🧱 CFC 215Composite facades: glass, metal and fixingsChapter 2 of 10 in the section

Adjustable fixings: compensating for structural work in all three directions

In steel construction and composite facades, the precision of metal inevitably comes up against concrete deviations. This chapter details how adjustable fixings work along the three geometric axes, the tightening and final locking procedures, as well as the methodology to apply when substrate deviations exceed the planned compensation capacities.

Key takeaways

  • Three-dimensional adjustment absorbs structural work deviations without distorting the steel framework.
  • Serrated shims and slotted holes ensure positioning prior to final mechanical locking.
  • Exhausting the entire adjustment travel invalidates the transfer of eccentric loads.
  • Exceeding theoretical tolerances requires installation to be halted and a report made to the site management.

Operation and adjustment travel along the three axes

The steel load-bearing structure of a composite facade imposes strict geometry to accommodate glazing and weatherproofing elements. The reinforced concrete shear wall or slab exhibits significantly wider execution tolerances. To absorb these offsets without introducing parasitic stresses into the transoms and mullions, metal anchorages incorporate independent adjustment mechanisms along the three axes: X (transverse), Y (vertical) and Z (depth).

Theoretical compensation capacities per geometric axis
Adjustment axisCompensation mechanismTypical travel (mm)Effect of exceeding travel
X (Transverse)Horizontal slotted holes / Sliding sleeves± 20 to ± 30Centre-to-centre distance error and anchor stud shear
Y (Vertical)Vertical slotted holes with jacking screw± 25 to ± 40Misalignment of glazing and settlement
Z (Depth)Levelling screw, shim pack or telescopic bracket± 30 to ± 50Increase in bending moment within the anchorage

Depth adjustment (Z-axis) proves particularly critical for correcting slab out-of-plumbness. A thickness variation in the thermal insulation build-up or a tilt in the concrete shear wall directly alters the fixing lever arm. During design, the available travel must incorporate the maximum deviation tolerated by standard SIA 262 while guaranteeing a minimum contact area under the baseplates.

Adjustment travel
Maximum range of linear displacement permitted for a fastening element in a given direction, allowing the framework to be aligned perfectly without altering the nominal load-bearing capacity of the anchoring system.

Out-of-plumb compensation combines the action of the Y-axis and the Z-axis. When the structural work deviates from the theoretical vertical, the installation crew rectifies the orientation of the anchor brackets using adjustment screws or metal bevelled washers. Laser alignment guides the exact positioning of the steel structure before the glazed units are loaded.

Mechanical locking, substrate deviations and acceptance limits

Initial positioning of a facade structural element is carried out under partial dead load. Once the volumetric adjustment has been approved by the gang leader, the connection must be locked irreversibly to resist permanent loads, wind actions and thermal expansion. Locking relies on surface friction and positive mechanical engagement.

  1. Alignment and temporary shimmingAdjustment of the bracket to the required height and depth using jacking screws or precision levelling shims.
  2. Insertion of anti-slip componentsInstallation of spherical seating washers, serrated plates or spring washers preventing loosening under dynamic stresses.
  3. Tightening to the specified torqueTightening of high-strength bolting using a calibrated torque wrench in accordance with the execution drawings and specifications.
  4. Final lockingExecution of a stop fillet weld on the adjustable component or locking by a locknut secured with anaerobic threadlocking resin.

When the concrete deviation exceeds the theoretical capacity of the anchor (for instance, a shear wall deviation greater than 50 mm), the substrate is deemed non-compliant. The steelwork installer stops fitting the bay concerned. In accordance with the general rule of the contract for work set out in art. 365 CO, the contractor must promptly notify the client of any defects in the ground or substrate to avoid bearing the consequences.

In this scenario, the engineering solution requires the approval of a custom adaptation piece (welded counter-plate, structural bracket extension) or remedial work on the substrate by the mason. Any modification is subject to an addendum approved by the site management before installation work resumes.

Managing cumulative out-of-plumbness and structural load transfer

On load-bearing frameworks of metal curtain walls, out-of-plumb reinforced concrete is not limited to a localised offset from one slab to the next. When the shear wall or floor edge exhibits a continuous inward or outward tilt across multiple consecutive storeys, geometric stacking transfers major parasitic stresses into the metal brackets. The steel or aluminium primary framework must imperatively maintain its theoretical installation plane, determined by the benchmark level and surveyor axes, without ever following the belly or tilt of the rough substrate.

Accommodating out-of-plumbness with adjustable anchor brackets directly modifies the fixing lever arm. The more the shimming thickness or bracket projection increases to reach the theoretical alignment of a receding shear wall, the greater the bending moment applied to the anchor bolt or cast-in channel. Conversely, overhanging concrete reduces the space available to accommodate edge clearance, the perimeter thermal insulation system and expansion splices.

Geometric and structural impact of out-of-plumbness on facade brackets
Structural work configurationImpact on the metal bracketDirect structural consequenceWorkshop or construction site corrective action
Concrete receding inwards (+15 to +25 mm)Extension of threaded rod or bracket projectionIncrease in overturning moment on the anchorageTightening torque verification and enlarged baseplate
Concrete projecting outwards (-15 to -25 mm)Bracket compressed against end of slot or rebate stopRisk of direct contact with the slab edge (thermal bridge)Mechanical trimming of bracket or offset upstand on drawing
Helical twist of the shear wall over its heightAngular misalignment between the mullion plane and bearing seatShear force combined with eccentric tensionInterposition of machined aluminium alloy taper washers
Deviation exceeding effective travel (> 30 mm)Total exhaustion of adjustment slots and threadsFixing outside the engineer's domain of validityRefusal to install and request for structural remedial work

Angular compensation cannot be achieved by forcing the frame profiles, at the risk of inducing residual stresses that cause thermal breakage of insulated glazing units or pinching of EPDM weather seals. Articulated joints, taper washers and spherical washers ensure that the nut bears perfectly flat against the bracket, even when the structural work bearing surface exhibits a pronounced transverse out-of-level.

Total clearance exhaustion: contingency measures and technical refusal

When the three-dimensional survey reveals that the structural work tolerances exceed the adaptation capacity of the brackets and plates, the installation crew reaches an operational breaking point. Stacking loose shims haphazardly, bending a bracket with a blowtorch or slotting a hole with an angle grinder constitutes a severe alteration of the fixing product that voids certified mechanical warranties.

As soon as an ironmongery fitting reaches its mechanical adjustment stop, installation work in the affected zone is suspended. The contractor applies the contractual defect notification procedures provided for under the general framework of construction contracts, without compromising their own liability through makeshift workarounds on the construction site.

  • Use of custom-welded steel adaptation counter-plates, formally dimensioned and approved by the facade civil engineering firm.
  • Restoring surface flatness by planning or scabbing reinforced concrete, performed by the structural work contractor, strictly subject to maintaining minimum rebar cover.
  • Replacing mechanical fixings with interposition profiles chemically anchored to the inner faces of slabs rather than at the congested slab edge.
  • Outright refusal of the installation face when the setback requires an inadmissible reduction of the fire-rated insulation build-up or ventilated cavity.

The contractor promptly notifies the site management of any unforeseen circumstances or substrate defects that compromise the orderly execution or solidity of the assigned work.

Norme SIA 118

Procedure to follow when installation tolerances are exhausted

On a stick-system or steel-framed curtain wall construction site, three-dimensional fixings serve to compensate for normal execution tolerances in reinforced concrete, not to correct major structural defects. When the anchor bracket reaches its mechanical stop in any of the three directions, the metal facade can no longer absorb the defect. Under no circumstances must the installer force the framework, enlarge a slotted hole on site without engineering approval or remove a distribution shim: forcing a steel section to compensate for an out-of-plumb alignment induces parasitic stresses and compromises watertightness or proper glazing performance.

As soon as the geometric survey indicates that remaining adjustment travel is zero or insufficient to guarantee the specified plumb, the crew halts installation of the bay concerned. The contractor applies the general notification procedure for defective substrates covered in the CFC 201 trade, immediately forwarding a dimensional inspection report to the site management.

  • Execution of a joint survey using a theodolite or laser scanner to record concrete slab positioning errors.
  • Engineering a custom adaptation plate in the workshop, recalculated for the actual lever arm and resisting wind and dead loads.
  • Localised trimming of the slab edge by the masonry contractor if the concrete projects beyond the theoretical envelope.
  • Final tightening of adjustable fixings only after approval of the complete bay geometry, using serrated washers or taper locking shims torqued to the specified value.

Pursuant to art. 365 para. 3 CO, if the material supplied by the client or the ground designated by them is found to be defective, or if any other circumstance compromises the orderly or timely execution of the work, the contractor must inform the client. Installation resumes only after written agreement on the selected technical alternative.

Frequently asked questions

Can several flat metal shims be stacked to compensate for excessive slab setback?

Stacking loose, smooth shims is prohibited beyond the thickness validated by the structural calculation note. This stacking creates an unplanned lever arm on the anchor bolt or cast-in channel, increasing the bending stress in the threaded rod. If the structural work setback exceeds the bracket travel, a welded counter-plate or extended bracket substantiated by the structural steel engineer must be inserted.

How is an adjustable fixing locked securely after precise facade alignment?

Position retention is achieved by friction or positive mechanical engagement. Brackets utilise serrated locking washers, toothed locking plates or locknuts tightened to the specified torque using a torque wrench. In zones exposed to severe thermal variations or wind-induced vibrations, a locking fillet weld or an approved threadlocking resin secures the final position.

What structural concrete out-of-plumb tolerance warrants stopping work?

Halting installation is mandatory as soon as the actual deviation exceeds the nominal travel of the bracket, typically plus or minus twenty millimetres. If the shear wall exhibits an out-of-plumbness exceeding standard tolerances and uses up the entire clearance from the very first storey, installation of the steel structure cannot continue without risking misalignment of the glazing or head profiles.

Who bears the machining cost of adaptation components when structural work is out of tolerance?

The supply of special brackets or extension plates constitutes extra work caused by the non-compliance of the preceding trade's work. Costs for engineering, workshop fabrication and delayed installation are subject to an addendum submitted to the site management, as the steelwork contractor is not required to bear the costs of rectifying a substrate that fails to conform to the cast-in penetration and rebate plans.

Texts and standards cited

  • CO art. 365materials and ground: the contractor is liable for the sound quality of materials supplied by them; if materials supplied by the client or the ground designated by them are found to be defective, or if any other circumstance compromises the orderly or timely execution of the work, the contractor must promptly inform the client, under penalty of bearing the consequences (para. 3).