Key takeaways
- Lifting must begin with a braced bay to ensure immediate three-dimensional stability.
- Standard SIA 263 requires the verification of climatic and site loads during temporary phases.
- Slings remain tensioned as long as temporary or permanent stability connections are not bolted.
- Permanent bracings must be secured before extending the structure to adjacent bays.
Lifting sequence and design of temporary bents
Steel frame erection cannot be improvised on the crane hook. Without its complete system of bridging and bracing, an isolated element offers no resistance to horizontal forces induced by wind or load sway. The structural steel engineer and the site manager must approve the erection plan before the first lift. The fundamental rule is to erect the stability core first, consisting of a rigid bay equipped with its vertical bracing bents and wind girders.
The structure must provide adequate safety against collapse and excessive deformation at all stages of erection, taking into account temporary construction loads and wind actions.
norme SIA 263
When the building architecture does not permit starting with the bay containing the permanent bracing, the use of temporary bents becomes mandatory. These systems, often made of tubular sections or guy ropes with turnbuckles, take up horizontal forces. The design of these temporary elements is governed by standard SIA 263: they must withstand site wind gusts as well as initial out-of-plumb deviations before the final grouting and shimming of baseplates.
| System | Main use | Installation point to watch |
|---|---|---|
| Steel wire ropes with turnbuckles | Temporary guying of isolated columns | Tension check with a dynamometer and verification of the ground anchor angle |
| Bolted tubular bents | Stability of tall bays before installing permanent bracing | Resisting compressive forces and checking anchors in concrete |
| Temporary raking props on foundation blocks | Restraint of large-span frames and portals | Provide transfer plates designed for shear force |
Switching to permanent bracing and releasing lifting equipment
Once the rigid core or first stable bay is assembled, progress of the structure is carried out by cantilever or by successive bays tied back to the main block. Each new column or beam added must be immediately tied back to the already stabilised section by its sag rods, purlins, or spacers. Temporary bolted connections must contain the minimum number of bolts required by the erection calculation notes before continuing infill work.
- Erection of the reference bayErection of the first 4 columns, installation of main beams, and torque tightening of permanent bracing diagonals or installation of temporary guy ropes.
- Geometric and plumb checksVerification of column verticality and axis alignment with a total station before locking the baseplates onto the reinforced concrete.
- Installation of permanent bracing membersInstallation of permanent cross bracings, tubes, or tie rods. Locking of connections and verification of preloads according to standard SIA 263.
- Removal of temporary bentsMethodical dismantling of temporary guy ropes once overall stability is ensured by the permanent elements of the project.
Accurate alignment of the structure and grouting under baseplates conclude the initial fixing stage. Only when permanent bracings are fully installed and tightened to the specified torque may adjacent structures be loaded, particularly during the installation of metal decking or composite slabs. For details on crane and lifting plant hire costs, refer to the rates in the /tenders/ section.
Erection sequencing and inspection of temporary stability bents
The erection of a steel frame allows no improvisation on the construction site. A steel structure during assembly goes through critical phases where its geometry depends entirely on temporary fixings and an approved lifting sequence. Standard SIA 263 defines the fundamental requirements regarding structural safety and the behaviour of steel members, but it is the rigorous preparation of the erection plan that guarantees resistance to wind forces, eccentric actions, and the self-weight of members not yet braced.
The approved lifting sequence requires erecting the stability cell or rigid core first. If the construction site does not allow direct access to this central bay, the erector must erect temporary stability bents. These temporary systems, made of adjustable tie rods, tubular section bracings, or heavy-duty props, absorb all horizontal loads until the permanent structural grid is fully assembled and bolted.
| Temporary equipment | Primary field of application | Installation and adjustment | Critical inspection point |
|---|---|---|---|
| Wire rope ties with turnbuckles | Low-rise sheds, light frameworks | Manual tensioning with a torque wrench | Checking for wire rope clip slippage |
| Bolted section bents | Multi-storey buildings, heavy loads | Assembled on the ground then lifted by crane | Tightening HR/HV bolts to the specified torque |
| Heavy-duty telescopic props | Temporary shimming of isolated columns | Millimetre adjustment via base screw | Ground anchoring on concrete slabs or pads |
Completion of permanent bracing and unhooking instructions
Unhooking an element from the crane hook must never take place before the spatial stability of the bay under assembly is physically ensured. This is an absolute safety rule on the construction site. For every column or rafter, the erection gang immediately fits the required connecting bolts and installs the temporary or permanent bracings specified on the erection drawing.
Switching to permanent bracing requires strict geometric checks (column plumb, beam level, squareness of bays) before final tightening of connections. Cross bracings, bracing purlins, and stiffening diaphragms must be installed in the exact sequence determined by the design office. As soon as the permanent bracing phase is approved for an area, temporary bents can be removed safely, allowing lifting plant to be released and loads to be transferred to the foundations.
- Installation of the initial stability blockErection of two successive portal frames connected by their permanent bracings (cross bracings or wind girders) and tightening of connection bolts.
- Topographic survey of the structureVerification of alignments, verticality tolerances, and diagonal tension before releasing temporary bents.
- Compliance notice and equipment releaseRecording the approval of the rigid bay in the site log, authorising the final release of temporary bents and the advancement of typical bays.
Managing erection deviations and emergency stabilisation
During the erection of a steel frame, an out-of-plumb deviation exceeding tolerances or the inability to align a bolted connection indicates deformation under self-weight or movement of supports. In the event of a geometric error or an unexpected wind gust before the stability cell is in place, all assembly work at height must be stopped immediately. The major risk is progressive buckling of unsupported columns caused by load shedding.
- Immediate securing of the bayKeep the load suspended from the crane hook if the element is being placed, or immediately install temporary guying using steel wire ropes fitted with turnbuckles fixed to verified anchor points.
- Topographical survey of deviationsMeasure out-of-plumb deviations with a total station and compare recorded values against erection tolerances defined by standard SIA 263/1 and standard SIA 414.
- Consultation with the structural steel engineer or appointed specialistSubmit the deviation survey to the design office to approve the rectification procedure (reaming holes, column base shimming, or adjusting temporary bents).
- Controlled unhookingThe member or bay may only be unhooked after safety guy ropes are fully locked off and written approval is granted by the erection manager.
In accordance with the Construction Work Ordinance, all emergency stabilisation measures and protections against falling components must be planned and recorded in the health and safety plan. Erector safety and overall structural stability remain inseparable until final tightening of the permanent diagonals.
Frequently asked questions
Can a steel column be unhooked if only the baseplate bolts are tightened?
No. An isolated column, whether pinned or fixed at the base, does not provide sufficient stability against wind forces or impact loads during construction. It must be immediately braced with temporary rakers or tied to a rigid stability bent by a beam locked against rotation before unhooking from the crane is permitted.
How can column level and plumb be adjusted without forcing the connections?
Adjustment is carried out at the column base by adjusting levelling nuts under the baseplate or using calibrated steel shims. Alignment of corner bolt holes is achieved using tapered drift pins inserted manually before installing the permanent bolts.
Who decides on the installation and removal of temporary guy ropes on the construction site?
Temporary guy ropes are installed by the erection gang according to the temporary propping plan. Their removal is exclusively authorised by the site foreman or the site manager after complete assembly of the permanent bracing cell and verification of the torque tightening of all structural bolts.
What should be done if a bolt hole does not line up during lifting?
The member must be held stationary with the crane and the overall geometry of the bay must be checked. If the discrepancy exceeds allowable tolerances, grinding or reaming is prohibited without the explicit agreement of the structural engineer. The member must be adjusted using the adjustment mechanisms of the temporary bents.
Texts and standards cited
- norme SIA 263Steel structures - Design and calculation
- norme SIA 263/1Steel structures - Complementary specifications for execution
- norme SIA 414Tolerances in building construction and interior works
- OTConstOrdinance on safety and health protection of workers in construction work