Façade hose testing: protocol, test areas and reading results

On metal-framed curtain walls, the on-site hose test validates watertightness before interior linings are installed. You will learn how to adjust the flow rate according to standard SIA 331, target critical mullion-transom junctions, and record observations in an enforceable joint inspection record.

Key takeaways

  • Standard SIA 331 governs the verification of watertightness on assembled metal façades.
  • The spray rate and exposure duration must strictly comply with the validated test parameters.
  • Hosed areas primarily target framing nodes, junctions, and spandrel sealing.
  • The joint inspection record signed on site formally binds the contractor, the site management, and the inspector.

Spraying parameters and targeting critical areas on the metal frame

In situ water spray testing allows direct water paths through the envelope to be tracked before interior finishes conceal the load-bearing metal structure. Conducting this test is based on the principles of standard SIA 331 for curtain walling and windows, ensuring that assemblies withstand actual weather conditions without liquid water ingress.

To ensure technical representativeness, the test uses a spray bar equipped with solid cone nozzles, supplied under regulated pressure. Water must be sprayed perpendicular to the plane of the glazing or metal cladding, with continuous sweeping covering all joints in the selected area.

Control parameters for the on-site hose test
ParameterUsual target valueMeasurement toleranceInspection tools
Linear spray rate2 l/min per linear metre of joint± 10%Calibrated in-line flow meter
Operating pressure at nozzles200 to 300 kPa (2 to 3 bar)± 20 kPaGlycerine-filled pressure gauge
Nozzle-to-façade distance250 to 400 mm± 25 mmRigid measuring gauge
Spray duration per section15 to 30 continuous minutes- 0 / + 2 minSite stopwatch

The selection of test areas is not done at random. The site foreman and the site manager must target the most vulnerable details of the metal system: intersections between mullions and transoms, junctions at spandrel profiles, vertical expansion joints in the framework, and building corners. Spraying should be carried out from bottom to top to identify precisely the exact entry point of any suspect water ingress.

Detection of water ingress, defect management and joint inspection record

Throughout the duration of external spraying, a two-person team inspects the inner face of the load-bearing metal structure. Observation requires powerful grazing floodlighting, inspection mirrors for blind spots, and blotting paper or moisture-indicating strips placed at the low points of the drainage rebates.

  • Direct visual inspection of hollow sections and fixings.
  • Verification of drainage weep holes in pressure plates.
  • Check of the continuity of the perimeter waterproofing membrane (EPDM or butyl).
  • Monitoring the mullion base and the base plate anchored to the concrete slab.

If water appears internally, the elapsed time since nozzle activation and the exact location of the resurgence must be recorded immediately. In a mullion-transom façade properly designed according to standard SIA 331, water penetrating external joints must be guided by internal drainage channels outwards without ever overflowing towards internal components.

  1. Defect location and water shut-offInterrupt the flow immediately as soon as a droplet appears. Mark the location on the setting-out drawing and tag the metal profile.
  2. Diagnosis of the water ingress pathDismantle the affected pressure plate to check the alignment of setting blocks, the watertightness of fixing screws, and the bonding of sealing plugs.
  3. Remediation and re-testingReplace the defective component or remake the junction seal according to system supplier guidelines, then resume the full hose test for the nominal duration.

The operation concludes with the signing of the joint inspection record. This document formalises the conformity of the works or details the reservations noted. Art. 367 CO specifies the obligations relating to the client's inspection of the works after delivery; for immovable works, the client has 60 days to report defects. By carrying out the test at an early stage and jointly before finishes are applied, the contractor secures the conformity of its façade system.

Implementation of the spray rig and calibration according to standard SIA 331

The on-site watertightness test for a metal-framed façade is not improvised with a simple hose nozzle. To achieve an exposure representative of driving rain in accordance with the requirements of standard SIA 331, the apparatus uses a spray bar fitted with calibrated solid-cone nozzles. The spray bar is fixed parallel to the plane of the glazing or infill panel, at a distance rigorously adjusted between 300 mm and 500 mm from the load-bearing profiles.

The dynamic pressure at the spray bar must be stabilised using a calibrated pressure gauge and an adjustable pressure reducing valve. Any hydraulic surge distorts droplet dispersion and alters the impact energy on the EPDM gaskets and pressure plates. Overall volumetric flow rate is checked at the base of the rig before starting the test, using a mechanical flow meter or by timed weighing into a graduated container.

Operating hose parameters according to metal façade configuration
Configuration testedApplied flow rateWater pressure (nozzle)Duration per sequence
Mullion-transom junction in reveal2.0 L/min·m²2.0 to 3.0 bar30 minutes
Steel structural movement joint2.5 L/min·m²2.5 bar45 minutes
Façade base and sill flashing3.0 L/min·m²2.0 bar30 minutes
Glass roof / brise-soleil fixing penetration2.0 L/min·m²3.0 bar40 minutes

Application systematically begins at the bottom of the structure, moving upwards in successive stages. This ascending chronology prevents runoff water from upper zones from masking an emerging leak at a lower transom or a structural work interface. Each spray level must be maintained for the prescribed duration without interruption before moving the rig to the upper bay.

Joint inspection record protocol and defect traceability

The in situ hose test only has probative value if conducted in the presence of the site management and the metal façade contractor. As soon as the valves are opened, a two-person team monitors the interior face of hollow sections, setting blocks, and air/vapour barrier membranes. Direct observation is supplemented by using indicator blotting paper slipped beneath metal mullion claddings and, where appropriate, an endoscope to inspect the interior of decompression chambers.

  1. Baseline environmental conditions recordRecording external ambient temperature, wind speed with an anemometer, and moisture condition of profiles prior to water exposure. The test is postponed if wind exceeds thresholds that disrupt the spray cone.
  2. Continuous internal inspection during sprayingMeticulous examination of through-fixings, transom end-cap notches, perimeter sealing joints, and metal rebate drainage slots.
  3. Post-spray observation periodMaintaining surveillance for at least 30 minutes after nozzle shut-off to detect delayed ingress caused by slow capillary action along thermal breaks.
  4. Immediate signing of the inspection recordJoint drafting of the document recording the tested bay, any runoff patterns, measured flow rates, and the decision on validation or remediation.

In the event of confirmed water ingress, standard SIA 331 governs the classification of the defect. The contractor proceeds with partial removal of pressure caps, checking the compression of vulcanised gaskets and inspecting silicone bridging pieces at transom intersections. When remedial sealing works are carried out on the metal framework, a second full hose test on the same zone is required to validate the effectiveness of the corrective action before final closure of interior linings.

The joint inspection record of hose testing forms a core document in the as-built record file. After delivery, the client inspects the state of the works as soon as feasible in accordance with art. 367 CO and gives notice of defects to the contractor. This document certifies that the load-bearing framework and its glazed envelope meet the impermeability requirements specified for the project prior to the installation of suspended ceilings and floor finishes.

Managing water ingress and formal clearance of reservations

The appearance of water on the interior side during a hose test on a metal-framed curtain wall stops the test sequence. The absolute priority on the construction site is to locate the exact path of the fluid before water spreads into insulation, raised technical floors, or along steel mullions and transoms. Water often enters several metres away from the visible discharge point, following profile slopes or unsealed internal drainage paths.

  1. Immediate recording and dryingMark the exact location of water ingress with an indelible pen or a photographic scale. Shut off the spray bar, dry the wetted parts with an air nozzle or lint-free cloth, then remove pressure plates and metal covers to inspect glazing gaskets and sealing membranes.
  2. Joint inspection recordDraft on site a record signed by the metal fabricator, the site management and the façade specialist. This document notes the time water appeared, residual pressure, the affected nozzle and impacted building elements.
  3. Targeted remediationProhibit makeshift repairs using surface sealant applied from the outside. The waterproofing barrier must be rectified at its origin: repositioning or replacing EPDM gaskets, re-bonding flashing sheets, or cleaning obstructed drainage weep holes.
  4. Validation re-testAfter observing the prescribed vulcanisation or curing times for new materials, subject the repaired zone again to the complete hose test protocol, using the same duration and pressure parameters.

If the client challenges the conformity of the works following repeated leaks, the contractual provisions apply. Under art. 367 CO, after delivery, the client inspects the state of the works as soon as feasible and reports defects to the contractor. In the event of persistent failure during re-tests, CO specifies the rights of the client in case of defects in the works, notably opening the way to remediation of the defective façades at the contractor's expense.

Frequently asked questions

How can one distinguish water ingress from internal condensation during the test?

Cold water sprayed onto glazing and metal sections rapidly chills internal surfaces, encouraging condensation when warm, humid ambient air is present. Water ingress shows as continuous, targeted, and localised flow along sections or beneath weather seals. Condensation, by contrast, forms a diffuse and uniform mist across the entire exposed glass or metal surface with no distinct entry point.

Can a façade hose test be performed in high winds?

No, the on-site hose test must be postponed if wind disturbs the spray pattern. Excessive wind speed deflects the water curtain delivered by the spray bar or nozzle, preventing the uniform wetting specified by standard SIA 331. Furthermore, dynamic pressures exerted by gusts distort gravity-driven runoff conditions and prevent defects from being objectively attributed to façade geometry.

What must be done if thermal insulation batts absorb water during spraying?

Any mineral wool slab or thermal insulation soaked with water during testing must imperatively be removed and replaced. Wet insulation permanently loses its initial thermal performance, sags inside cavities, and holds residual moisture against the load-bearing metal frame over long periods. This encourages stress corrosion cracking and mould growth behind interior linings, even after the load-bearing sections have apparently dried out.

Who must supply and pay for the water needed to perform the hose test?

Unless contractually agreed otherwise in the tender specifications, the general water supply and site utility connections are the responsibility of the client under common site facilities. Conversely, the metalwork contractor supplies the specific inspection equipment, such as the calibrated spray bar, pressure gauge, hoses, and flow meter, and provides the labour required to set up, calibrate, and conduct the joint test.

Texts and standards cited

  • SIA 331Windows and window façades: performance requirements and watertightness testing
  • CO art. 367after delivery, the client inspects the state of the works as soon as feasible and reports defects to the contractor; for immovable works, they have 60 days to report them and a shorter contractual period is void (para. 1bis, in force since 1 January 2026); each party may request an examination by experts (para. 2).
  • COrights of the client in case of defects in the works: rejection, price reduction, repair, damages; any clause agreed in advance restricting or excluding the right to repair defects is void if the defect concerns a structure (para. 2bis, since 1 January 2026).