Key takeaways
- Systematically install temporary lifelines on beams at ground level before any lifting.
- Calculate the actual available fall clearance, taking into account cable deflection and energy absorber deployment.
- Define specific safety measures in writing by consulting an accredited specialist on the construction site.
- Ensure the erector wears a properly adjusted harness with fall arrest equipment suited to the fall clearance.
Ground pre-assembly of the lifeline and anchoring rules before lifting
The risk of falling when walking on a beam flange twenty centimetres wide is extremely high during the erection of a steel structure. Working directly on open sections without prior collective protection is the main cause of serious accidents in steel erection. To ensure the safety of erectors as soon as they access the upper level, the temporary flexible lifeline must be fully fitted to the beam while it is still on the ground in the pre-assembly area.
- Preparation on the groundPosition the structural beam on stable timber baulks. Clean the top flange to remove rolling oils or manufacturing grease.
- Securing anchor postsBolt or clamp the steel anchor posts at both ends of the beam. Check the tightening torque recommended by the manufacturer of the anchor system.
- Cable tensioning and installationThread the stainless steel cable or reinforced textile strap through the intermediate and end supports, then apply the required pretension using a dynamometer.
- Lifting and verificationCrane the equipped beam into its final position. The erector can clip on immediately upon stepping out of the mobile elevating work platform to carry out node bolting.
Rigorous calculation of actual fall clearance and sign-off of written measures
Fall clearance represents the minimum free height required below the beam flange to prevent the erector from striking the ground or an obstacle in the event of a fall. An erroneous or imprecise calculation of this distance makes the use of a lifeline completely ineffective. The height available below the anchor point must strictly exceed the sum of the lanyard length, the energy absorber tear-out distance, dynamic cable deflection, and the height of the erector, plus a safety margin.
| System component | Typical value / Parameter | Impact on required height |
|---|---|---|
| Lanyard length including connectors | 1.50 m to 2.00 m | Determines the initial distance between harness and cable |
| Absorber deployment length | 0.75 m to 1.75 m | Extends under impact to limit arresting force |
| Dynamic deflection of the lifeline | 0.50 m to 1.50 m | Horizontal and vertical displacement of the cable under tension |
| Erector height and safety margin | 2.00 m (body height + margin) | Ensures a clear clearance margin above ground after full arrest |
If the fall clearance measured below the beam is less than the total calculated value (often between five and six metres depending on equipment), the use of a conventional fall arrest system with a tear webbing absorber is prohibited. In this situation, the designated safety specialist must record the alternative technical solution in writing: installation of a retractable fall arrester with fast-acting lock, exclusive use of a mobile elevating work platform, or installation of temporary safety nets.
Walking on narrow 20 cm beams and ground pre-rigging
An erector walking on a steel flange only twenty centimetres wide constitutes a work situation with a high risk of a serious accident. At this height, a loss of balance leaves no room for error. Installing a temporary lifeline directly on the steel profile while it is still on the ground is the only state-of-the-art method to eliminate the presence of unattached personnel on the structure during assembly.
In accordance with art. 29 OTConst, when it is technically not possible or too dangerous to erect edge protection, a facade scaffolding, a safety net, or a catch scaffolding, equivalent protective measures must be taken and laid down in writing with the involvement of an occupational safety specialist. This document must be included in the construction site safety plan and bear the signature of the safety manager for the steel erector.
- Inspection of the condition of rigid posts welded or bolted to the top flange on the ground.
- Tension of the steel wire rope or flexible anchor line checked with a dynamometer before lifting.
- Check the positioning of automatic intermediate shuttles allowing movement past angle plates without detaching.
- Wearing a full fall arrest harness adjusted at the thighs and chest with a construction site hard hat with chin strap tightened in accordance with art. 6 OTConst.
Calculation of actual fall clearance below the flange and technical sign-off
Actual fall clearance represents the minimum clear height required between the bottom flange of the beam and the first obstacle or the ground below the work area. An incorrect fall clearance calculation exposes the erector to a severe impact against the slab or an underlying structure before the fall arrester has locked completely.
| Arrest system component | Technical description | Margin / Integrated average value |
|---|---|---|
| Lanyard length | Connectors included between harness and cable | 1.50 m to 2.00 m |
| Absorber tear-out | Extension of the webbing during energy dissipation | 1.20 m to 1.75 m |
| Lifeline deflection | Sag of the steel cable under dynamic load | 0.50 m to 1.50 m depending on span |
| Harness slippage and erector height | Take-up of harness slack and erector height | 1.50 m |
| Clear safety margin | Mandatory clear space beneath the feet after arrest | 1.00 m net |
Where the available fall clearance under the structural frame is limited (less than six metres), the use of a conventional lanyard with textile energy absorber becomes ineffective. The site foreman must then enforce the use of retractable fall arresters with instant lock designed for structural steelwork or adapt the lifeline tension with the safety specialist.
- Precise measurement of height below the flangeMeasure the exact height with a laser distance meter between the underside of the steel profile and the nearest obstacle below (concrete slab, pipework, scaffolding).
- Verification of the calculation noteCompare the value measured on the construction site with the fall clearance calculation set out in the written safety measure drawn up by the specialist.
- Selection of personal protective equipmentEquip the steel erector with a twin tail lanyard with energy absorber or a retractable fall arrester suited to the actual measured fall clearance.
- Sign-off and instructions to the chargehandPermit access to the beam only if the calculated fall clearance is strictly less than the available free space beneath the work station.
Handling contingencies and deviations during tie-off on narrow beams
During the erection of steel structures, walking across beams with a minimum width of 20 cm requires absolute compliance with the fall arrest system. If the construction site reveals an altered layout, an unplanned level difference, or inadequate available fall clearance below the flange, erector movement must be halted immediately. The use of personal fall arrest equipment allows no on-site improvisation or guesswork regarding the fall factor.
When the clear height available below the bottom flange of the beam is less than the calculated stopping distance (comprising energy absorber elongation, lanyard length, and ground safety distance), the use of a flexible lifeline ceases to comply. In this case, art. 29 OTConst mandates the implementation of equivalent protective measures, duly validated in writing with an occupational safety specialist (safety engineer or Suva specialist). The use of a mobile elevating work platform (MEWP) or safety nets then becomes mandatory to safeguard the crossing area.
In the event of a technical dispute regarding safety conditions or anchor selection, the site manager records the work stoppages in the site logbook. The employer applies the general prevention principles laid down by LAA to ensure the physical integrity of the erection crew before any resumption of steelwork operations.
Frequently asked questions
What should be done if the ground-assembled lifeline has been damaged during the lifting phase?
If the cable, fastenings, or absorbers suffer impact or snagging during crane handling, the beam must be set down on the ground immediately. No erector may step onto a beam with a compromised fall arrest system. The damaged component is replaced and inspected on the ground before a new lifting attempt is made.
How should one respond when the actual fall clearance measured on site is less than expected?
If the height beneath the flange is insufficient to accommodate the deployment of a conventional energy-absorbing lanyard, walking along the beam must be stopped. The site manager must review the risk assessment and consult an occupational safety specialist. The use of fast-acting retractable fall arresters or a MEWP must be approved in writing.
Who is authorised to sign off on an equivalent protective measure under the OTConst?
In accordance with Swiss regulations, whenever it is impossible to install edge protection or a net, the equivalent personal protective measure must be defined in writing by consulting a qualified occupational safety specialist (MSST safety engineer or recognised expert). This written validation specifies the approved equipment and procedures for moving on the structure.
Can one anchor directly to a 20 cm beam using a twin-tail lanyard if the lifeline is missing?
Walking continuously using a twin lanyard by clamping or choking the flange on a 20 cm beam without a pre-installed lifeline is extremely dangerous and results in high fall factors. Without a lifeline installed on the ground or a rigid overhead anchor point, this working method is prohibited unless explicitly specified in the written procedure drawn up with the safety specialist.
Texts and standards cited
- OTConst art. 29other fall protection measures and written referral to a specialist
- LAAgeneral accident prevention rules and employer obligations
