🧱 CFC 215Steel: grades, sections and execution classesChapter 3 of 10 in the section

Marking and traceability: linking a section to its test report

Upon delivery of a framework or ten years after assembly, you must be able to link every beam to its original inspection certificate. This chapter details specific inspection procedures upon delivery, marking methods for structural steels and the rigorous organisation of the traceability file required by standard SN EN 1090.

Key takeaways

  • Receiving checks cast numbers on the delivery note against the section.
  • The inspection certificate must correspond precisely to the ordered grade and requirements.
  • Marking of parts prevents any confusion between workshop cutting and the construction site.
  • The traceability file archives certificates to safeguard the ten-year liability of the work.

Check delivery and lock down section identification from receipt

As soon as sections are unloaded in the storage yard or workshop, the compliance chain is initiated. The site foreman or workshop manager systematically checks that the delivered bars match the dispatch note and purchase order. On each hot-rolled section, the cast number and steel grade are marked by the rolling mill, either by cold stamping at the bar end or by secure labelling. If this visual match is missing, the bar cannot enter production.

Inspection certificate
Inspection document issued by the steel producer certifying the actual chemical and mechanical properties of the heat from which the section originates, in accordance with the specified technical requirements.

Managing offcuts and cropped pieces is the critical point of workshop marking. As soon as a main beam or column is cut, the element mark and heat code must immediately be transferred onto each usable length. Depending on the execution class defined for the structure by standard SN EN 1090, traceability requirements vary: batch traceability may suffice for simple structures, but unbroken individual traceability becomes essential for structures subject to severe loading.

Traceability requirement levels according to execution class
Execution class (SN EN 1090)Material traceability requirementPermitted marking method
EXC1By delivery batch or overall gradeIndustrial paint, labelling or permanent marker
EXC2Traceability ensured from delivery to erectionLow-stress mechanical cold marking or engraving
EXC3 / EXC4Full individual traceability per componentControlled cold stamping with low-stress punch without notch effect

Compile the traceability file to prove provenance in the long term

Ten or twenty years after erecting a steel structure, the client or a forensic expert may require proof of the mechanical properties of a specific beam following an incident or vertical extension. The steel construction company is responsible for the conformity of materials incorporated into the structure. In accordance with art. 365 CO, the contractor is liable for the sound quality of the material supplied.

  1. Recording the inspection certificateUpon arrival at the workshop, scan the producer's certificate of conformity and file it in the IT database under the job number and cast number.
  2. Allocation on fabrication drawingsTransfer the unique mark of the cut element directly onto the workshop drawings and the cutting list from the technical office.
  3. Recording assembly operationsLink the section mark, welding consumable batch numbers and qualified welder identities on the shop traveler.
  4. Archiving in the as-built documentationAssemble all inspection sheets, certificates and as-built drawings into the final execution file submitted to the site management.

Documentary rigour protects the company in the event of future disputes. If a brittle fracture occurs or a latent defect is suspected, the contractor must immediately be capable of retrieving the specific certificate corresponding to the affected section to prove the impact strength and yield strength supplied at the time. Furthermore, according to art. 370 CO, the contractor is released from liability upon acceptance of the work, except for defects that could not be detected during regular inspection or that were intentionally concealed.

Constituent products must be identified and documented at each stage of manufacturing, so as to ensure the required traceability between the finished product and the corresponding inspection documents.

Norme SN EN 1090-2

Transferring marking and managing offcuts in the fabrication shop

As soon as a bar leaves the storage yard for the cutting or notching line, the main risk lies in losing the rolling mill's original identification. A cut HEB 300 or angle profile immediately loses its cast identification if the section carrying the physical mark is scrapped or cut off. Under standard SN EN 1090, the structural steel workshop must apply a strict mark transfer procedure prior to any material separation.

  1. Locating the initial markingBefore feeding the section into the band saw or flame-cutting table, the steel fabricator locates the position of the steel mill stamp or barcode label.
  2. Mechanical transfer or stampingThe fabrication piece mark and internal cast number are transferred onto each usable length using round-nose (low-stress) punches for sensitive grades, or by mechanical engraving.
  3. Immediate marking of reusable offcutsAny length exceeding the minimum reuse length defined by the workshop immediately receives the cast identifier and the initial fabrication order number, marked with permanent paint or restamped.
  4. Entry in the shop travelerThe operator records the exact breakdown of the bar on the cutting sheet: which connection component or beam was cut from which length, and under which material identifier.
Identification transfer methods by zone and stress levels
Marking techniquePermitted zoneAssociated technical riskTarget execution class
Traditional sharp-edged punchEnds outside welded joint areasCrack initiation under mechanical fatigueEXC1 only
Round-nose punch (low-stress)Section web, low-stress zonesLimited notch, visual inspection requiredEXC2 and EXC3
Chloride-free industrial paintAny clean surface prior to blast-cleaningRemoval during shot blasting operationsAll classes
CNC dot-peen engravingMachining zones, beam flangesControlled depth without notch effectEXC2 to EXC4

Linking to the inspection certificate and ten-year file archiving

Ten years after the acceptance of the work for a framework or load-bearing façade, an expert assessment or vertical extension requires finding the actual yield strength and impact strength of a specific section. To comply with art. 365 CO, according to which the contractor is liable for the sound quality of the material supplied, the steel fabricator must be able to work backwards: start from the mark number painted on the erected structure to trace back to the original factory inspection certificate.

The cornerstone of this documentary continuity lies in systematic indexing. The inspection certificate (type 3.1 according to the reference standard for steel products) received from the stockholder or steelworks is digitised and assigned an internal batch number. This number appears on the fabrication drawings, on the erection list and on the welder's self-inspection sheet.

  • As-built erection marking drawings indicating the exact allocation of main sections.
  • Type 3.1 material inspection certificates filed by cast and linked to structural component numbers.
  • Non-destructive testing reports for welds (visual, penetrant, magnetic particle, ultrasonic) linked to key connections.
  • Technical data sheets for preloaded or non-preloaded structural bolting assemblies with their declarations of performance.
  • Declaration of conformity and CE marking of the structure under standard SN EN 1090 submitted to the site management.

In the event of a subsequent dispute regarding abnormal deflection or brittle fracture during alterations, the lack of this irrefutable link between the installed component and its certificate leaves the contractor unable to justify the work. Conversely, a complete file allows responsibilities to be isolated immediately: rolling defect attributable to the steelworks or loading error attributable to building operations.

Managing traceability discrepancies and restoring compliance

On the construction site or in the workshop, losing the mark of a rolled section compromises the entire compliance chain. Under standard SN EN 1090, a structural element lacking a physical link to its inspection certificate cannot be incorporated into a required execution class without approved corrective actions. Art. 365 CO reiterates that the contractor is liable for the sound quality of the material supplied. Any doubt regarding the identity of a steel requires physical segregation of the bar.

Handling protocol by level of documentary failure
Identified discrepancyImmediate actionRemedial measure
Workshop mark erased or illegibleQuarantine in an identified areaDimensional check, cutting list verification and centre-punch restamping
Inspection certificate missing or incorrectHalting of cutting or erectionClaim to supplier demanding certificate within 48 h
Untraceable cast without documentationFormal refusal to incorporate into structureDestructive laboratory testing or downgrading to secondary use

When the exact origin of a section cannot be found, the structural engineer and site management must be notified in writing. To requalify the component in the traceability file, optical emission spectrometry chemical analyses, tensile tests and impact tests must be entrusted to an accredited laboratory. This testing campaign, representing costs of around 1,500 to 3,000 CHF per grade depending on complexity, enables a ruling on the actual grade (S235, S355) and the weldability of the component.

If the client refuses requalification testing or if the result invalidates design assumptions, the steel must be removed from site. The contractor records the incident in the final technical file by archiving the disposal note or downgrading form for secondary non-load-bearing components.

Frequently asked questions

What should be done on a construction site if a section is delivered without its centre-punch marking?

The component must be isolated immediately and marked with permanent marker as non-compliant. The site foreman cross-checks the delivery note, actual dimensions measured with callipers and the workshop packing list. If the match is definitive, the construction manager records the deviation, confirms identification against the general arrangement drawing and authorises restamping of the mark prior to hoisting.

Which inspection certificate must be required for hot-rolled steel beams?

Standard SN EN 1090 generally requires a specific type 3.1 inspection certificate according to the reference standard for rolled structural steels. This official document issued by the steel mill confirms the ladle chemical analyses and actual mechanical properties obtained through tensile and impact testing. A type 2.2 certificate of non-specific testing remains insufficient for standard execution classes of a load-bearing building.

Can workshop offcuts without a cast number be used for stiffeners?

No. Even for a simple gusset or web stiffener, the grade and weldability must be guaranteed. In execution class EXC2 or higher under standard SN EN 1090, every component welded to the load-bearing structure contributes to load transfer. Without full traceability to an original certificate, the plate must be scrapped or reserved for temporary jigs not forming part of the structure.

What does the traceability file transmitted at acceptance of the work contain?

The file submitted to the site management brings together erection drawings with fabrication marks, the component list linking each mark number to its 3.1 inspection certificate, dimensional check sheets and non-destructive weld testing reports. This complete collection is retained for at least ten years to prove structural integrity in the event of an incident or alteration.

Texts and standards cited

  • CO art. 365material and ground: the contractor is liable for the sound quality of the material supplied
  • CPbreach of the recognised rules of construction: whoever, in directing or executing a construction or demolition work, breaches the recognised rules of construction and knowingly endangers the life or physical integrity of persons shall be liable to a custodial sentence or a monetary penalty