bolts, generating no sparks, without damaging the surface protection and without exerting unintended stresses on the steel.
- Installation of continuous anchor channels on the underside of main beams for HVAC service runs.
- Installation of threaded inserts welded in the workshop to support heavy equipment identified on the drawings.
- Exclusive use of ductile iron flange clamps for gripping beam flanges.
- Use of hangers for composite steel decking to transfer light loads to the sheet rather than to the primary frames.
In the event of a violation of instructions and drilling discovered on site, the intervention is governed by the strict application of the codes of practice. According to art. 229 CP, anyone who, intentionally or through negligence, breaches the recognised rules of the building trade when directing or carrying out a construction project, and thereby endangers the life or physical integrity of persons, is liable to criminal penalties. Consequently, the steelwork foreman or site supervisor must immediately halt the load on the damaged component, have a joint inspection record drawn up and enforce the installation of a reinforcement splice or bolted stiffener under the supervision of the structural engineer.
Installation protocols and freezing of blockouts for building services trades
As soon as the load-bearing structure is completed, the technical finishing work contractors (heating, ventilation, sanitary and electrical) intervene en masse beneath the steel structures. To prevent uncontrolled drilling of members, the site management must arbitrate service layouts solely based on the structural concept approved by the civil engineering firm. The steel structure is under no circumstances an unprocessed substrate open to indiscriminate dowelling.
To suspend cable trays, ventilation ducts or substations without affecting the load-bearing steel, interfaces must favour mechanical clamping connections or the use of profiled service channels. Integrating standardised mounting rails from the fabrication stage allows vertical load paths to be shared and provides installers with a millimetre-precise adjustment range.
| Structural element | Authorised fixing device | Installation constraint | Strict prohibition |
|---|---|---|---|
| Bottom flange of welded plate girder | Beam clamps or certified girder clamps | Tightening torque verified with a torque wrench | Direct drilling, tapping or welding on the construction site |
| Web of hot-rolled section (IPE, HEB) | Reinforced duct penetrations provided in the workshop | Minimum centre-to-centre spacing according to the engineer's calculation report | Cutting with an oxy-fuel torch or angle grinder |
| Cold-formed roof purlins | Suspension brackets matched to Z or C section | Point load limited to manufacturer's specifications | Self-tapping screws outside factory pre-drilled holes |
| Soffit of composite slab decking | Cast-in anchor channel rails or trapezoidal fixings | Insertion before pouring or onto dedicated rib | Shot firing without structural approval |
During the execution of works, compliance of the structure is assessed against the codes of practice and strict adherence to contractual tolerances. The provisions of standard SIA 118 govern the respective duties of contractors when geometric clashes or interferences between trades arise, particularly regarding the reporting of situations that jeopardise the progress of the construction site.
Management of unauthorised drilling, inspections and remediation
When a finishing work operative drills a structural member without an approved drawing, the mechanical integrity and corrosion protection of the frame are immediately compromised. The steelwork erection foreman logs the damage in the site logbook and submits a joint inspection record to the site management.
Article 367 CO specifies the procedures for inspecting the work and reporting defects by the client. As soon as damage to the steel frame is detected, the steel fabricator must have the defect formally notified to discharge its liability regarding the structural performance and durability of the protective coating.
- Immediate halt to the offending activityImmediate notification to the foreman of the responsible trade and to the site management to stop all drilling in the affected area.
- Dimensional survey and photographic reportAccurate measurement of the diameter, location on the section (edge distances, tension or compression zone) and identification of the damaged steel grade.
- Structural assessment by the engineering firmCalculation of the member's residual section and determination of required remedial measures (filling by qualified welding, splicing or fish-plating).
- Remediation and reinstatement of the paint systemExecution of mechanical repairs by certified welders, followed by grinding, degreasing and reapplication of the corrosion protection or intumescent paint in accordance with manufacturer specifications.
The engineering cost for recalculating the member, mobilising qualified welders on the construction site and repairing the surface protection must be paid entirely by the offending company. A systematic clarification of these consequences during initial technical meetings helps prevent damage to the completed frame.
Management of interface disputes and frame remediation
On construction sites in French-speaking Switzerland, the temptation for building services trades to drill beam flanges or weld makeshift brackets without the approval of the steel fabricator remains a frequent source of defects. As soon as uncontrolled drilling or a fixing not listed on the permitted fixings drawing is identified, the site management must immediately record the joint inspection record in the site minutes, complete with photographs and precise location markings on the layout drawings.
The offending contractor cannot unilaterally carry out weld-filling. Under the Code of Obligations (CO), the client or its representative demands the remediation of defects caused by execution contrary to technical standards. The procedure mandates systematic consultation with the structural engineer: either the calculations approve the hole after the fact subject to a derating of the allowable load, or they mandate reinforcement by a bolted splice or certified welded plate. Engineering costs, workshop expenses and the reapplication of corrosion protection (liquid paint or cold galvanising) are backcharged in full to the party responsible for the drilling.
- Halting the fixing work and formal recordImmediate notice to the site management and cessation of installation for the offending building services package.
- Structural assessment by the engineerVerification of residual stresses in the steel section and formal sign-off of the reinforcement scheme.
- Qualified repair and surface restorationExecution of the repair by the steel fabricator's erectors and reinstatement of the certified protective coating.
Frequently asked questions
Can a plumbing installer drill a hole in the web of a steel beam to pass a pipe through?
No. Any drilling of a web or flange strictly requires prior approval from the civil engineer and the steel fabricator. Even outside the maximum tension zone, the opening alters shear forces and web buckling behaviour. Without a blockout shown on the permitted fixings drawing, drilling is strictly prohibited. The offending contractor must bear the costs of the structural check calculations and the potential installation of a welded stiffener frame.
How can cable trays be fixed without drilling through painted steelwork?
The standard solution is to use malleable cast iron beam clamps or girder clips tailored to the flanges of the steel sections. These mechanical fasteners grip the steel without altering the load-bearing cross-section or damaging the intumescent paint system. Suspended loads must strictly comply with the limits defined during the technical coordination meeting with the site management.
At what stage should cast-in channels for secondary trades be integrated?
Anchor channels must be integrated as early as the workshop and erection drawing phase of the steel package. During the coordination meeting, each trade (HVAC, electrical, suspended ceilings) communicates its requirements in terms of loads and locations. The profile channels are then welded in the workshop before the application of corrosion protection, thereby preventing any subsequent abrasive interventions or hot work on the construction site.
Who is financially responsible for the repair of a steel section damaged without authorisation?
The contractor responsible for the unapproved drilling bears all incurred costs. This covers the civil engineer's recalculation fees, the supply and installation of reinforcement splices or plates by the steel fabricator, and the reinstatement of the corrosion or fire protection in accordance with the original specification. The amount is directly deducted from the offending trade's payment applications.
Texts and standards cited
- norme SIA 118General conditions for construction work
