🧱 CFC 215Corrosion protection and fire resistanceChapter 2 of 10 in the section

Surface preparation: shot blasting, degree of care, and roughness achieved

After this chapter, you will be able to determine the required degree of care for load-bearing steel structures, measure the surface roughness achieved, and strictly manage the critical time window for applying the anti-corrosion primer to prevent substrate recontamination.

Key takeaways

  • Degree of care Sa 2 ½ removes mill scale and guarantees the adhesion of paint systems.
  • Medium-profile roughness (Ra 6 to 10 µm) ensures mechanical keying of coatings.
  • The first primer coat must strictly be applied before any flash re-oxidation of the substrate.
  • No paint coat can compensate for rushed or non-compliant surface preparation.

Degree of preparation and roughness of structural steel

More than 80% of the durability of an anti-corrosion system depends on the quality of the surface treatment. On structural steel, the presence of mill scale, rust, grease, or hygroscopic salts prevents direct primer adhesion. Abrasive blast cleaning (shot blasting) remains the most effective method for exposing bare metal and creating the required anchor profile.

Degrees of preparation by blast cleaning are classified from Sa 1 to Sa 3. For steel construction exposed to corrosivity categories C3 to C5, degree Sa 2 ½ (very thorough blast cleaning) is the standard minimum specification.

ISO 8501-1 et ISO 12944

At degree Sa 2 ½, the surface must be free from oil, grease, dirt, and almost all mill scale, rust, and previous coatings. Only slight traces in the form of spots or stripes may remain. For areas subjected to extreme stress or immersion, degree Sa 3 (white metal blast cleaning) is required, eliminating absolutely all shadows or traces.

Surface profile (Roughness)
Topography created by the impact of steel shot. It is characterised by the peak-to-valley height (Rz) or mean roughness (Ra). Standard ISO 8503-1 defines visual-tactile comparators (Fine, Medium, Coarse profiles).
Roughness requirements according to anti-corrosion primer type
Primer typeRoughness class (ISO 8503-1)Roughness Rz (µm)Roughness Ra (µm)
Alkyds / Light zinc silicatesFine (F)25 - 403.2 - 6.3
High-build epoxies / PolyurethanesMedium (M)40 - 756.3 - 12.5
Thick passivations / Thermal sprayingCoarse (C)> 75> 12.5

Primer application conditions and recoat windows

Once the steel is shot-blasted to the required degree of care, the bare metal is extremely reactive to ambient humidity. The phenomenon of flash oxidation (flash rusting) can appear within tens of minutes under adverse hygrometric conditions. It is therefore vital to strictly govern the time interval between blast cleaning and applying the first paint coat.

  1. Dust removal and cleanliness inspectionRemove residual abrasive and dust by industrial vacuum cleaning. Check dust level according to ISO 8502-3 (pressure-sensitive adhesive tape test, cleanliness class ≤ 2).
  2. Verification of atmospheric conditionsMeasure steel temperature, which must be at least 3 °C above the dew point. Relative air humidity must be below 85%.
  3. Application of shop primerApply the first coat within the specified time window. In a controlled workshop, this window generally does not exceed 4 hours. On the construction site, it must be reduced to less than 2 hours.

Regarding occupational health and safety at the workstation, sandblasting and shot-blasting operations generate respirable fine dust and high-intensity noise. In accordance with the Ordinance on Health Protection and the Ordinance on Machine Safety, shot-blasting booths must be equipped with a filtering extraction system that maintains ambient air quality and protects personnel via sealed equipment with clean air supply.

Degrees of care according to ISO 12944 and preparation inspection

Surface preparation by shot blasting or sandblasting dictates the mechanical adhesion and durability of the anti-corrosion system on structural steel. No paint, however high-performing, can compensate for a substrate presenting residual mill scale, unremoved rust, or soluble salt contamination. Surface condition assessment relies on the criteria of standard ISO 12944 and ISO 8501-1.

Degrees of surface preparation by shot blasting and fields of application
Degree (ISO 8501-1)DesignationVisual appearance obtainedUse in steel construction
Sa 1Light blast cleaningFree from visible cross-hatching and dirt. Tenacious mill scale and rust remain.Not permitted for structural anti-corrosion paints.
Sa 2Thorough blast cleaningAlmost free from mill scale and rust. Slight incrustations persist.Temporary shop primer or sheltered structures in C1/C2.
Sa 2 ½Very thorough blast cleaningVery slight traces in the form of spots or stripes. Metallic grey surface.Minimum standard for steel frameworks and mixed façades.
Sa 3Blast cleaning to visually clean steelMetal completely bare, uniform metallic colour without any shadows.Very aggressive environments (C5/CX) or thermal zinc spraying.

On the construction site or in the factory, the foreman checks the degree of care by direct visual comparison with the ISO surface profile comparator under suitable lighting. Prior to shot blasting, any grease, oil, or machining salts must be removed by solvent degreasing or high-pressure washing, as the shot embeds these contaminants into the steel's porosity.

Roughness profile and primer application window

Shot blasting creates an anchor profile (roughness) characterised by its peak-to-valley height (Rz or Ry). Insufficient roughness prevents mechanical keying of the epoxy or zinc silicate primer, causing a risk of delamination under thermal or mechanical façade stress.

Surface roughness (Rz)
Average of profile depths measured on the blast-cleaned surface. For anti-corrosion protection by painting of steel frameworks, the target roughness is generally within the "Medium" profile (Rz between 40 and 75 µm).
  1. Environmental monitoringMeasure relative humidity (max 85%) and verify that the steel temperature is at least 3 °C above the dew point.
  2. Roughness and dust inspectionMeasure the Rz profile using a stylus surface roughness tester or replica tape. Carry out the adhesive tape test (ISO 8502-3) to ensure the absence of shot-blasting dust.
  3. First coat application (time window)Apply the anti-corrosion primer immediately after dust removal. In a controlled workshop, the maximum time window is 4 hours. On a construction site, this window often drops to less than 2 hours.

Managing blast-cleaning non-conformities and surface repairs

In steel frameworks and mixed façades, a surface preparation defect identified after shot blasting prohibits any entry into the paint booth. When the required degree of care (Sa 2 ½ or Sa 3 according to standard ISO 12944) is not reached, or if flash oxidation appears due to exceeding the primer application window, holding coats cannot compensate for the lack of adhesion. The workshop must halt the painting line and correct the surface prior to spray application.

  1. Findings of flash oxidation or contaminationIf the maximum time window between shot blasting and primer application (generally 4 hours to 6 hours depending on ambient relative humidity) is exceeded, the formation of a fresh rust film or the deposition of oily dust invalidates the substrate. Visual inspection and the tape test confirm the contamination level.
  2. Corrective treatment by sweep blastingTo remove flash rust without destroying the existing anchor profile, a light shot blasting known as a "sweep blast" is executed using fine abrasive at reduced pressure. This operation restores the initial degree of care and reactivates the medium to high roughness required by standard EN ISO 8503.
  3. Localised repairs and joint areasOn weld beads produced on the construction site or during touch-ups of bolted connections, automatic shot blasting is not practicable. Power tool chipping or abrasive disc grinding (degree St 3) is then implemented, combined with thorough solvent degreasing prior to applying the touch-up primer.
  4. Validation of thermo-hygrometric conditionsBefore reapplying the first coat, the foreman checks that the steel temperature is 3 °C above the dew point and that the relative air humidity remains below 85%. These measurements are recorded on the workshop's self-inspection log sheet.

Execution disputes regarding the degree of cleanliness are resolved by direct comparison with ISO 8501-1 standard photographs in the presence of the quality inspector. If roughness is insufficient following the use of worn or improperly graded shot, only a new pass through an automatic shot-blasting machine charged with angular abrasive can restore the anchor profile required by the project specifications.

Frequently asked questions

How should one react if flash rust appears before primer application?

The appearance of flash oxidation indicates that the allowable time window was exceeded or that workshop humidity was too high. Primer application is immediately blocked. The surface must undergo a dry sweep blast or mechanical preparation to regain the required degree of care Sa 2 ½ before any painting. Ambient conditions must be brought back below 85% relative humidity.

What is the difference between degree of care Sa 2 ½ and degree Sa 3?

Degree Sa 2 ½ (very thorough blast cleaning) only tolerates slight traces of shadowing or discolouration on the steel. Degree Sa 3 (blast cleaning to visually clean steel) requires a surface totally free from any residue, mill scale, rust, or paint, displaying a completely uniform metallic colour. Sa 3 is reserved for extremely aggressive exposures or immersion service.

Can shot blasting be replaced by power tool sanding on large structures?

No. Sanding with an angle grinder does not produce the angular roughness (anchor profile) necessary for the retention of anti-corrosion paint systems thicker than 160 micrometres. Sanding polishes the metal and classifies it at best as St 3, which is reserved for touching up small areas or construction site welds, but is not permitted for the main structural frame.

What is the maximum time window between blast cleaning and the first coat of paint?

The standard window is 4 hours maximum in a controlled workshop atmosphere, and must be reduced to less than 2 hours in high ambient humidity or aggressive atmospheres. If the steel temperature approaches within 3 °C of the dew point, pinpoint rusting is almost immediate and the primer must not be applied.

Texts and standards cited

  • ISO 12944Paints and varnishes - Corrosion protection of steel structures by protective paint systems
  • ISO 8501-1Visual assessment of surface cleanliness - Preparation grades of steel substrates
  • EN ISO 8503Surface roughness characteristics of blast-cleaned steel substrates