🧱 CFC 215Section 4 of 610 chapters

Corrosion protection and fire resistance: the execution reference standard

Intended for team leaders, foremen and site managers in steel construction (CFC 215), this section details the methods for preserving the steel structure against atmospheric degradation and thermal failure. From initial blast-cleaning to non-destructive testing of dry film thicknesses, it brings together the concrete application rules for paint, galvanising and fireproofing systems according to standards ISO 12944 and SIA 263.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

ISO 12944

3 °C

Minimum required clearance between steel temperature and dew point during paint application

ISO 12944

Sa 2 ½

Minimum surface preparation grade by abrasive blast-cleaning for technical and intumescent films

ISO 12944

80/20

Dry film thickness compliance rule: 80% of measurements ≥ nominal value, none < 80% of it

OTConst art. 33

19 to 21%

Minimum and maximum oxygen content by volume required in the air at workstations

Technical scope and intervention limits

The mechanical durability of a steel structure relies on the rigorous control of its surface treatments and passive fire protection. In the context of contracts subject to standards SIA 263 and ISO 12944, the steelwork contractor assumes the integrity of the load-bearing structure, its rolled sections, welded plate girders and bolted connection nodes. This section deals exclusively with corrosion protection barriers applied in the workshop or touched up on the construction site, as well as thermal insulation systems intended to maintain the load-bearing capacity of the framework during the evacuation time required by the VKF.

  • Included: preparation of black steel substrates by abrasive blast-cleaning, thermal spray metallisation and hot-dip galvanising.
  • Included: duplex systems, solvent-borne or water-borne liquid paints, shop primers and intumescent coatings for open and hollow sections.
  • Included: passive protection by sprayed mineral or paste coatings (fireproofing spray) and rigid retrofitted encasements on columns and beams.
  • Included: sealing of on-site connections, drainage of hollow sections and dielectric breaks against bimetallic coupling.
  • Excluded: lightweight facade metal joinery and cladding cassettes without structural function (falling under CFC 221).
  • Excluded: secondary metalwork, guardrails and non-load-bearing architectural metalwork (falling under CFC 274).
  • Excluded: interior decorative coatings without industrial protection function or framework reaction-to-fire rating (falling under CFC 272).

Applying technical coatings in the workshop or on the erection front requires strict alignment between confined space ventilation and the capture of emulsion mists. The employer takes the technical measures required by the Construction Works Ordinance to ensure air renewal and source capture of volatile solvents.

Technical progression method across chapters

Corrosion protection treatment and fire protection cannot be improvised at the final stage: they are determined right from the preparation of shop and erection drawings. Reviewing the chapters follows the logical chronological order of fabrication and erection, ensuring the absence of destructive non-conformities.

  1. Environmental characterisation and mechanical preparationIdentify the environmental exposure category according to standard ISO 12944 to fix the coating system, then define the blast-cleaning degree by grit blasting and the surface roughness profile required for mechanical keying.
  2. Geometric design and metal compatibilityIncorporate vent holes for molten zinc, eliminate standing water accumulation zones and introduce electrolysis isolators between steel, aluminium and stainless steel.
  3. Thermal application and thickness inspectionSize the dry film thickness according to the section factor of the profiles for fire, apply the statistical acceptance rule for paints, and evaluate alternatives using boards or sprayed mortars.
  4. Operation, maintenance and workshop safetyEstablish the periodic monitoring plan for the finished structure and organise spraying stations according to art. 33 OTConst to exhaust toxic fumes and prevent explosive atmospheres.

Quality tracking relies on the traceability of thermo-hygrometric conditions during application (dew point, substrate temperature) and on keeping thickness inspection records, which are essential for hand-over of the works according to standard SIA 118.

📘 Chapters in this section 10

Corrosion protection and fire resistance

Corrosivity category: read the environment to choose paint system

Select the exact coating and required durability by deciphering corrosivity categories C1 to CX without error.

Corrosion protection and fire resistance

Surface preparation: shot blasting, degree of care, and roughness achieved

Achieve preparation grade Sa 2 ½ and the anchor profile that guarantees adhesion without blistering.

Corrosion protection and fire resistance

Hot-dip galvanising: designing parts for the bath, vent holes and distortion

Avoid explosion and twisting of components during hot dipping by rigorously sizing vent holes.

Corrosion protection and fire resistance

Measuring dry film thickness: where, how many points, and which value to retain

Validate the acceptance of coats according to the 80/20 rule with dispute-free thickness calibration.

Corrosion protection and fire resistance

Galvanic corrosion: steel, stainless steel and aluminium in contact, and the required insulation

Eliminate destructive galvanic coupling between steel, aluminium and stainless steel sections using assembly isolators.

Corrosion protection and fire resistance

Intumescent paint: thickness by profile and fire resistance rating

Calculate the section factor of the framework to set the exact microns of intumescent paint.

Corrosion protection and fire resistance

Spray fireproofing or board encasement: alternatives to intumescent and their visual constraints

Decide between sprayed mineral coating and rigid encasement to secure concealed or exposed elements against fire.

Corrosion protection and fire resistance

Details that trap water: inverted channel sections, laps and low points without drainage

Eliminate rust traps in the workshop by modifying the layout of sections and gusset plates.

Corrosion protection and fire resistance

Maintenance of a steel structure: intervals, points to inspect and file to hand over

Structure the multi-year maintenance plan to preserve structural warranties and avoid heavy repairs.

Corrosion protection and fire resistance

Paint and Solvents: Ventilation, Respiratory Protection and Fire Risk

Organise the application booth to eliminate asphyxiation and explosion hazards related to volatile solvents.