Skip to content
Website
🧱 CFC 215Steel: grades, sections and execution classesChapter 9 of 10 in the section

Storing steel on the construction site: bearers, drainage slope and surface corrosion

This chapter details the rules for temporary storage of steel sections and sub-assemblies on the construction site. The metal constructor learns how to set out stable bearer layouts, ensure a minimum fall to prevent standing water, distinguish admissible flash rust from deep degradation, and protect painted or treated parts from permanent markings.

Key takeaways

  • Isolate sections from the ground using evenly spaced runners laid on a draining platform.
  • Ensure a continuous longitudinal fall to drain rainwater clear of the chords.
  • Prevent steel-to-steel contact to avoid the formation of under-film corrosion.
  • Protect finished coatings using clean spacers and remove watertight plastic sheeting.

Preparing the laydown area, placing bearers and setting the drainage fall

Organising a storage area for structural steel requires a compacted, free-draining platform clear of puddles. Offloading structural members directly onto bare ground, rubble or a flood-prone slab compromises the integrity of the steelwork even before lifting begins. Sections must rest on stable bearers, raised at least 150 mm above natural ground level to prevent mud splashes, immersion of the bottom flanges and capillary moisture draw.

Bearers must consist exclusively of dry softwood, untreated baulks or rot-proof polyethylene pads. Wet timber or wood impregnated with acidic substances releases tannins that permanently stain shop primers. Vertical alignment of bearers from one tier to the next is essential: each intermediate bearer must sit precisely plumb above the support below to transfer loads straight to the ground without causing residual bending or local web crippling under the weight of the stack.

Indicative bearer spacing according to section profiles
Section typeSection heightMaximum bearer centresMaximum end overhang
I and H sections (IPE, HEA)Less than 200 mm3 m 000 m 80
I and H sections (HEB, HEM)200 mm to 500 mm4 m 501 m 20
Hollow sections (square, rectangular tubes)All sizes4 m 001 m 00
Plate girders (PRS)Over 600 mmSpecific calculation / 3 m 000 m 60

The orientation of sections in the storage yard must preclude any natural water traps. Channel sections (UPN, UPE) and unequal angles must never be stored with the channel or trough facing upwards. For I-beams laid on their flange, a tapered bearer or a longitudinal level difference of at least 1 % to 2 % forces immediate run-off of precipitation towards the ends, preventing standing water on the chords.

Preventing standing water, assessing rust and protecting paintwork

Water trapped between two stacked sections triggers differential aeration corrosion. Dissolved oxygen is depleted at the centre of the contact area while the perimeter remains aerated. This confinement creates a microscopic galvanic cell that aggressively attacks bare steel or destroys unfinished anticorrosion systems. Even after drying thoroughly, these enclosed areas leave dense oxide rings and residual salts that subsequent finish coats cannot passivate, leading to mid-term blistering.

  1. Sorting and visual inspectionCheck the surface rust grade upon arrival in accordance with applicable surface preparation standards. A uniform, non-powdery flash rust layer on bare steel intended for shop blast-cleaning remains admissible; however, pitting or flaking mill scale disqualifies the substrate without extensive mechanical treatment.
  2. Separation of painted surfacesSystematically insert dry timber battens, dense synthetic felt or elastomeric strips between coated or shot-blasted and painted sub-assemblies. No steel-to-steel contact is permitted when stacking multiple components.
  3. Management of transit coveringsImmediately slice open or remove heat-shrink wraps and closed polyethylene sheeting upon delivery to the site. These coverings act like ovens under direct sunlight, sustaining constant condensation that softens freshly cured paint systems.
  4. Draining hollow bodiesVerify the presence of temporary weep holes at the lowest point of closed hollow sections and column stems fitted with welded end plates, otherwise freezing water will burst the steel walls during winter.

On components treated with a final anticorrosion coating (industrial liquid paint or powder coating), any scuffing caused by unstable bearers exposes the structural steel to atmospheric conditions. If blistering or surface defects appear on painted surfaces due to trapped water, the repair protocol requires sanding back to sound steel, degreasing with a suitable solvent and a localised touch-up compatible with the original binder, approved by the site foreman before the part is finally erected in the structure.

Arrangement of bearers, drainage fall and preventing water pooling

On an assembly area in French-speaking Switzerland, temporary storage of structural steel members requires uncompromising geometric discipline. Setting beams straight down on bare concrete slabs, asphalt or a gravel bed traps moisture against the metal and exposes the coating to mineral contamination. Direct contact with the ground fosters capillary action and blocks rainwater run-off. Setting out dry softwood runners or oak timbers at least 100 mm thick provides the essential first line of defence.

Stacking directly flange-to-flange causes severe capillary moisture trapping. When two flat steel surfaces meet, rainwater seeps between the faces and fails to evaporate. This trapped water dissolves residual soluble salts and chemically degrades the shop primer film. To eliminate this risk, each stack tier must include trapezoidal or rectangular spacing strips aligned strictly plumb over the lower supports, preventing plastic deformation under self-weight across long spans.

Stack stability also complies with rigorous safety standards. In accordance with art. 17 OTConst, at workstations and walkways, measures must be taken so that workers are not endangered by the collapse of building elements or the fall of objects and materials. Bearers must not project excessively beyond bundles where they could obstruct access routes for lifting equipment or site personnel.

Acceptable rust criteria and preservation of anticorrosion coatings

Not all oxidised states are equal when taking delivery of steelwork on the construction site. For hot-rolled steels delivered in as-rolled condition prior to blast-cleaning and coating, mill scale offers partial protection to the metal but cracks quickly. A clear distinction is made between light surface flash rust, which exhibits no pitting or significant metal loss, and heavy flaking scale that compromises the surface preparation grade required before applying finish or intumescent paint.

Section surface diagnosis and site preservation measures
Condition observed on siteConsequence on substrateTechnical admissibilityRemedial action
Uniform yellow-orange flash rustSuperficial oxidation without steel pittingAdmissible on bare steel before shop shot-blastingLight manual wire brushing before assembly or welding
Black oxide film with exfoliated mill scaleFlaking of mill scale in the presence of moistureNot admissible for direct paint applicationGrit-blasting or mechanical grinding at connection nodes
Ferruginous water marks under contacting flangesOsmotic degradation of primer and discolourationRejected if final anticorrosion system applied on sitePressure washing, localised sanding and touch-up
Crevice corrosion at splice connectionsPitting and measurable loss of section thicknessNot admissible (geometric non-conformance)Dimensional survey and complete coating reinstatement

Painted or galvanised components delivered to the site demand increased vigilance. Sections fitted with a finished anticorrosion system must never come into contact with unjacketed steel wire ropes or lifting chains without polyurethane protective sleeves. Paint repairs on site consume time and compromise the visual uniformity demanded by the site management.

  • Insert elastomeric strips or rot-proof felt between timber bearers and painted flanges to prevent tannin leaching.
  • Prohibit airtight wrapping under impermeable plastic sheeting: prefer breathable tarpaulins to avoid condensation under covers in direct sun.
  • Protect manholes, gusset plates and machined bearing faces with peelable varnish or temporary sealing grease.
  • Promptly wash off deposits of cement dust or site slurry generated by the passage of earthmoving trucks.

Maintaining structural steel quality relies on coordinating supply logistics with the lifting schedule. Under art. 365 CO, the contractor is liable for the sound quality of the materials supplied. Storing components beyond agreed durations without renewing surface protections directly engages the steelwork contractor's liability towards the client.

Site repair protocols for standing water or surface degradation

If a bundle's bearers settle or rainwater remains trapped between two stacked sections, the paint film or shop primer rapidly degrades through blistering, delamination or underlying rust formation. On a structural steel or load-bearing façade construction site, these defects prevent direct erection without prior remediation, otherwise the failure will re-emerge irreversibly under the completed building's finish coats.

  1. Batch isolation and adhesion testingRemove affected components from the stack, clear residual water and check primer adhesion with a manual tape or cross-cut test across the bearing areas.
  2. Clean-water washing and degreasingRinse the surface thoroughly under moderate pressure to dissolve all embedded ferrous salts, then remove greasy residues using an appropriate solvent.
  3. Localised mechanical prepGrind or wire-brush blistered zones and rust pits back to sound bare metal, feathering the edges of intact surrounding paint.
  4. Touch-up coating applicationImmediately brush-apply the original primer or a compatible epoxy resin, respecting the dry film thicknesses specified in the specifications.

Under art. 17 OTConst, measures must be taken at workstations and walkways so that workers are not endangered by the collapse of building elements or the fall of objects and materials. Re-stacking unstable or settled piles therefore requires a controlled restacking operation, systematically slinging sections with the crane. The contractor also applies the general provisions of the Code of Obligations (CO) for the contractual handling of defects identified upon delivery or caused by severe weather.

Frequently asked questions

How do you distinguish acceptable surface rust from inadmissible corrosion?

Acceptable rust forms a uniform, powdery orange-brown film with no measurable thickness loss using callipers and no lifting of rolling scale. It wipes clean with light hand brushing without pitting the parent metal. If the rust exhibits visible pits, deep blistering or lifts the shop primer, the corrosion is inadmissible and requires mechanical grinding back to bright steel followed by a compliant paint touch-up.

Why must water-soaked rough timbers be avoided under painted sections?

Unseasoned softwood or rain-soaked timber releases organic acids and maintains continuous moisture against the steel flange. This enclosed interface forms a differential aeration cell that destroys the shop primer binder within a few weeks. Only dry planed timber bearers isolated with elastomeric strips, or free-draining composite spacers, should be used to support finished metal components.

What drainage fall should be provided for stacks of beams to prevent water pooling?

A minimum longitudinal fall of 1 % to 2 % must be built in when laying the initial ground bearers. This incline ensures the natural run-off of rainwater towards the open ends of IPE or HEA sections. Hollow components like rectangular or square tubing must be arranged so that any drainage holes are not blocked by the timber bearers.

What should be done if timber bearers partially settle under a bundle of steel?

Immediately cordon off all access to the storage area. The remedy consists of slinging top bars individually with the crane to lighten the stack, then replacing rigid bearers on compacted, free-draining ground. Attempting to hammer out or wedge bearers under a loaded pile is strictly forbidden due to the fatal risk of collapse or slip.

Texts and standards cited

  • OTConst art. 17protection against the collapse of building elements or the fall of objects and materials: at workstations and walkways, measures must be taken so that workers are not endangered.

In the same section