🧱 CFC 215Connections: bolting, welding and inspectionChapter 9 of 10 in the section

Shear studs: interconnecting the steel beam and concrete slab

This chapter details the installation of shear studs welded by capacitor discharge or drawn arc onto steel beams. You will learn to prepare the top flange according to standard SIA 263, adjust welding parameters, and perform the 30° bend test to ensure monolithic composite steel-concrete floor action.

Key takeaways

  • Absolute cleanliness of the top flange determines the quality of stud fusion.
  • Capacitor discharge or drawn arc welding requires rigorous shielding gas or ceramic ferrules.
  • Standard SIA 263 defines the design and ductility requirements for shear connectors.
  • Mechanical bend testing confirms HAZ integrity without cracking of the weld.

Preparation of the steel flange and stud welding process

In a composite steel-concrete floor, the transfer of longitudinal shear relies entirely on the bond quality of the shear studs. The top flange of the steel beam must provide a thoroughly prepared, bare surface. The presence of mill scale, rust, paint, cutting oil, or moisture disrupts the electrical current and creates gas pores or lack of penetration. Before any welding operation, grinding the impact area to bare metal is mandatory to expose the steel and ensure minimal electrical impedance.

The standard fastening method is drawn arc stud welding with a ceramic ferrule or gas shielding. The equipment strikes an electrical pilot arc that simultaneously melts the base of the stud and the base metal of the flange. The welding gun then plunges the stud into the weld pool, fusing both parts. The ceramic ferrule contains the molten metal pool, shields the arc from atmospheric disturbances, and forms a uniform weld collar around the base of the connector.

  1. Substrate preparationCleaning the flange by grinding at the exact stud locations until a bright metallic finish is achieved.
  2. Ferrule placementPositioning a dry ceramic ferrule on the steel surface to contain the molten metal.
  3. Automated weldingTriggering the gun: arc ignition, weld pool generation, and automatic plunge of the stud into the flange.
  4. Deburring and cleaningSystematic breaking away of the ceramic ferrule after cooling and removal of slag around the collar.

Assembly quality control and bend testing on the construction site

Visual inspection forms the first verification stage on the construction site. A complete, uniform weld collar extending 360° around the stud shank indicates adequate welding energy and correct plunge depth. If the weld collar is incomplete or exhibits undercut grooves, the joint is suspect and must undergo further non-destructive or destructive testing.

Bend testing
A site test consisting of mechanically deflecting the welded stud to an angle of 30° using a pipe lever to verify ductility and the absence of defects at the root of the weld.
Summary of stud welding defects and corrective actions
Defect observedProbable causeCorrective action to apply
Incomplete collar on one sideGun not held perpendicular or contaminated flangeGrind off the stud, clean the flange, and re-weld adjacent
Brittle failure during bend testIncorrect current settings or presence of moistureAdjust the power source and check that ferrules are dry
Excessive spatter and flat collarWelding energy too highReduce the arc time or current output of the power unit

In accordance with the directives of the ordinance on the safety of workers during construction work, erection crews must ensure work area stability and wear appropriate PPE during grinding and bend testing. In the event of repeated non-conformity within a batch, the entire series must be tested under the supervision of the site manager.

Preparation of the steel flange and discharge welding process

In composite steel-concrete structures, the shear stud transfers shear forces at the interface between the steel beam and the reinforced concrete slab. To ensure this composite action and prevent any longitudinal slip, the quality of the welded connection to the top flange of the steel framework is decisive. The success of this assembly relies on rigorous substrate preparation and strict parameter setting of the welding process.

The discharge welding process with a ceramic ferrule (drawn arc stud welding of fasteners) enables high installation rates directly on the construction site or in the steel fabrication shop. The welding equipment applies calibrated pressure, strikes an electrical arc to create a weld pool on the flange and at the base of the stud, and then plunges the connector into the liquid metal. The ceramic ferrule contains the molten pool, protects the arc from atmospheric disturbances, and shapes the peripheral weld collar.

Execution parameters and stud welding verifications
Process stageOn-site inspection criterionCorrective action in case of deviations
Steel substrate preparationClamping and grinding the flange to bare metal (free of water, paint, and mill scale)Grinding with an abrasive disc and drying with a blowtorch
Ferrule positioningCeramic ferrule dry, intact, and centred on the stud axisImmediate replacement of damp or chipped ferrules
Welding gun adjustmentArc time and current set according to stud diameter (e.g. SD 19 mm)Adjusting the power source and checking the ferrule seating
Fillet weld (collar) inspectionUniform 360° weld collar at the base of the connectorGrinding and repair using manual metal arc (MMA) welding if insufficient filler

Conformity checks according to standard SIA 263 and bend testing

Validation of the composite connection is performed via systematic visual inspections supplemented by destructive or non-destructive mechanical tests on the construction site. Standard SIA 263 specifies the execution and structural design requirements applicable to steel structures and their connecting devices.

The bend test consists of striking or bending the stud using a pipe lever or sledgehammer until reaching the prescribed angle of 30 degrees from its original vertical axis. The test is successful if no cracks or fractures appear in the weld zone or in the heat-affected zone on the flange. In the case of scheduled non-destructive testing, the stud deflected during the test remains in place and is embedded in the slab concrete without being restraightened.

Weld collar (flash)
A continuous ring of molten metal formed at the base of the stud as it is plunged into the ceramic ferrule. Its continuity around the entire circumference guarantees the absence of lack of fusion and provides the shear resistance required by the composite beam design.
  1. Full visual inspectionVisually inspect 100% of welded studs after removing the ceramic ferrules by chipping. Check the stud height after welding and verify the formation of a full fusion collar around the entire base.
  2. Batch selection for the bend testDefine the testing sample size according to the quality inspection plan. Apply the 30° bend test to the first studs installed at the start of each work shift or whenever there is a change in the steel batch.
  3. Execution of cold bendingSlide the extension pipe over the connector shank and apply progressive force until bending the stud 30° along the longitudinal axis of the steel beam.
  4. Examination of the fused zone and recordingInspect the root of the weld for microcracks. Record the batch results in the steel fabricator's self-inspection report.

Prior to concrete placement by the structural work contractor, the steel construction site foreman carries out sweeping and final cleaning of the top flanges. Broken ceramic ferrules, grinding spatter, and metallic debris must be completely cleared away to prevent honeycombing or contamination of the reinforced concrete cover.

Management of non-conformities and remediation of flanges

During the discharge welding of shear studs for composite steel-concrete floors, installation defects or failures during bend tests require an immediate remediation procedure to ensure the transfer of shear forces specified by standard SIA 263. A defective weld or a sheared-off stud must never be left as is or simply covered by the slab concrete.

  1. Removal of the non-compliant elementCut the defective stud flush with the flange using an angle grinder fitted with a suitable cut-off disc. Remove surplus filler metal and weld spatter using light grinding.
  2. Preparation of the replacement substrateClean the steel flange by wire brushing or grinding to return the surface to bare metal, free of oil, mill scale, rust, or paint. Cleanliness and flange condition are essential for correct arc ignition.
  3. Re-installation and welding of the new studPosition the new shear stud at a minimum distance of three times its diameter from the failed anchor location. Use a new ceramic ferrule and carry out discharge welding after adjusting current and arc time settings.
  4. Visual and mechanical acceptance inspectionCheck the continuity of the weld collar through 360 degrees around the stud. Perform a 15-degree bend test on the replacement stud using a pipe lever to confirm the ductile performance of the connection.

If discharge welding proves impossible on the construction site due to restricted access or electrical supply constraints, replacement with a manual metal arc-welded stud or a certified mechanical anchor system must be explicitly approved by the timber-metal engineer or the civil engineer in charge of the project.

Frequently asked questions

What should be done if a stud snaps cleanly during the bend test?

A clean fracture in the weld zone indicates quench embrittlement or lack of fusion. The fastening area on the flange must be ground down to sound base metal, verified to be free of moisture or grease, and a new stud welded immediately adjacent, systematically using a new ceramic ferrule. The replacement stud is then subjected to a new bend test.

Can shear studs be welded through profiled steel decking mounted on the beam?

Yes, through-deck welding is common in composite construction, but it requires specific studs, higher welding power, and strict cleanliness between the deck and flange. The profiled sheet must be pressed tightly against the beam flange without any gap to ensure electrical circuit continuity and weld pool quality.

What is the acceptable tolerance for stud alignment on the flange?

According to the requirements of standard SIA 263, the geometric positioning of shear studs must respect a specific centre-to-centre spacing to avoid any clash with the concrete slab reinforcement. A deviation of a few millimetres is tolerated provided that the minimum concrete cover around the stud head and the edge distances on the steel flange continue to comply with the execution drawing.

Why is the cleanliness of the steel flange so critical before welding?

The presence of oil, water, paint, or mill scale on the flange disrupts the electric arc during the discharge process. This causes spatter, porosity, or incomplete collar fusion. A contaminated surface reduces the mechanical strength of the connection and inevitably leads to failure of the bend test required for composite slabs.

Texts and standards cited

  • SIA 263Steel structures - Design and execution of composite structures and joints