🧱 CFC 215Interfaces with structural work, tolerances and handoverChapter 2 of 10 in the section

Factory acceptance: inspect at the manufacturer before steel heads to the construction site

A non-compliant primary component rejected upon delivery immediately halts the mobile crane and the erection team. This chapter details the dimensional and quality inspection protocol at the steel fabricator, the rigorous drafting of the joint inspection report, and the formal criteria authorising release for dispatch to the construction site.

Key takeaways

  • Factory inspection prevents the highly costly downtime of mobile cranes and erection teams.
  • Standard SN EN 1090 mandates dimensional, documentary and geometrical verification prior to any dispatch.
  • The acceptance report jointly records interface dimensions, welds, and surface treatments.
  • The release signature governs the collection of steel sub-assemblies and the haulier's departure.

Inspect in the workshop to eliminate the risk of erection stoppages on the construction site

Delivering major steel elements to a Swiss construction site requires rigorous synchronisation. When a sub-assembly such as a built-up column, a truss girder or a facade bracket exhibits a hole centre distance error or an end-plate angular distortion, rejection at unloading immediately halts the mobile crane booked for the day as well as the erection team. The downtime cost of such lifting machinery combined with erector downtime frequently reaches several thousand francs per day. To prevent these disruptions, the site foreman or the works supervisor carries out a systematic workshop acceptance before loading onto the lorry.

The execution of steel structures requires full traceability of components, compliance with manufacturing geometric tolerances and conformity of connections according to the specified execution class.

SN EN 1090

The procedure relies on the SN EN 1090 reference framework. Checkpoints at the manufacturer primarily target assembly interfaces: end plate alignment, actual hole centres for preloaded bolts, squareness of cuts, and compliance with the precamber required during fabrication. The inspector also checks the visual quality of weld beads, the absence of undercut or blowholes, as well as the surface preparation state before painting or galvanising. Regarding bearing on concrete, the steel fabricator verifies the consistency of interface components with their shop drawings; the duty to notify regarding a non-compliant structural work support was addressed in the chapter dealing with masonry trade supports.

Critical points checked during inspection at the steel fabricator
Inspected itemMeasuring toolUsual SN EN 1090 toleranceConsequence of non-compliance
Hole centre distancesCalibrated pin gauge, Class I tape measureDeviation less than 1 to 2 mm depending on classImpossible to pin bolts during lifting
Flatness of end platesPrecision straightedge and feeler gaugesResidual deflection less than 1 mmJoint gapping, loss of load transfer
Beam precamberLaser level, optical lineManufacturing tolerance L/500 to L/1000Elevation defect under dead loads
Corrosion protection thicknessMagnetic induction coating thickness gaugeNominal value according to corrosivity categoryComplete rework of the surface treatment on the construction site

Formalising the factory acceptance report and releasing delivery

Acceptance at the steel fabricator does not rely on simple informal visual appreciation. It is formalised through a factory acceptance report drawn up jointly between the workshop production manager and the erection or works supervisor. This document certifies the dimensional, mechanical, and documentary compliance of the finished components. Under standard SIA 118, joint records accurately register the actual condition of presented elements and establish liabilities prior to the transfer of custody.

  1. Inspection of workshop documentation fileVerify the presence of 3.1 material certificates for rolled steels, the welding quality control plan, and non-destructive testing reports required by standard SN EN 1090.
  2. Joint inspection of assembled componentsMeasure primary dimensions on elements positioned on inspection trestles, cross-check markings against erection drawings, and record any minor reservations.
  3. Verification of coatings and packagingCheck paint dry film thickness and adhesion, ensure complete deburring of contact zones, and verify protection of machined faces during transport.
  4. Establishment of the joint reportExplicitly state inspected parts, resolved non-compliances, any accepted immediate touch-ups, and the agreement of both parties on final quality.
  5. Signing the dispatch releaseFormally sign the delivery release notice, an essential document without which the haulier is not authorised to load the structures.

A contractor supplying a steel frame remains liable to their contracting party for material compliance. Art. 365 CO reiterates the contractor's liability for the good quality of materials supplied under a contract for work and services. Furthermore, if foreseeable delay or defective execution is identified during the factory visit, art. 366 CO allows the client to take action to enforce required repairs or prevent the defective continuation of the works. The unqualified signing of the dispatch release confirms that the steel meets the required geometric criteria and ensures that operations on the construction site proceed without erection downtime.

Geometric and metallurgical checkpoints under standard SN EN 1090

A structural steelwork construction site stoppage caused by a non-compliant component incurs immediate indirect costs: immobilised mobile crane, waiting MEWPs, and stranded erectors. To protect the erection team against these risks, factory inspection mandates a methodical check based on standard SN EN 1090. Verifications are not limited to an overall visual check; they target critical zones where the slightest drift compromises connection with the structural work or the frame's mechanical strength.

Critical hold points during workshop inspection prior to dispatch
Inspected itemInspection toolsAcceptance criteriaDirect impact on the construction site
Base plate and end plate hole centres and drillingsMillimetre pin gauge, assembly template, calibrated tape measureDeviations complying with SN EN 1090 tolerance classesFailure to engage over cast-in anchor bolts
Deflection and straightness of membersLaser line, 3-metre straightedge, precision levelFunctional straightness tolerances according to execution classOut-of-plumb facade or out-of-square bays
Shop weld runsWelding gauge, 100% visual inspection, dye penetrant or ultrasonic testingEffective throat thickness respected, absence of undercut, cracks or inclusionsStoppage of operations for underpinning rework or rejection by the engineer
Coatings and galvanisationMagnetic thickness gauge, cross-cut combMinimum zinc or paint thickness according to the corrosion protection systemExtensive site touch-ups, premature weathering degradation
Identification and CE markingInspection of hard stamping or durable tagsUnambiguous correspondence with erection drawings and 3.1 certificatesOffloading errors, reversed beams, compromised traceability

Raw material conformity serves as the primary barrier against structural defects. The inspector cross-references each cast number hard-stamped on rolled sections or fabricated plates with the factory inspection certificates included in the fabrication file. A steel grade that does not conform to the class specified in the structural calculations invalidates the element automatically, regardless of the geometric quality of its fabrication.

Protocol for clearing reservations, joint sign-off and dispatch note

Formalisation of the factory acceptance report concludes the industrial processing phase and permits transfer to the erection area. This joint document, drawn up by the factory quality manager and signed off by the steel contractor's works supervisor or the site management representative, details every audited element. When minor non-compliances appear, such as a localised low film thickness on a primer coat or machining burrs on a secondary hole, a corrective action sheet defines the repair method and workshop turnaround time.

  1. Full documentation reviewVerification of 3.1 material certificates, welding record sheets, non-destructive testing reports and declarations of performance under standard SN EN 1090.
  2. Joint inspection walk-throughJoint dimensional check of assembled components, inspection of surface condition, absence of handling damage, and validation of paint through-drying.
  3. Handling non-compliances and touch-upsImmediate execution of workshop repairs (deburring, qualified weld repair, spot thermal spraying) under inspector supervision, followed by a new visual inspection.
  4. Signing the acceptance reportSigning the document recording the list of accepted parts, cleared reservations, and any erection notes.
  5. Issuance of dispatch releaseAffixing the release stamp on the delivery note and issuing the loading order sent to the haulier and the site manager.

Once agreement is recorded, components receive green tagging authorising collection. The loading order specifies the orientation of members on trailers to match the lifting sequence defined by the erection scheme. This logistical discipline ensures that the first rigged piece corresponds precisely to the first approved assembly node, eliminating the hazard of intermediate re-handling under the crane hook.

Managing critical non-compliances and arbitration prior to dispatch

Discovering a major non-compliance during workshop acceptance immediately halts the logistical flow. Whether it is a weld flaw detected by dye penetrant testing, out-of-tolerance twisting under standard SN EN 1090, or an incorrect splice hole centre distance, the component does not leave the factory. Premature dispatch shifts the issue onto the construction site, where the downtime cost of a high-tonnage mobile crane and an erection team rapidly amounts to several thousand francs per day.

The immediate logging of a non-conformance report documents the identified geometric or metallurgical deviation. The steel fabricator notifies site management and the civil engineer responsible for the load-bearing structure. Art. 365 CO stipulates that if the material or ground supplied, or any other circumstance, jeopardises the proper or timely execution of the work, the contractor must immediately inform the client. In the workshop, this rapid notification enables assessment of remedial solutions before the lifting schedule is irrevocably compromised.

  • Deviation assessment by the structural engineer: recalculation to approve an extended tolerance or local connection redesign.
  • Definition of repair method: gouging and rewelding in accordance with a qualified welding procedure specification, controlled thermal straightening, or additional bench machining.
  • Corrosion protection repair: grit blasting and reinstatement of the paint system or passivation on areas affected by mechanical intervention.

If the defect cannot be rectified within timelines compatible with erection, the client may exercise rights under the Code of Obligations (CO). Art. 366 CO governs delay and predictable defective execution, allowing a reasonable deadline to be set before contemplating rectification at the defaulting workshop's expense. The rejected component is placed in physical quarantine, identified by visible red marking, until its complete replacement.

Frequently asked questions

Who must attend the factory acceptance inspection before dispatch?

The inspection brings together at least the workshop production manager, the steel contractor's works supervisor, and the site management representative or the structural engineer. For complex frames governed by standard SN EN 1090, the welding coordinator attends the meeting to sign off non-destructive tests and certify conformity of the fabrication records.

Can delivery be approved for a component bearing minor reservations?

Yes, if the reservations affect neither structural safety nor stability during initial erection. Primer paint touch-ups or finishing of a secondary hole can be executed on site. However, the acceptance report must explicitly state that these points do not block transport, setting an execution deadline prior to final bolting of the steelwork.

What should be done if a rejected component halts the overall site schedule?

The works supervisor immediately adjusts the lifting sequence to erect available compliant sections, curbing crane standby costs. Simultaneously, the workshop introduces shift work to refabricate or repair the part under engineering supervision. In the event of non-performance likely to jeopardise contractual milestones, formal notice procedures apply under the Code of Obligations (CO).

What is the legal standing of the dispatch note compared to the acceptance report?

The dispatch note is a purely logistical document confirming the loading and transport of steel elements to the construction site. It does not under any circumstances replace the factory acceptance report. The latter constitutes the joint technical instrument validating geometric and welded compliance under standard SN EN 1090, formally authorising release of the component from the manufacturing facility.

Texts and standards cited

  • SN EN 1090Execution of steel structures and aluminium structures: technical requirements for steel structures and execution tolerances.
  • CO art. 365Materials and ground: the contractor is liable for the good quality of materials supplied; if the material supplied by the client or the site designated by them is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor must inform the client immediately, under penalty of bearing the consequences (para. 3).
  • CO art. 366Delay and predictable defective performance: if the contractor does not begin the work on time, delays execution, or if the delay is such that completion by the agreed deadline is no longer possible, the client may withdraw from the contract without waiting for the scheduled completion date (para. 1); if it is certain that the work will be executed defectively or contrary to the agreement through the contractor's fault, the client may set a reasonable deadline, warning that, upon its expiry, repairs or continuation of the works will be entrusted to a third party at the contractor's expense and risk (para. 2).