Key takeaways
- A poorly insulated metal profile lowers the interior temperature below the dew point.
- The polyamide insulating strip must maintain seamless continuity at corners and joints.
- Through-screws create point thermal bridges that must be offset using insulating bushes.
- Standard SIA 180 requires mould prevention through rigorous control of the temperature factor.
Thermal behaviour of aluminium and insulation continuity at corners
Aluminium exhibits very high thermal conductivity. Without an effective thermal break, the interior face of the profile rapidly matches the outdoor temperature during freezing periods. When heated indoor air comes into contact with this cold metal, it undergoes sudden cooling. As soon as the surface temperature drops below the condensation temperature, the water vapour contained in the ambient air transitions into a liquid state, generating water run-off and subsequently mould.
Standard SIA 180 specifies the criteria relating to thermal protection and humidity in buildings, requiring the absence of surface condensation and the prevention of mould growth under intended operating conditions.
norme SIA 180
- Dew point
- The temperature at which humid air reaches water vapour saturation at a given pressure, triggering the formation of liquid water on cold surfaces.
To eliminate this energy transfer, composite façade profiles are fitted with insulating strips, generally made of glass-fibre reinforced polyamide, mechanically crimped between the interior and exterior half-shells. Overall performance relies on maintaining a continuous thermal plane. If a discontinuity appears at the junction between mullions and transoms, the heat flow bypasses the insulation.
- Mitre cuts and notchingExecute mitre cuts and notching with precision so that the insulating strips of both profiles meet edge-to-edge without air voids.
- Installation of the insulating corner pieceInsert an insulating corner bracket or inject a polyurethane resin into the thermal chamber at the corner joint.
- Airtightness of the central chamberApply a compatible sealing mastic or a vulcanised gasket to block any convective circulation of cold air towards the interior half-shell.
Neutralising point thermal bridges at mechanical fixings
The transfer of wind loads and dead weight requires the mechanical fixing of pressure plates and anchoring brackets to the load-bearing metal structure. Every carbon steel or stainless steel clamping screw that penetrates the insulating zone forms a thermal short circuit. Even if the polyamide strip is continuous, the screw dissipates heat from the interior to the exterior via point conduction.
| Assembly element | Material used | Thermal and mechanical function |
|---|---|---|
| Crimping strip | Polyamide with glass fibres | Separates the interior shell from the exterior. |
| Insulating bush or sleeve | Rigid synthetic material | Insulates the screw shank from the aluminium profile. |
| Thermal break bearing washer | Elastomer or polyamide | Prevents metal-to-metal contact beneath the screw head. |
| Rebate insulating block | PE foam or expanded EPDM | Fills the void between glazing and pressure plates. |
To comply with the requirements of standard SIA 180, the installer must insert insulating sleeves around the through-screws and place an extruded profile made of cellular material into the channel of the pressure plate. This measure raises the interior surface temperature at the profile nose. During installation, the tightening torque must be checked to avoid crushing the thermal components.
Dew point calculation and requirements according to standard SIA 180
In an aluminium mullion and transom façade, the hygrothermal equilibrium directly depends on the interior surface temperature of the profile exposed to winter climatic conditions. Standard SIA 180 establishes the framework governing thermal protection and humidity inside buildings in Switzerland. When a metal profile suffers from a defective thermal break, its interior face experiences a sudden temperature drop. Heated ambient air, laden with moisture from occupant activity, comes into contact with this cold surface. If the contact temperature falls below the dew point temperature of the indoor air, the water vapour transitions from a gaseous to a liquid state. Droplets run down the profiles, degrade finishes, wet the rebate insulation, and pool at the bottom transoms.
- Interior surface temperature factor (fRsi)
- Dimensionless indicator defined by Swiss thermal standards, representing the ratio of the temperature difference between the interior surface and outdoor air to the total temperature difference between indoor and outdoor air. It quantifies the risk of surface condensation and mould growth.
| Indoor air relative humidity | Dew point temperature | Behaviour of an unbroken profile (-5 °C ext.) | Behaviour of a profile with PA 6.6 strip |
|---|---|---|---|
| 40% RH | 6.0 °C | Immediate condensation (face temperature around 2 to 4 °C) | Sound surface (face temperature maintained around 14 °C) |
| 50% RH | 9.3 °C | Heavy run-off and pooling at the base of the mullion | Sound surface, no water deposition |
| 60% RH | 12.0 °C | Continuous run-off, high risk of mould | Permissible limit reached if ventilation decreases |
| 70% RH | 14.4 °C | Complete saturation, degradation of backing rods | Temporary condensation possible at singular points |
Installation instructions and management of fixing interfaces
On the construction site, the thermal break does not solely rely on selecting a high-performance insulating strip made of glass-fibre reinforced polyamide (PA 6.6) crimped in the workshop. It depends on the precision of assembly execution during installation. Structural steel used as the primary load-bearing frame exhibits lower thermal conductivity than aluminium, but remains a formidable conductor of thermal energy. Any untreated through-fixing creates an intense point heat loss known as a point thermal bridge chi (χ). This phenomenon concentrates the cold flow precisely at the interior fixing of the frame, generating a localised cold spot that condenses even in a properly regulated indoor environment.
- Installing the bracket anchor insulatorIt is imperative to insert a compressible and rot-proof thermal break shim made of engineering plastic (POM, reinforced PA, or high-density elastomer) between the metal load-bearing structure and the aluminium bracket of the façade mullion.
- Insulating studs and clamping rodsTo prevent thermal bridging via direct conduction through steel bolts penetrating the façade insulation, insert insulating tubular sleeves around the threaded rods and place insulating washers beneath the metal bearing washers.
- Checking the glazing rebate insulatorVerify that the continuous insulating profile located between the mullion nose and the exterior pressure plate fits snugly without play. No gap must be left open at mullion-transom intersections, as this would create a linear thermal bridge bypassing the main strips.
- Executing the interior airtightness sealConnect the interior sealing membrane (vapour barrier) tightly and continuously against the interior half-shell of the aluminium profile, in front of the thermal break strip zone, to prevent humid air from reaching the cold core of the rebate.
When the contractor identifies that a metal substrate provided by the structural work or a third-party trade compromises alignment or forces a direct fixing without an insulating shim, the cross-cutting rule applies: the contractor's duty to notify regarding a non-compliant substrate is only detailed under CFC 201; the installation team refers to it to formally notify the client of the situation before any final tightening of the base plates.
Handling condensation defects and remediating thermal breaks
The appearance of running condensate on metal mullions or transoms during winter operation indicates a breach of the isothermal plane or a direct thermal shunt. The diagnostic procedure requires precise hygrothermal measurements prior to any destructive intervention on cover caps or glazing beads.
- Thermographic and hygrometric surveyMeasure the surface temperature of interior profiles using a thermal imaging camera or contact thermometer. Simultaneously record the relative humidity and ambient room temperature to calculate the dew point temperature based on standard SIA 180 principles.
- Non-destructive drilling inspectionDismantle exterior pressure plates in areas experiencing condensation. Check the screw thread engagement to ensure there is no metal-to-metal contact between the pressure plate fixing screws and the interior face of the metal frame.
- Inspection of strips at intersectionsLocally remove glazing blocks to inspect corner junctions. Check whether the polyamide insulating strips are interrupted or if the EPDM corner sealing blocks are missing or improperly compressed.
- Restoration of the insulating planeReplace direct clamping screws with fixings featuring insulating bushes or install continuous synthetic thermal shims. Inject an appropriate polyurethane foam or reinstate the continuous seal bead at transom-mullion joints.
If the thermal bridge stems from a structural workshop defect or a manufacturing non-conformity on the delivered profiles, the contractor refers to the rules of the Code of Obligations (CO). In accordance with art. 365 CO, if the material supplied by the client or the site designated by him is found to be defective, or if any other circumstance arises which compromises the regular or timely execution of the work, the contractor shall inform the client thereof.
Frequently asked questions
How can an invisible thermal bridge behind a façade cover cap be detected?
Use a calibrated thermal camera from the interior during cold weather, with an indoor-outdoor temperature difference of at least fifteen degrees. A localised and linear drop in surface temperature at fixings or mitre cuts immediately reveals the shunt. A surface thermocouple then allows validation of the exact value below the dew point temperature.
What should be done if the polyamide strip is interrupted at a mullion-transom intersection?
An interruption in a strip creates a thermal and air leak. The adjacent glazing units must be removed, the area cleaned, and a specific thermal bridging component made of cellular elastomer or moulded EPDM inserted. This component must be sealed with a compatible mastic to restore the specified continuous isothermal alignment without creating a mechanical discontinuity in the drainage.
Are self-drilling pressure plate screws penetrating the profile nose always insulated?
No, standard screws create a critical point thermal bridge if they touch the interior aluminium. Execution requires thermally broken profiles fitted with an extruded central insulator or engineering plastic saddles. Screws must pass exclusively through the insulating material or be installed with plastic sleeves to avoid any contact with the load-bearing box section.
Does standard SIA 180 permit temporary surface condensation on profiles?
Standard SIA 180 sets requirements to prevent surface condensation and mould formation under normal operating conditions. Transient condensation is only tolerated during exceptional outdoor climatic extremes, provided it does not wet adjacent materials or cause structural or biological deterioration, with drying having to be rapid.
Texts and standards cited
- norme SIA 180Thermal insulation, moisture protection, and indoor climate in buildings
- CO art. 365Material and site: notification to the client if the material supplied or another circumstance compromises regular execution