Key takeaways
- Standard SN EN 1090 requires full traceability of steels and welding qualifications.
- Type 3.1 material test certificates must be archived before workshop fabrication of sections begins.
- Torque-controlled tightening reports must strictly be drawn up during assembly on the construction site.
- As-built drawings precisely incorporate anchor adjustments and modifications approved by the engineer.
Collect material and fabrication traceability documents right from the workshop
Compiling the as-built file does not begin when the scaffolding is dismantled, but as early as the procurement of commercial steel products. In steel construction, standard SN EN 1090 sets strict traceability requirements according to the execution class selected for the project. Every rolled section, gusset plate, and batch of fasteners must be unambiguously linkable to its respective mill test certificate.
Attempting to retrieve rolling certificates several months after erection is a frequent dead end. Offcuts have been cleared, heat numbers stencilled on bundles disappear under primer coats, and steel stockholders charge heavy fees for retrospective searches. The site manager must demand material certificates upon delivery of the beams to the fabrication workshop.
| Required document | Issuer | Critical collection stage |
|---|---|---|
| Material certificates (3.1) | Steel mill or stockholder | Arrival of sections at the workshop |
| Welder qualification test certificates | Certification body | Prior to start of welding operations |
| Welding procedure specifications (WPS) | Welding coordinator | Prior validation of joints |
| Non-destructive testing reports | Independent or qualified internal inspector | After welding of main connections |
The lack of these documents at final handover frequently blocks the release of financial guarantees. The client may, pursuant to the Code of Obligations (CO), assert its rights regarding the inspection of the work and withhold payments for as long as proof of structural compliance is not provided.
Record construction site inspections and finalise as-built drawings
On the construction site, assembly operations generate transient data that becomes inaccessible once structures are painted, fireproofed, or encased by composite facades. Inspection reports must be signed immediately on site by the erection foreman. This applies first and foremost to the casting of anchor bolts, base plate levelling and grouting, and the controlled tightening of high-strength (HR) or preloaded bolts.
- Survey of anchors and setting-out tolerancesMeasure levels and flatness of concrete pier tops as well as anchor bolt positions before landing the steel frame. Record deviations from theoretical grid lines.
- Connection tightening reportsComplete daily tightening logs indicating the bolt batch used, the method applied (calibrated torque wrench or combined method), and achieved torque values.
- Corrosion protection touch-up reportDocument in writing and with photographs the treatment of site-welded areas, remedial holes, and bolt heads in accordance with the prescribed protective coating system.
- Red-line mark-up of erection drawingsRecord on the site office erection drawing every geometric adjustment, unexpected cope, or additional stiffener requested by the civil engineer.
As-built drawings (revised "as-built" drawings) represent the culmination of the file. They are not merely a reprint of initial workshop drawings. They must establish the actual position of primary members, the effective layout of vertical bracing, altered hole diameters used to absorb structural work tolerances, and penetrations left for other trades.
Pursuant to art. 365 CO, the contractor is liable for the sound quality of the materials supplied. The complete as-built file constitutes the physical proof certifying that the structure erected on concrete supports fully complies with the project's structural design and safety requirements.
Structure the technical folder in accordance with standard SN EN 1090
Compiling the as-built file for a steel frame or load-bearing facade cannot be improvised when scaffolding is dismantled. Applying standard SN EN 1090 imposes absolute documentary rigour connecting each installed component to its manufacturing records. If certificates are not indexed as deliveries arrive, the steel fabricator faces irretrievable gaps once elements are cast in, painted, or clad by finishing trades.
The final technical folder combines physical evidence from the workshop and on-site intervention reports. Technical data sheets for corrosion protection systems—hot-dip galvanising or powder coating—must incorporate dry film thickness measurements taken before dispatch. Any substitution of grade S235 steel with S355 due to procurement constraints must be logged and formally approved by the structural engineer to appear in the final documents.
| Work item | Mandatory documents | Document origin | Risk in case of late omission |
|---|---|---|---|
| Rolled sections and plate girders | Material certificates (type 3.1), manufacturer DoP | Rolling mill / Workshop | Inability to verify steel impact toughness |
| Critical welded joints | Welding specifications (WPS), NDT reports | External inspector / Workshop | Destruction of claddings for retrospective testing |
| Preloaded bolting assemblies | Bolt/nut batch certificates, tightening reports | Supplier / Construction site | Uncertainty regarding applied torque or angle |
| Anchors and fixings | Technical approvals, tightening torque records | Installers / Erection foreman | Refusal of sign-off by the civil engineer |
| Paint and galvanising | Thickness reports, treatment warranty vouchers | Applicator subcontractor | Forfeiture of warranty claims for premature corrosion |
Securing as-built records: erection reports and as-built drawings
On the construction site, execution data collection stops at the precise moment structural components become inaccessible. Inspection reports for controlled tightening of preloaded bolts (HR or HV) must record torque wrench sizes, the method used (torque or combined torque-rotation), and fastener batch numbers. Once suspended ceilings are fitted or fire spray applied, non-destructive verification is impossible without significant cost overruns.
Compiling as-built drawings requires rigorous recording of all site adjustments made during lifting. Site-drilled penetrations, unpredicted shims under column base plates, and displaced anchor studs must appear on the final prints submitted to site management. Under the Code of Obligations (CO), the contractor is liable for the sound execution of their work; accuracy of as-built drawings protects the contractor in the event of subsequent claims.
- Post-erection geometric surveyCheck plumb of steel columns and beam levels with a total station prior to final tightening. Immediately plot actual deviations against standard SN EN 1090 tolerances on the site drawing set.
- Joint sign-off on tightening reportsHave connection tightening sheets countersigned by the quality manager or appointed engineer as soon as a bay is completed, prior to any intervention by facade contractors or plasterers.
- CAD/BIM model updateIncorporate site modification sheets into the workshop digital model to generate final general arrangement, marking, and detail drawings bearing the "as-built" designation.
- Preparation of maintenance fileCompile surface coating maintenance recommendations, bolted connection inspection intervals, and the general declaration of conformity for ten-year archiving.
The final financial settlement of the works contract and release of bank guarantees depend directly on the delivery of this complete set of documents. Under standard SIA 118, site management may withhold the acceptance report until the as-built file is deemed complete and compliant with the structure's structural specifications.
Managing documentary non-conformities and acceptance disputes
On the construction site, the lack of supporting evidence at final sign-off blocks the release of final advance payments and the signature of the acceptance report. When self-inspection reports are missing or a material certificate cannot be found, the structure cannot be declared compliant with standard SN EN 1090 requirements. The burden of proof rests with the steel contractor. Any undocumented component is deemed unverified by site management.
| Missing document | Direct impact | Substituted technical action |
|---|---|---|
| Missing 3.1 material certificate | Lack of structural steel traceability | Sampling test coupons from sections for chemical analysis and tensile testing at an accredited laboratory |
| Missing tightening reports | Uncertainty regarding bolt preloading | Retrospective testing campaign by sampling with a calibrated torque wrench in accordance with the execution class |
| Misplaced non-destructive testing reports | Doubt concerning soundness of weld beads | Complete repeat of non-destructive testing on site by a certified inspector (magnetic particle, ultrasonic testing) |
| As-built drawings not updated | Geometric discrepancy with structural work | 3D land surveyor survey campaign using a total station to establish actual as-built records |
Pursuant to art. 367 CO, the client inspects the state of the work as soon as feasible and notifies the contractor of defects. If dimensional discrepancies are observed on as-built drawings or a critical documentary gap exists, the client may refuse acceptance until compensatory tests have certified the structural steelwork's serviceability. The costs of expert assessments, core sampling, or retrospective tightening torque verification remain at the sole expense of the defaulting steel contractor.
Frequently asked questions
How can a lost 3.1 material certificate for sections already erected be regularised?
Contact the stockholder or rolling mill using the heat numbers hard-stamped on the steel sections. If physical markings have disappeared under the anti-corrosion coating or remain illegible, the contractor must commission an accredited laboratory to take a material sample from an unstressed zone of the structure to carry out spectrometry and mechanical tests certifying the steel grade.
What should be done if bolt tightening reports were not filled in during assembly?
A failure to record requires a joint verification campaign on the construction site. For preloaded or torque-controlled connections, the foreman must repeat verifications on a sample basis using a calibrated torque wrench in the presence of site management. A retrospective inspection report is then compiled, stating the method applied, measured torque values, and any bolt replacements.
What is the legal status of hand-annotated as-built drawings?
Workshop drawings marked up in red on the construction site serve as temporary proof, but do not constitute the final as-built document. They only serve as survey input for the design office. To be incorporated into the official as-built file delivered to the client, amendments must be drafted into final CAD drawings, endorsed by the responsible civil engineer, and clearly marked as-built.
Who must bear the cost of retrospective non-destructive testing required at acceptance?
If the inspection plan initially prescribed by standard SN EN 1090 was not adhered to during fabrication or assembly, all remedial tests are at the steelwork contractor's expense. Conversely, if site management requests additional examinations not specified in the specifications and the contractor has provided all contractual inspection reports, the financial burden falls upon the client.
Texts and standards cited
- SN EN 1090Execution of steel structures and aluminium structures
- CO art. 367after delivery, the client inspects the state of the work as soon as feasible and notifies the contractor of defects; for an immovable work, the client has 60 days to give notice, and a shorter contractual period is null and void (para. 1bis, in force since 1 January 2026); each party may demand an examination by experts (para. 2).