Key takeaways
- A beam tipping in mid-air results from a centre of gravity incorrectly positioned beneath the hook.
- The lifting points shown on the erection drawing dictate the exact position of the slings.
- Using a rigid spreader beam guarantees a vertical load without crushing the structure or slipping.
- Each piece of lifting tackle undergoes a strict visual inspection by the erector before use.
Prevention of tipping risks and SUVA directives during lifting
During crane handling operations, an IPE or HEB steel beam that tips during transfer poses an immediate fatal risk on the construction site. Destabilisation generally occurs when the centre of gravity of the component is located above the suspension line or when the cable slips along the flange of the section. The Construction Work Ordinance requires workstations and passageways to be organised to protect personnel against falling objects or the overturning of structural elements.
To ensure safety on the construction site, the design engineering office defines in advance the lifting points provided on the working drawing. These points take into account weight distribution, the presence of asymmetrical welded base plates, and the elastic deflection of the section during lifting. The steel erector must strictly comply with these planned anchor points without improvising any attachment point on the construction site.
- Verification of the total weight of the section stated on the manufacturer's shipping document.
- Identification of slinging holes or temporary attachment fittings welded in the workshop.
- Fitting of rigid polyurethane corner protectors on the edges of IPE/HEB flanges.
- Cordoning off and prohibited access to the load travel area during the manoeuvre.
Balancing with a spreader beam and inspection of certified tackle before use
Using a lifting spreader beam remains the required solution for handling long-span beams. By keeping the sling legs perfectly vertical, the spreader beam eliminates transverse compressive forces on the component and removes the risk of hooks sliding towards the centre. Balancing the load is achieved by adjusting the position of the suspension points relative to the actual centre of gravity of the steel component.
| Lifting tackle | Condition of use | Main risk avoided |
|---|---|---|
| Fixed hook spreader beam | Straight symmetrical HEB / IPE beams | Crushing of flanges and slippage |
| Grade 80/100 chain sling | Sharp edges with steel sleeves | Shear failure on corners |
| Self-locking beam clamp | Individual lifting of rolled sections | Unhooking under load during swinging |
- Visual inspection of equipmentCheck for the presence of identification tags indicating the working load limit (WLL) on each sling, shackle and on the spreader beam. Reject any equipment showing deformation, incipient cracking or wear beyond tolerances.
- Inspection of safety componentsCheck the correct operation of safety catches on all lifting hooks as well as full engagement of shackle pins fitted with their split pins.
- Adjustment of the centre of gravityPosition the crane hook plumb above the exact centre of gravity of the section. Attach slings to the points identified on the component and perform an initial trial lift 10 cm off the ground.
- Confirm stability before transferEnsure the suspended section is perfectly level. If the component tilts, lower it immediately back to the ground and correct the attachment point on the spreader beam.
Locating lifting points and specifics of HEB and IPE sections
The overhead handling of I- or H-beams, such as IPE and HEB sections, allows for no improvisation. Due to their asymmetrical geometry in terms of stiffness distribution and their susceptibility to lateral-torsional buckling, inappropriate slinging leads to a major risk of tilting or slipping under load. The exact determination of lifting points derives directly from the structural steel calculations and the indications shown on the erection drawings approved by the design engineering office.
On broad-flange HEB sections, the centre of gravity corresponds to the geometric longitudinal axis, provided the component does not include stiffeners, asymmetrical end plates or off-centre welded gussets. For an IPE section, the narrow flange width increases lateral instability during lifting. If anchor points are not factory-welded or tapped, direct choke hitch slinging around the steel section requires the use of protective sleeves to prevent shearing of webbing or crimping of wire ropes against the sharp edges of the component.
| Section type | Recommended attachment method | Required tackle | Specific point of vigilance |
|---|---|---|---|
| HEB section (span < 8 m) | Basket hitch or direct 2-leg sling | Webbing slings with sleeves or steel wire ropes | Check perfect centring of the load before lifting off the ground |
| HEB section (span > 8 m) | Rigid hook lifting spreader beam | Certified spreader beam, safety shackles with bolt and nut | Prevent excessive longitudinal deflection during the hoisting phase |
| IPE section with end plates | Temporary slinging lugs or tapped fittings | Swivelling articulated lifting eye bolts | Comply with tightening torque and alignment along the line of pull |
| Plate girder (PRS) | Factory anchor points defined on drawing | Grade 80/100 chain slings with shortening clutches | Account for the off-centre shift of the centre of gravity caused by gussets |
Spreader beam use, balancing and inspection of certified tackle
The use of a lifting spreader beam is required as soon as the length of the section produces significant deflection under its own self-weight or when the angle formed by a two-leg sling exceeds permissible tolerances. The spreader beam guarantees a strictly vertical pull on the lifting points, thereby eliminating transverse compressive forces liable to crush the flanges of IPE sections or cause slings to slide along the body of the component.
- Visual inspection and adequacy of markingsCheck for the presence of the rating plate displaying the working load limit (WLL), CE marking, manufacturer's name, and the date of the latest mandatory periodic inspection recorded in the register.
- Methodical inspection of gripping devicesCheck for the absence of permanent deformations, incipient cracks, nicks, pitting corrosion, or elongation of chain links and shackle bodies. Note any broken wires on steel wire ropes.
- Positioning and balancing without loadAdjust the sliding hooks on the spreader beam in exact match with the centre-to-centre distances shown on the structural steel drawings. Perform an initial trial lift 10 cm off the ground.
- Levelling confirmation and guidanceConfirm that the beam is perfectly horizontal. Attach two synthetic tag lines to the ends to steer the load remotely without ever standing beneath the lifting path.
Directives of the Swiss National Accident Insurance Fund (SUVA) mandate the immediate removal from service of any lifting equipment showing a visible defect. A webbing sling cut across more than 10% of its width, a hook with a defective or deformed safety catch, or a shackle whose pin has been replaced by an uncertified site bolt are grounds for stopping work on the construction site. The foreman ensures that the inspection register for lifting equipment and tackle is up to date before erection operations commence.
Managing lifting anomalies and emergency procedures on the construction site
Whenever a steel section (HEB or IPE) starts to tilt, experiences unexpected slippage in its slings, or presents an anchoring defect while suspended, the foreman must order an immediate stop to the manoeuvre. No manual adjustment or hand-guiding must be attempted on an unstable load suspended from a hook. The danger zone beneath the boom and within the slewing radius of the component must be evacuated immediately by the erectors. The crane operator lowers the load to the ground or onto a stabilised safety packing support if lowering is possible without snagging hazards.
- Root cause analysis and load inspectionAfter lowering the section safely to the ground, inspect the integrity of the steel component and attachment points. Check whether the slippage resulted from poor positioning of the centre of gravity, an excessive slinging angle, or the presence of oil on the beam flanges.
- Rectification of the lifting arrangementAdjust the position of the spreader beam or adjustable sling legs. If the lifting points specified on the erection drawing prove unsuitable due to an on-site change, request written approval from the structural engineer before any further lifting attempt.
- Authorisation to resume operationsLifting is resumed only after a full visual inspection of the rigging by the gang leader and confirmation that weather conditions, particularly wind speed, allow work at height.
Deliberate disregard of slinging rules, the use of decommissioned lifting tackle, or continuing an unstable lift directly endangers the lives of personnel on the construction site. Site management ensures strict compliance with the recognised rules of the trade in steel erection. In the event of an accident resulting from gross negligence or disregard of safety instructions, criminal liability of the parties involved may be incurred on the basis of CP. Active prevention remains the only means of ensuring safe erection.
Frequently asked questions
What should be done if an HEB section slips slightly in its webbing slings during hoisting?
If slippage is observed during the lifting of an HEB beam, the crane operator must stop the movement immediately and lower the component smoothly back to the ground. It is strictly prohibited to straighten the load while suspended or pull on the slings by hand. After landing, inspect the webbing sling for any cuts caused by the sharp edges of the component, then clean off any mill oil present on the section.
Can temporary lifting eye bolts be welded directly onto the flanges of a steel beam?
Welding temporary lifting lugs onto a section is permitted only if specified on the erection drawing approved by the structural engineer. Welds must be executed by a qualified welder and sized to withstand tensile and shear stresses. Following final positioning of the section, grinding off the temporary lugs must be carried out without gouging the load-bearing cross-section or compromising the corrosion protection of the component.
How should one react if the safety catch on a spreader beam hook breaks during lifting?
If the safety catch on a spreader beam hook breaks or jams, the manoeuvre must be stopped as soon as the component is stabilised or set down on its support. A lift must never be continued with a defective hook. The hook must be locked out of service and repaired by a certified specialist before any further use. Using wire or adhesive tape to secure a broken catch is proscribed.
Who must carry out daily inspections of slings and rigging on the steel erection construction site?
The daily visual inspection of lifting equipment is the responsibility of the slinger-signaller and the gang leader before each work shift. They check the legibility of rating tags and the absence of deformation, wear or tears on slings and chains. In addition, an in-depth periodic thorough examination must be conducted by a qualified competent person, with results recorded in the company's lifting equipment inspection register.
Texts and standards cited
- OTConstOrganisation of occupational safety and appointment of a competent person on the construction site
- CPBreach of the recognised rules of building and endangering the life of others
- SIA 263Steel structures - Design, dimensioning and execution of steel structures
