🧱 CFC 215Erection and lifting of a steel structureChapter 4 of 10 in the section

Temporary then final bolting: how many bolts before unhooking the crane

This chapter details the assembly requirements during the erection of steel structures, from positioning the suspended component through to final tightening. You will learn how to determine the minimum number of bolts required before unhooking the crane slings, the geometrical adjustment methodology, and the essential checks before applying the final tightening torque in accordance with standard SN EN 1090.

Key takeaways

  • Install at least 33 % of the bolts per connection before unhooking the crane slings.
  • Engage at least two bolts per connection to guarantee stability and prevent tipping.
  • Snug-tighten with an impact wrench before releasing the crane hook.
  • Check the overall geometry of the section before performing final tightening in accordance with standard SN EN 1090.

Temporary assembly requirements and minimum number of bolts before slinging

During the erection of a structural steel member, the most critical phase lies in the transition between suspension from the crane and the mechanical autonomy of the component within the framework. Unhooking the crane hook must never take place before a sufficient number of fasteners ensures the transfer of self-weight forces, instantaneous wind, and construction site loads. Standard SN EN 1090 defines the execution rules for steel structures and imposes a strict methodology for temporary assembly.

For a column splice comprising 12 bolts, the site foreman must have at least 4 bolts installed and locked, distributed at the outer edges of the bolt group, before giving the order to release the crane. On a secondary beam connected with moment or shear connections via two welded angle cleats, installing two bolts (one in the upper part, one in the lower part) constitutes the minimum required to prevent any tipping or slip in shear.

  1. Presentation and driftingGuide the suspended component using tag lines. Insert at least two tapered drift pins into diagonal holes to align the plate holes with the supporting member.
  2. Installation of temporary boltsPlace the assembly bolts in the free holes manually or using an impact wrench. Fit the washers and nuts specified by the erection drawing.
  3. Snug tightening (pre-tightening)Tighten the temporary bolts until firm contact of the mating surfaces is achieved ('snug-tight' condition or approximately 10 to 20 % of the final torque). Then remove the drift pins to install the remaining bolts of this first stage.
  4. Approval to unhookThe site foreman visually checks that the minimum percentage of tightened bolts is present and gives the signal to the crane operator to slacken and unhook the slings.

Geometric survey and final tightening methodology for the framework

Once the component is stabilized and the crane is released for the next sequence, the structure enters the adjustment phase. Final tightening to torque or angle must never be performed immediately member by member, but by geometrically stabilized sub-assemblies. If the erector locks the connections of a bay permanently before adjusting the verticality and squareness of the entire grid, hyperstatic forces and cumulative tolerances will prevent the erection of adjacent elements.

Assembly phases for structural bolts
StagePercentage of boltsTightening levelCrane status
Initial slinging0 %None (guiding)Under tension
Temporary bolting33 % minimum (min. 2 per joint)Snug-tight (impact wrench / manual)Unhooking permitted
Connection completion100 %Fitted without final lockingReleased
Final tightening100 %According to SN EN 1090 (torque / angle)Released

Before ordering final tightening, the site manager or site foreman validates the topographical survey of the stability braced bay or the framework section. This check covers the plumbness of the columns, the levels of the beam tops, and the straightness of the alignments. Temporary or permanent bracings must be tensioned to fix the geometry.

  • Check the cleanliness of the contact surfaces (absence of loose mill scale, grease, or ice).
  • Replace temporary bolts that have been subjected to abnormal stress or impacts during alignment.
  • Ensure the correct installation direction of Preloaded (HR/HV) or Non-Preloaded (SB) bolting assemblies in accordance with the engineering office specifications.
  • Apply the tightening protocol in two passes (pre-tightening then final tightening with controlled torque or using the turn-of-nut method) according to standard SN EN 1090.
  • Mark each nut with a line of paint after validation of final tightening.

Criteria for crane unhooking and connection pre-tightening

During the erection of a steel structure, the critical moment lies in the decision to release the crane slings. Before any unhooking, the temporary assembly must provide sufficient mechanical strength to support the self-weight of the member, the weight of the erectors at work, as well as temporary climatic loads (wind). Standard SN EN 1090-2 strictly governs these transient phases by requiring temporary bolted connections to guarantee the overall stability of the frame or section being installed.

To avoid any risk of collapse or tipping of the component (in accordance with the safety requirements of art. 17 OTConst), erectors must install centering drift pins and pre-tightened erection bolts. Drift pins allow holes to be aligned perfectly without damaging the bolt threads, while temporary bolting ensures the transfer of shear loads and initial tensile forces.

Temporary bolting rules before releasing the crane hook
Connection typeMinimum driftingMin. temporary boltingTightening before unhooking
Column base on anchorNot applicable (anchor rods)100 % of rods engagedNuts run down + locknuts spanner-tightened
Beam-to-column moment connection (end plate)2 tapered drift pins30 % of holes (min. 2 bolts)Tightened to refusal (so-called 'spanner-tight' effort)
Splice connection (web + flanges)2 drift pins on the web25 % of holes per plateSnug-tight contact of mating surfaces
Purlins and cladding railsNot applicable50 % of bolts (min. 2 bolts)Full manual tightening

Geometrical survey and final tightening methodology

Once the component is unhooked and the bay has been made self-supporting, the erection team completes the bolting and proceeds with fine geometrical adjustment (plumbness of columns, elevation of rafters/beams, squareness of braced bays). No final tightening must be carried out before the plumb and level tolerances of the structure have been approved.

  1. Filling the remaining holesInstallation of all missing bolts and progressive replacement of centering drift pins with final bolts of the specified property class (8.8 or 10.9).
  2. Snug-tightening (Stage 1)Application of an initial torque (approximately 75 % of the final torque for preloaded bolting according to SN EN 1090-2) to the entire bolt group, starting from the centre of the group outwards toward the edges.
  3. Overall geometry checkChecking alignments using a total station or laser plumb line. Adjustment of shims under column base plates if necessary.
  4. Controlled final tightening (Stage 2)Application of the final torque or rotation angle specified in the specifications (torque method or combined method) for SB or HV/HR assemblies.

The erection foreman records the acceptance of connections in the site log. This step is a prerequisite for releasing the areas below and authorizing the installation of metal decking or composite facade elements. Responsibility for the compliant execution of load-bearing steel structures is subject to the provisions of art. 229 CP in the event of endangerment through non-compliance with the recognized rules of the trade.

Management of assembly non-conformities and remediation of faulty tightening

During the erection of a steel structure according to standard SN EN 1090, the transition from temporary bolting to final tightening may reveal geometrical or mechanical anomalies. The primary rule before unhooking the crane requires installing at least 30 % of the bolts per connection (with an absolute floor of 2 bolts per joint) snug-tightened. If the clearance holes do not align perfectly due to fabrication tolerances or deformation during hoisting, it is strictly forbidden to force bolts with a hammer or realign parts using drift pins while maintaining the component suspended from the crane for an extended period.

If a torque-controlled bolt (HR or HV preloaded assembly) is found to be defective or to have undergone overtightening during the final phase, the complete assembly (bolt, nut, and washers) must be discarded. Reusing a preloaded bolt that has already been partially or fully tightened is prohibited. The replacement procedure requires maintaining or installing temporary propping if the component has already been released from the crane, in order to guarantee the stability of the bay.

If the overall geometrical survey of a bay shows a deviation exceeding the tolerances permitted by standard SN EN 1090-2 before 100 % final tightening, the erection crew must loosen the pre-tightening of the temporary bolts across several adjacent nodes, rectify the offset using turnbuckles or adjusting jacks, and then re-bolt step by step before authorizing the release of the lifting equipment.

Frequently asked questions

Can the crane sling be released if only two bolts are installed on an eight-hole connection?

No, unless two bolts represent at least 30 % of the total number of holes in the connection and the erection engineer has validated the load capacity under self-weight and temporary wind. According to standard SN EN 1090, bolting must be brought up to the required percentage and snug-tightened before unhooking the slings.

How can a hole misalignment be corrected on the construction site?

Alignment must be carried out using twist drills or magnetic portable reamers to respect hole geometry without altering the steel. The use of a cutting torch is prohibited by standard SN EN 1090. If the misalignment exceeds standard tolerances, a non-conformance report must be submitted to the engineering office.

Is it permitted to reuse a preloaded bolt that was used for temporary bolting?

If the preloaded bolt (HR or HV type) has advanced beyond manual pre-tightening and has undergone initial tensioning, it can no longer be used for final tightening. Plastic deformation of the threads compromises the control of the preloading force specified by standard SN EN 1090.

Who approves the transition from temporary to final tightening on the construction site?

The erection foreman or site manager validates the plumb and geometry of the structure using measuring instruments. Once the geometrical survey conforms to the requirements of standards SN EN 1090 and SIA 263, the order to carry out final tightening to torque or angle is given to the team.

Texts and standards cited

  • SN EN 1090Execution of steel structures and aluminium structures: technical requirements for steel structures
  • SIA 263Steel construction: design and execution of steel structures
  • OTConst art. 17Protection against the collapse of construction elements or falling objects and materials