Key takeaways
- Standardised clearance directly conditions the slip resistance of connections acting in shear.
- Standard SN EN 1090 imposes direct drilling or punching followed by systematic reaming.
- A slotted hole requires precise orientation, a thick washer and the express approval of the civil engineer.
- Any remedial reaming on site requires a guided tool, formally excluding cutting torches.
- Careful deburring ensures clean mating of components and maintenance of bolt preloading.
Hole sizes and cutting methods according to standard SN EN 1090
In a structural steel frame, load transfer through bolting relies on precise hole geometry. Excessive clearance alters the kinematics of the connection: in simple shear or in preloaded slip-resistant connections, an opening outside tolerances allows differential movements incompatible with the structural engineer's assumptions. Standard SN EN 1090 strictly defines the allowable nominal clearance between the fastener shank and the hole wall.
| Nominal bolt diameter d (mm) | Nominal hole diameter d0 (mm) | Nominal drilling clearance (mm) |
|---|---|---|
| M12 | 13 | 1 |
| M14 | 15 | 1 |
| M16 | 18 | 2 |
| M20 | 22 | 2 |
| M24 | 26 | 2 |
| M27 and above | d + 3 | 3 |
The choice of shop cutting method depends on the steel thickness and the execution class required for the structure. Drilling using twist drills or core cutters constitutes the benchmark method to ensure cylindrical surfaces without metallurgical alteration. Full punching is limited by standard SN EN 1090: it generates microcracks and severe peripheral work-hardening on the die exit edges.
The drilling or punching operation must always conclude with full deburring. The presence of compressed swarf or metal burrs between splice plates and section flanges prevents perfect contact between friction surfaces. This lack of adhesion leads to rapid loss of preload in preloaded bolted connections.
Management of slotted holes and regulation of on-site reaming
Slotted holes are intended to accommodate erection tolerances or allow controlled thermal expansion, particularly at anchor brackets for composite facades or connections on secondary beams. They must never be used to make up for setting-out errors without structural verification. The long axis of the slot must be positioned perpendicular to the direction of the applied load, unless technically justified and validated.
- Short slotted hole
- Bolt hole whose width matches the normal hole diameter d0 and whose total length equals d0 plus a limited travel, calculated according to standard SN EN 1090. It requires the use of thick flat washers under both head and nut to distribute bearing pressures without plate deformation.
On the construction site, alignment errors between shop drillings and connecting steel create hole misalignments. Forcing bolts through using sledgehammers is strictly prohibited, as it risks damaging threads and introducing residual bending stresses into the shank. Using a cutting torch or plasma cutter to slot a hole on site is strictly prohibited by professional standards.
- Assessment and validation by the engineerMeasure the geometrical offset between the parts to be connected. Submit the survey to the structural engineer to verify that hole enlargement or repositioning respects minimum end and edge distances.
- Mechanical securingClamp the framing members using heavy-duty G-clamps or tapered drift pins to prevent any relative movement during machining.
- Reaming using rotary toolsRework the hole using a magnetic base drill fitted with a tapered reamer or an annular cutter. The operation must yield a perfectly smooth internal surface without crack initiation sites.
- Corrosion protection and erectionClean away swarf, remove sharp edges, and apply a zinc-rich corrosion protection coating to the exposed steel before inserting the permanent fasteners.
If the final diameter after reaming exceeds the standardised clearance, the bolt class must be adapted. Using a larger diameter bolt, or switching from an ordinary Category A connection to a preloaded connection with hardened washers, compensates for slotting while ensuring the node does not deform under service loads.
Mechanical behaviour of connections: hole clearance and load transfer
In a steel frame, the mechanical performance of a bolt directly depends on the fit tolerance between the threaded shank and the hole wall. In standard connections acting in shear and bearing, nominal clearance permits an initial slip of the sections before mechanical bearing engagement occurs. This residual movement modifies the bending moment distribution and alters the geometry of rigid nodes under wind or live loads.
For structural nodes where no slip is permitted under service or ultimate load combinations, the engineer specifies friction-grip preloaded connections. Transverse load transfer then does not rely on direct bearing of the bolt shank against the plate, but on the friction developed across the interface of the clamped plates. Any excessive hole clearance or wall deformation under clamping force compromises preload stability.
| Fastener category | Loading mode | Load transfer | Hole clearance requirement |
|---|---|---|---|
| Category A | Simple shear | Bearing after clearance take-up | Standard clearance (1 mm to 2 mm depending on diameter) |
| Category B | Slip-resistant at SLS | Friction between plates under preload | Standard or oversized clearance subject to design calculation |
| Category C | Slip-resistant at ULS | Friction without slip possible under ultimate loads | Strict standard clearance or close-tolerance reamed holes |
| Fitted bolts | Shear without clearance | Immediate direct bearing on hole walls | Direct reaming H11 after trial assembly |
Hole ovalisation resulting from off-centre punching or mating misalignment drastically reduces the contact area under the head. When the thickness of a splice plate exhibits local deformation exceeding connection thresholds, preload force is no longer uniformly guaranteed. Site managers must ensure before bolting that the plate stack achieves full contact without gaps visible to a 0.5 mm feeler gauge.
Installation protocols for thick washers and slip-resistance checks
The use of slotted or oversized holes alters the distribution of local compressive stresses under the washer. In these specific configurations, standard thin metal washers buckle or dish into the opening gap, triggering an immediate drop in bolt axial tension. Structural steelwork then requires the installation of cover plates or hardened washers of appropriate thickness.
- Short slotted holes: mandatory installation of a washer at least 4 mm thick under both head and nut if the connection is preloaded.
- Long slotted holes: installation of a continuous cover plate or flat strip at least 8 mm thick fully covering the slot opening.
- Slot orientation: the major axis of the slotted hole must be oriented perpendicular to the line of action of the shear force, unless expressly authorised by the civil engineer.
- Chamfer orientation: assemble the washer with the internal chamfer facing the fillet under the bolt head to prevent stress concentration.
- Stack-up inspection before tighteningCheck visual alignment of the components using an alignment pin. Using a tapered drift pin must never tear the hole edges or plastically deform the contact rims.
- Positioning of packing elementsInsert the specific thickness washers specified for oversized holes. Check that no radial play remains under the outside diameter of the washer.
- Application of snug-tight torqueApply initial tightening to approximately 75 % of the final torque across the entire bolt group, working from the centre toward the outer edges to bring the contact surfaces firmly together.
- Final tightening and inspection markingApply the prescribed torque according to the execution class. Draw a paint witness mark connecting the nut, threaded shank and washer to identify any subsequent unintended movement.
The erection foreman logs all inspected diameters, packing values and any reaming operations carried out with rotary tapered reamers in the site logbook. Full compliance of holes with erection drawings ensures wind loads are transferred without dimensional drift in the completed structure.
Hole non-conformities and on-site remedial actions
On the construction site, hole misalignment directly impairs structural frame node kinematics. If components do not engage freely, using a cutting torch or manual thermal cutting to force passage is strictly prohibited by standard SN EN 1090. These practices create crack initiation sites, locally modify the steel microstructure, and nullify load-bearing guarantees, particularly for preloaded non-slip connections.
- Observation and immediate erection haltAs soon as a drift pin fails to pass without excessive force, secure the section under the crane or on temporary falsework. Measure the actual offset with callipers.
- Technical assessment and engineer endorsementRecord the offset in the erection report. Submit the remedial solution to the site management: reaming to the next diameter up with bolt adaptation, or controlled conversion into a slotted hole.
- Clean machining and deburringCarry out reaming at controlled speed with appropriate lubrication. Chamfer sharp edges to remove all burrs preventing perfect seating of bearing washers.
- Restoration of corrosion protectionDegrease the machined area, remove swarf, and apply a compatible primer (liquid zinc or zinc-rich paint) compliant with the specified protection system requirements.
Pursuant to art. 365 CO, if any circumstance compromises the proper or timely execution of the work, the contractor shall inform the client thereof. Art. 229 CP provides penalties for breaches of the rules of the art of building endangering the life or physical integrity of persons. Full traceability of every reworked hole protects the structure.
Frequently asked questions
Can a hole be slotted using a cutting torch to facilitate bolt insertion?
No, this practice is strictly forbidden by standard SN EN 1090. Manual thermal cutting alters the steel grade through uncontrolled heat input, generates notches, and impairs bearing area under the head. Any adjustment must be performed mechanically, using a tapered reamer or guided milling cutter, subject to prior approval from the structural engineer to ensure load capacity.
Which washer should be fitted when using a slotted hole in a base or splice plate?
A slotted hole requires fitting an approved thick washer, or even a steel cover plate at least 8 mm thick. This load-bearing component distributes tightening stresses over the hole edges and prevents creep or local dishing under tension, thereby ensuring required friction is maintained without plate distortion.
What is the standard clearance tolerance for an ordinary M20 bolt?
For a standard non-preloaded metric M20 bolt, the nominal standardised hole size is 22 mm, providing a diametral clearance of 2 mm according to standard SN EN 1090. Any larger diameter or slotted geometry not specified on the fabrication drawings requires formal authorisation from the civil engineer, as load transfer through bearing is altered.
How should corrosion be treated on a hole reamed directly on the construction site?
Any site machining removes the original protective coating, whether hot-dip galvanising or a shop paint system. It is necessary to immediately deburr, clear away swarf, degrease the bare steel surface, and apply by brush an equivalent-thickness zinc-rich touch-up system certified for the project's corrosivity class, prior to final bolt tightening.
Texts and standards cited
- SN EN 1090Execution of steel structures and aluminium structures: technical requirements for steel structures.
- CO art. 365materials and ground: the contractor is liable for the sound quality of the materials supplied; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he shall immediately inform the client thereof, on pain of bearing the consequences (para. 3).
- CP art. 229breach of the rules of the art of building: whoever intentionally infringes the recognised rules of the art and thereby knowingly endangers the life or physical integrity of persons when directing or executing construction or demolition work shall be liable to a custodial sentence not exceeding five years or a monetary penalty; in the event of negligence, to a custodial sentence not exceeding three years or a monetary penalty.