🧱 CFC 215Corrosion protection and fire resistanceChapter 8 of 10 in the section

Details that trap water: inverted channel sections, laps and low points without drainage

Geometric design and assembly defects in external steelwork create areas of standing water. This chapter details installation rules for open sections, the provision of drainage holes at low points, and the correct treatment of sheet laps to prevent premature corrosion caused by weathering.

Key takeaways

  • Systematically install channel sections with flanges pointing downwards to prevent water trapping.
  • Drill a drainage hole at the lowest point of each box section or base plate.
  • Apply a bead of sealing mastic at undrained sheet laps.
  • Check the minimum slope of bearing surfaces to ensure natural run-off of rainwater.

Orientation of open sections and elimination of undrained low points

In external steel construction, standing rainwater accelerates the degradation of the corrosion protection system, whether hot-dip galvanising or a multi-coat paint system. Corrosion invariably starts in areas where moisture remains stagnant instead of being drained by gravity. The orientation of sections during workshop preparation and site assembly is the primary lever of prevention.

Where structural geometry requires an enclosed low point, as in the case of embedded column base plates or welded box girders, the formation of a basin is inevitable without specific measures. On an external steelwork construction site, the site manager and the site foreman must ensure that every enclosed channel has an escape route for run-off and condensation water.

Low point without drainage
Geometric zone of a steel component where liquid water accumulates by gravity without the possibility of natural run-off or rapid drying by ventilation.

To neutralise these critical zones, connection details must incorporate systematic clearances. Continuous peripheral sealing welds are preferred on enclosed box sections. For open sections installed on an incline, gusset plates must never block the bottom of the section web: a run-off chamfer at the corner of the gusset allows water to slide away without accumulating against the stiffener.

Technical provisions for lap drainage and clearance perforations

Overlaps of steel sheets or load-bearing metal facade elements are a frequent source of water ingress through capillary action. When two steel surfaces overlap outdoors without an interlayer seal or a ventilated cavity, water is drawn between the walls by suction. This trapped film of water starves the metal of oxygen and triggers particularly aggressive crevice corrosion.

  1. Design the overlap directionOrient the lap in the downward direction of flow, so that the upper sheet covers the lower sheet in the direction of the slope.
  2. Install the capillary breakInsert a preformed sealing strip or a bead of elastomeric mastic compatible with the corrosion protection coating prior to bolting.
  3. Drill the drainage holeDrill drainage holes of an appropriate diameter at the lowest point of the overlap area or box section.
  4. Protect site drillingsApply a cold corrosion protection touch-up paint to the bare edges of holes drilled after galvanising or painting.
Minimum drainage hole diameters according to exposure
Connection typeRecommended drainage diameterComplementary measure
External column base plate12 mm to 16 mmGrout chamfer sloping outwards
Enclosed box section or ventilated hollow tube10 mm at the endsCheck for absence of internal weld spatter
U or C section closed by a gusset10 mm at the corner point15 mm chamfer on the connection gusset

The provision of drainage openings must be strictly monitored during assembly. A drainage hole that is too small risks being rapidly clogged by construction site dust or atmospheric deposits. Site foremen ensure that the perforations indicated on the workshop drawings are clear after surface treatment and that no paint or galvanising zinc plug blocks the hole. In accordance with standard SIA 118, adjustments on the construction site must comply with the execution requirements specified by the design professionals.

Assessment of water traps on external steel structures

In external steel construction or composite facade load-bearing structures, premature deterioration of corrosion protection systems almost systematically stems from standing liquid water. When an open section such as a UPN or a UPE is installed with flanges pointing upwards, it forms a natural receptacle for rainwater, condensation, and contaminated condensates. Standing water dissolves acidic or saline atmospheric deposits, destroys the hot-dip galvanising passivation layer, and prematurely degrades the paint coats of the duplex system.

Undrained laps between connection plates, base plates or splice plates create capillary ingress. Water enters between two steel surfaces held in direct contact without sealing or a ventilation gap. Trapped in an oxygen-deprived micro-space, this moisture causes extremely aggressive crevice corrosion. This mechanism produces expanding rust whose volume (up to six times that of the original steel) exerts mechanical pressure capable of deforming bolted assemblies and shearing bolts.

At low points without drainage, such as the base of an external column bedded on a concrete footing or the bottom of a cladding bracket, run-off water stagnates against end plates. Without a sealed bedding joint or a drainage void, the steel remains permanently submerged in a puddle, negating the full effectiveness of the corrosion protection system specified according to the SIA standard applicable to the structure.

Constructive solutions, drainage drilling, and assembly details

Corrosion prevention on external steel structures relies on free-draining geometric design. The first rule is to prioritise orienting open sections with flanges facing downwards or webs vertical. When upward-pointing flange orientation is dictated by architectural interface constraints or load transfer requirements, the provision of drainage holes becomes mandatory right from the workshop fabrication stage.

Summary of critical details and corrective measures in external steel construction
At-risk configurationDegradation mechanismConstructive solution in workshop/on site
UPN/UPE section installed open side upRainwater retention, standing water and freezing in cavityTurn the section over or drill Ø 10 to 12 mm drainage holes every 500 mm at the lowest point
Unsealed plate/splice overlapCrevice corrosion by capillary action and expansive rustInsertion of an elastomeric interlayer or continuous sealing weld bead depending on the design
Column base at low point on concrete footingStagnation of run-off water at the base of the plateCreation of a concrete upstand raised by at least 50 mm and self-levelling, free-draining bedding mortar
Horizontal bracing gussetWater retention in bend angles and node pointsCorner cutout (20x20 mm drainage chamfer) on gussets to let water flow away

Drainage holes must be positioned at the lowest geometric points of each retaining box section or profile. A drainage hole with a diameter of less than 10 mm risks clogging rapidly due to dirt, dust deposits, and moss growth. During hot-dip galvanising, these same openings also serve as air vents and liquid zinc passages, ensuring complete coating of the internal surfaces of hollow sections and assemblies.

  1. Checking workshop drawings and identifying water trapsCheck the relative position of open sections and ensure that every area susceptible to trapping water features a drainage opening identified on the working drawings.
  2. Adapting gussets and end platesProvide corner cut-outs or chamfers of at least 20 mm on connection gussets to prevent water from stagnating against the web of the section.
  3. Installing shims and bedding mortarsPack and grout base plates on an upstand raised above the finished ground level to elevate the structure above splash zones.
  4. Inspection and corrosion protection touch-ups after assemblyEnsure after tightening the connections that drainage holes are not blocked by mortar, touch-up paint, or construction site debris.

If an undrained detail shown in the design is discovered on the construction site, the steelwork contractor must intervene before final painting or the closing up of the facades. If the modification affects the load-bearing cross-section or the capacity of the member, approval by the timber-steel engineer or the structural engineering consultancy is mandatory to ensure safety and compliance with the construction work ordinance.

Managing drainage non-conformities and on-site repairs

When a water-trapping structural detail is identified during handover inspections or in the operational phase, corrective action must be taken immediately to halt the premature degradation of the coating and the steel. Stagnant accumulation accelerates stress corrosion and localised perforation. On the construction site, the most frequent errors involve installing channel sections open side up without drainage holes, omitting voids in end plates located at low points, and directly fixing overlapping sheets without a sealing strip or a ventilated drainage cavity.

  1. Diagnostic assessment and survey of standing water pointsIdentify all undrained low points, upward-facing open sections, and capillary overlaps during a visual inspection after spraying or rainfall.
  2. Drilling required drainage holesDrill drainage holes at low points (minimum diameter 10 mm) as close as possible to the retention area, ensuring the load-bearing cross-section is not weakened according to the engineer's drawings.
  3. Anti-capillary treatment of overlapsInsert a neutral single-component sealing mastic or rot-proof levelling shims to maintain a ventilated drainage air gap of at least 5 mm between overlapping surfaces.
  4. Corrective corrosion protection of machined surfacesImmediately treat hole edges by light grinding, degreasing, and applying the corrosion protection touch-up system in accordance with good engineering practice.

In the event of a dispute relating to a design defect involving water retention on an external steel structure, the client's rights regarding the remediation of defects are governed by art. 368 CO. The contractor's liability for construction defects is subject to the limitation period under art. 371 CO. Systematic compliance prior to enclosing the connections remains the only guarantee against premature defects.

Frequently asked questions

What is the recommended minimum diameter for a drainage hole in an external steel section?

The minimum diameter of a water drainage hole must be 10 mm. A smaller diameter risks being rapidly blocked by dust, oxide deposits, or mill scale. On hot-dip galvanised elements, this hole also permits venting and the run-off of liquid zinc during the galvanising bath in the workshop.

How should a channel section be treated if it must be installed open side up?

If the open-side-up orientation of the channel is required by architecture or structural design, 10 mm drainage holes must be provided at a maximum of every 1.5 metres and at every absolute low point. Another solution consists in capping the section with a continuously welded top plate with a run-off slope.

Why does an unsealed sheet-on-sheet lap rust faster outdoors?

Fixing two sheets directly against each other creates a capillary gap. Rainwater enters by capillary action and cannot evaporate. This continuous standing moisture rapidly destroys the paint coat or zinc through stress corrosion. A sealing mastic must be inserted, or a gap of at least 5 mm maintained.

Can a drainage hole be drilled into a prestressed or highly stressed steel element?

No, any drilling in an area subject to high tensile or fatigue stresses must receive prior approval from the structural engineer. The location of the drainage hole must be moved to a neutral zone or the cross-section locally reinforced to prevent crack initiation under mechanical load.

Texts and standards cited

  • CO art. 368rights of the client in case of defects in the work
  • CO art. 371limitation period for the client's rights in respect of defects