Key takeaways
- Steel shims guarantee temporary levelling and load transmission beneath the baseplate.
- Checking with a laser level validates plumb and height tolerances according to SIA 414.
- Non-shrink grouting mortar eliminates all voids under the structure's baseplate.
- Temporary stability is ensured by bolting prior to pouring any grouting mortar.
Preparation of beddings and installation of shims under column baseplates
Height adjustment and levelling of the steel frame rely on meticulous preparation of the foundation heads or reinforced concrete walls. Before bringing columns into position, the site foreman checks the condition of the concrete substrate and the setting out of anchor bolts. Pocket formers or threads must be clean and free of all concrete debris. Level variations in the structural concrete are compensated for using steel bedding shims placed on either side of the anchor bolts to ensure stable, flat bearing beneath the baseplate.
- Use flat steel shims of a grade equivalent to the frame, free from burrs or flaky rust.
- Place shim packs as close as possible to the anchor bolts to avoid bending the baseplate under dead weight.
- Ensure a continuous contact surface under the baseplate to correctly transfer temporary vertical loads.
- Fit adjusting nuts and locknuts without fully locking the assembly before taking laser sightings.
- Levelling shim
- Steel plate of calibrated thickness positioned between the foundation concrete and the steel baseplate to adjust the column height and horizontal level prior to grouting.
Adjustment using a laser level and pouring non-shrink grouting mortar
Once the steel members are assembled and held by their temporary bolting, the team carries out fine adjustment of the overall geometry. Checking with a rotating laser level enables verification of column head levels, transom levels, and the general grid line of the building. Observed deviations are corrected by adjusting the thickness of the shim pack under each baseplate or by turning the levelling nuts beneath the baseplate. Column verticality is verified simultaneously along two orthogonal axes using a laser plumb or theodolite.
- Height check using a laserRecord level readings on each baseplate using the laser receiver and compare values against the construction site setting-out datum (-0.00).
- Shim adjustment and lockingAdd or remove thickness shims beneath the baseplate until the specified level is achieved, then moderately tighten the anchor nuts.
- Formwork and substrate wettingInstall watertight formwork around the baseplate and pre-soak the supporting concrete to refusal to prevent absorption of the mixing water.
- Pouring non-shrink mortarMix and pour a high-strength, non-shrink fluid grouting mortar continuously from one side only to expel trapped air from beneath the steel baseplate.
At workstations and passageways, measures must be taken so that workers are not endangered by falling or collapsing construction elements.
art. 17 OTConst
Height checks and alignment tolerances according to standard SIA 414
Geometric adjustment of a steel frame must imperatively take place before pouring the bedding mortar. As soon as the first columns are placed on their anchor bolts, the erector must stabilise the members using chain hoists, props, or temporary guys. The overall geometry of the steel skeleton depends on strict compliance with the grid axes and reference levels provided by the surveyor. Application of the rules in standard SIA 414 defines allowable tolerances regarding verticality deviations, column centres, and column head flatness.
Height checks are carried out using a professional rotating laser level with a sensor or an optical level set to the structural work level datum (+1.00 m relative to the finished floor level). The site foreman checks each baseplate by measuring the distance between the reference line and the underside of the baseplate. Perfect column plumb is checked along two orthogonal axes using a plumb line or total station. Any deviation from the tolerances of standard SIA 414 requires immediate correction using the adjustment devices prior to final tightening of the connections.
Levelling shims, anchor tightening, and injection of non-shrink mortar
To adjust the height of the column baseplate before pouring the grouting mortar, two professional techniques are mainly used on Swiss construction sites: using packs of steel shims or using a system of levelling nuts and locknuts beneath the baseplate. Steel levelling shims, calibrated in various thicknesses (from 1 mm to 10 mm), are arranged on either side of the anchor bolts to ensure stable, flat bearing. They must be distributed to prevent any tipping or distortion of the baseplate under the dead weight of the frame and construction loads.
| Technique | Equipment used | Field of application | Advantages / Points to watch |
|---|---|---|---|
| Calibrated steel shims | Flat steel shims of 1, 2, 5, and 10 mm | Heavy baseplates, high vertical loads | Excellent point stability; requires a clean stack free from burrs. |
| Levelling nuts beneath baseplate | Nuts and large washers on threaded rods | Light to medium columns, secondary frameworks | Highly accurate millimetre-level height adjustment; beware of risk of bolt bending if the gap under the baseplate is too large. |
| High-density synthetic shims | Rigid plastic stepped shims | Lightweight structures, rapid pre-levelling | Non-corrosive; must be verified against allowable compressive loads. |
Once the frame is fully aligned, plumbed, and braced, the site foreman approves the temporary tightening of the top anchor nuts. The void beneath the baseplate (typically between 30 mm and 50 mm) must then be filled with high-performance non-shrink grouting mortar. This fluid cementitious mortar, formulated specifically to compensate for hydraulic shrinkage, guarantees complete transfer of compressive forces from the steel structure to the concrete foundation.
- Substrate preparation and watertight formworkCarefully remove dust from the concrete surface using compressed air and saturate the substrate with water without leaving standing water. Install watertight timber or metal formwork on all four sides of the baseplate, providing a 50 mm overhang on each side and a pouring hopper on one side.
- Mixing and pouring chuteMix the non-shrink grouting mortar using a low-speed mechanical mixer, strictly respecting the water ratio recommended by the manufacturer. Pour the mortar continuously from one side only to displace air trapped under the steel plate.
- Filling inspection and curingEnsure that the mortar rises on the opposite side of the formwork until it rises above the underside of the baseplate. Protect the product from premature drying out for at least 48 hours using a curing agent or damp hessian.
- Final torque tighteningAfter full hardening of the grouting mortar (minimum required strength achieved according to manufacturer data), apply final torque tightening to the anchor bolts using a torque wrench in accordance with specifications.
If the materials supplied by the client or the site designated by them are found to be defective, or if any other circumstance jeopardises the correct or punctual execution of the work, the contractor shall immediately inform the client, failing which they shall bear the consequences.
CO
Managing tolerance deviations and corrective measures on the construction site
During erection of the steel structure, the discovery of geometric discrepancies exceeding the requirements of standard SIA 414 dictates an immediate halt to final fixing stages. If the setting out of anchors or the level of the concrete foundation does not permit standard shimming of the column baseplate, the steelwork contractor must exercise the duty to notify the client before any non-shrink grouting mortar is poured. Temporary shimming using steel levelling shims must maintain absolute stability under temporary alignment and bracing loads.
- Joint level surveyCheck the position of all baseplates with the site laser level prior to final tightening of the anchor bolts. Record X, Y, and Z deviations in the setting-out report.
- Shimming adaptation and bracingAdjust the thickness of the steel levelling shim pack under the baseplates. Ensure accurate column levelling while maintaining the minimum gap required under the baseplate for fluid penetration of the non-shrink mortar.
- Pouring and final lockingInstall watertight formwork around the baseplate and pour the non-shrink grouting mortar by gravity from one side only to displace air bubbles. Allow the mortar to cure sufficiently before applying final torque to anchor bolts and releasing lifting hoists.
Frequently asked questions
What is the ideal thickness for grouting mortar under an anchor baseplate?
The standard clearance reserved under the baseplate is between 30 mm and 50 mm. This gap allows easy positioning of steel levelling shims while ensuring optimum cover and fluid gravity filling of the non-shrink grouting mortar. Below 20 mm, pouring becomes very difficult and risks creating voids under the baseplate.
Can levelling shims be left under the baseplate after pouring the mortar?
Yes, provided the levelling shims are made of structural steel resistant to compression and positioned so as not to impede the flow of the non-shrink mortar. They contribute to immediate level retention. Conversely, the use of deformable synthetic plastic shims is prohibited under main column baseplates to prevent any settlement under dead load.
How is the plumb of tall steel columns checked?
Checks are carried out using an automatic-levelling laser level or theodolite from two orthogonal axes at the base of the building. Baseplate alignment and column head verticality are verified simultaneously. Measurements must comply with tolerances stipulated by standard SIA 414 before proceeding with final tightening of anchor bolts and grouting.
What should be done if an anchor bolt cast into reinforced concrete is misaligned?
If the misalignment exceeds the baseplate bolt clearance holes, the non-conformance sheet must be submitted to the structural engineer. Approved solutions consist either of neatly slotting the hole and welding a thick load-distributing washer, or installing a new chemical anchor after core drilling the reinforced concrete, in compliance with project anchoring requirements.
Texts and standards cited
- SIA 414Dimensional tolerances in building construction