🧱 CFC 215Erection and lifting of a steel structureChapter 7 of 10 in the section

Mobile crane: ground bearing capacity, outrigger pad spreading and excavation proximity

The overturning of a mobile crane almost always results from ground failure or incorrect outrigger pad spreading. This chapter provides site foremen and site managers with practical methods for calculating the required pad spreading area, positioning outrigger pads relative to open excavations and drawing up a lifting plan compliant with safety requirements on steel structure construction sites.

Key takeaways

  • The maximum outrigger pad load determines the minimum surface area of the load spreaders on the ground.
  • Ground bearing capacity must be validated before setting up the mobile crane.
  • The distance to an open excavation depends on its depth and shoring.
  • A written lifting plan remains mandatory to regulate the handling of heavy components.

Determining ground bearing capacity and sizing outrigger pad spreading area

The erection of a steel structure requires the use of mobile cranes that support very high concentrated loads. An overturning crane always stems from a ground failure beneath one of the outrigger pads. Before setting up the machine, the site manager and the site foreman must obtain the permissible ground bearing capacity, expressed in kilonewtons per square metre, from the geotechnical engineer or the site management.

A crane's outriggers transfer the entire weight of the machine and the suspended load onto a small surface area. The original steel outrigger pads supplied with the crane are rarely sufficient on soft ground, backfill or unstabilised natural ground. To prevent punching shear, it is essential to place load spreaders (crossed hardwood timber mats, steel plates or high-density polyethylene pads) beneath each outrigger pad.

Minimum outrigger pad spreading area
Required load spreading surface area beneath an outrigger pad to limit the pressure exerted on the ground to a value below its permissible bearing capacity.

Calculating the outrigger pad spreading area is based on a simple formula: the maximum outrigger pad load (provided by the crane operator or the crane load chart) divided by the permissible ground bearing capacity. The team leader must ensure on site that the pad spreading is perfectly horizontal, centred beneath the jack cylinder and laid out on a surface cleared of any unstable rocks or blocks.

Indicative bearing capacity values and theoretical pad spreading areas for a 300 kN outrigger pad load
Ground typeEstimated permissible bearing capacityRequired load spreading area
Recent uncompacted fill100 kN/m²3.00 m² (e.g. 1.75 x 1.75 m)
Firm clay or silty soil150 kN/m²2.00 m² (e.g. 1.45 x 1.45 m)
Compacted gravel / Pit-run material250 kN/m²1.20 m² (e.g. 1.10 x 1.10 m)
Blinding concrete / Bedrock500 kN/m²0.60 m² (e.g. 0.80 x 0.80 m)

Observing safe distances to excavations and formalising the written lifting plan

Setting up a mobile crane near an open excavation or a trench presents a major risk of slope failure. The pressure exerted by the outrigger pads creates an angled thrust in the ground that can cause the excavation face to collapse. Swiss construction work regulations set strict rules regarding the positioning of machinery near these zones.

For an unbacked excavation, the general rule requires keeping outrigger pads outside the failure plane of the soil. In soft ground, the edge of the load spreader must be located at a horizontal distance equal to at least twice the depth of the excavation. If the slope is secured or if a retaining wall is in place, the stability verification must be confirmed by the geotechnical engineer before positioning the crane.

Before work begins, the employer ensures that there is a plan detailing the necessary measures for the work carried out on the construction site, including the organisation of first aid; this plan is drawn up in writing or in a form that allows proof by text.

art. 4 OTConst

In accordance with art. 4 OTConst, complex erection operations involving heavy loads or large radii must be covered by a written lifting plan. This key document compiles the weight of the steel components, boom lengths, working radius, slinging method and the exact location of outrigger pad spreading relative to existing infrastructure and excavations.

  1. Load data verificationIdentify the maximum weight of the load unit to be lifted, including the weight of the hook blocks, the hook and the steel slings.
  2. Site layout validationCheck the set-back distance from excavation edges on the ground and verify that no underground duct or pipe passes beneath the pad spreading zone.
  3. Acceptance of outrigger pad spreadingInspect the assembly of the load spreaders, the centring of the outrigger jacks and the levelling of the crane chassis using a spirit level.
  4. Erection crew briefingCommunicate the lifting plan to the crane operator, the appointed person / lift supervisor and the erectors before the first manoeuvre.

Safety distance from excavations and calculating outrigger pad set-back

A mobile crane overturning almost always starts with ground failure beneath an outrigger pad. The presence of an open excavation, a pipeline trench or an unstabilised embankment profoundly alters the stress distribution in the ground. During the lifting of structural steelwork or composite façade elements, the pressure exerted beneath the pads is not applied solely vertically, but spreads along a load cone into the rock or soft ground mass.

To avoid slope failure or punching shear at the edge of the excavation, the load influence angle must be strictly respected. In accordance with the Construction Work Ordinance, the distance between the bottom edge of the outrigger pad (or the edge of the load spreader) and the crest of the slope must comply with a strict geometric rule depending on the type of ground and the depth of the excavation.

Minimum outrigger pad spreading distances at the edge of an excavation or embankment
Ground type / StructureExcavation slope / ShoringMinimum safety distance ($d$)
Soft soils, uncompacted fillsUnbacked slope$d = 2 \times$ excavation depth ($h$)
Cohesive soils (dense clay, marl)Stabilised slope$d = 1.5 \times$ excavation depth ($h$)
Sound rock or sheet-piled wallRetaining wall designed for heavy loadsAs verified by the specialist engineer

If the construction site requires outrigger pad spreading at a distance smaller than these theoretical values, art. 76 OTConst requires a stability verification of the slopes by a specialist engineer or geotechnical engineer. Without this formal validation, setting up the mobile crane within the immediate perimeter of the excavation is prohibited.

Implementing the lifting plan and inspecting outrigger pad spreading on the construction site

The written lifting plan is the operational document that establishes the working conditions for the crane operator and the steel erectors. Prepared during work planning pursuant to the Construction Work Ordinance, this plan compiles the mass of the steel loads, the maximum radius, the boom and jib configuration, as well as the permissible ground bearing capacity determined at the crane outrigger location.

  1. Visual survey and subbase inspectionCheck for the absence of cavities, unprotected buried services or recent excavations beneath the pad spreading area. Inspect the compaction of temporary crane platforms.
  2. Verification of lifting plan complianceEnsure that the mass of the steel components to be erected (beams, columns, trusses) strictly matches the packing lists and the written installation plan.
  3. Positioning load spreadersExtend outriggers to 100% of their manufacturer stroke. Position spreader plates sized according to the ground bearing capacity and check the crane's spirit level.
  4. Unloaded and trial load lifting testPerform a test lift at a low height to observe ground behaviour beneath each outrigger pad before slewing over structures or deploying assembly teams.

When erecting composite structures or heavy façade elements, site foremen and team leaders ensure compliance with the general duty of prevention laid down in LAA, by ensuring that all personnel working within the crane's operating radius wear the prescribed personal protective equipment and comply with cordoned-off safety perimeters.

Managing ground anomalies and site shutdown during outrigger pad spreading

The overturning of a mobile crane almost systematically stems from a defective base. If, when setting up the outriggers, differential settlement appears, if an outrigger pad sinks its spreader into the ground or if water ingress alters ground consistency near an excavation, the erector must immediately stop the operation. Continuing the lift on an unstable base directly endangers personnel and the steel structure being assembled. In accordance with the Construction Work Ordinance, ground stability and excavation edge protection must be ensured before any loading.

As soon as the stoppage is established, the site foreman alerts the site manager and has the ground bearing capacity verified by the site geotechnical engineer. The outrigger pad spreading area must be reconfigured using criss-crossed timber mats, timbers or steel plates sized to the recalculated reaction force. If damage or risk of cave-in threatens an open excavation, additional slope shoring or trench sheeting pursuant to OTConst becomes mandatory before any resumption of crane operations.

  • Ground remediation: Removal of softened material and placement of a layer of compacted crushed gravel if bearing capacity is insufficient.
  • Enlarging load spreaders: Formal resizing of the outrigger pad surface area to lower the pressure transmitted to the ground below the permissible limit.
  • Updating the lifting plan: Written validation of the new outrigger pad positions and maximum permissible loads by the safety officer.

Any modification of bearing conditions on the construction site requires a complete visual inspection of the crane chassis, outrigger jacks and the machine's level using an electronic spirit level. The resumption of lifting may only be ordered once the written lifting plan incorporates the modified ground parameters. In the event of a serious failure to adhere to the recognised rules of the trade knowingly endangering the lives of workers, criminal liability applies to the site manager and the erector under CP.

Frequently asked questions

What should be done if the actual ground bearing capacity is lower than the data in the installation plan?

The set-up of the mobile crane must be stopped. The outrigger pad spreading area must be resized immediately by increasing the size of the spreader plates or timber mats. The site manager transmits the new values to the engineering office or the geotechnical engineer to formally validate the revised permissible pressure before authorising any lifting of structural steelwork elements.

What minimum distance must be maintained between a crane outrigger pad and an unbacked excavation?

The practical rule requires a set-back distance at least equal to the depth of the excavation relative to the toe of the slope for soft ground, or half a metre beyond the upper edge for stable rock. If this distance cannot be observed on the construction site, the civil engineer must provide written verification of slope stability.

Is a written lifting plan mandatory for a short-duration mobile crane operation?

Yes, a written lifting plan is required whenever lifting involves specific risks, particularly near excavations, beneath overhead power lines or when positioning heavy steel parts. It specifies crane capacities, maximum radius, outrigger pad spreading and the organisation of exclusion zones beneath the load.

Can timber mats be stacked beneath an outrigger pad to compensate for a steep ground slope?

No, unstable stacked packing is strictly prohibited. Levelling must be achieved using crossed, perfectly tight-fitting and non-slip packing laid on ground that has been stripped and levelled beforehand. The crane must be set up perfectly level on its outriggers in accordance with the manufacturer's instructions and the machine manual.

Texts and standards cited

  • OTConstPreparation of excavations, shafts and earthworks to prevent falls and cave-ins.
  • CPCriminal penalties for breach of the recognised rules of the trade endangering life or limb.