🧱 CFC 215Connections: bolting, welding and inspectionChapter 1 of 10 in the section

High-strength bolting: torque tightening, method and report

This chapter details execution requirements for preloaded connections in steel structures according to standard SN EN 1090. You will learn how to set and verify a calibrated torque wrench, adhere to the methodical tightening sequence to bring parts into full contact without warping, and record each step in a tightening report ensuring the compliance of the work.

Key takeaways

  • A non-preloaded high-strength bolt acts purely as an ordinary shear fastener.
  • The calibrated torque wrench ensures exact application of the torque specified by the civil engineer.
  • The tightening sequence must run from the centre of the joint towards the outer free edges.
  • The tightening report records batches, tooling, and final inspection values.

Apply preloading according to standard SN EN 1090 using calibrated tooling

In friction-grip joints or connections subjected to fatigue, the high-strength (HR) bolt derives its efficiency from the axial preload force developed in its shank. When this tension is lacking, the joint slips and the bolt acts in bearing like an ordinary standard-grade rod. Standard SN EN 1090 governs the execution of steel structures and imposes a strict correlation between under-head friction, thread pitch, and applied tightening torque. Interchanging components within the same bolt-nut-washer assembly is prohibited: elements must come from the same single manufacturing batch, delivered lubricated from the factory.

Preloaded bolt (HR / HV system)
Assembly consisting of a bolt, a nut, and hardened washers, designed to develop a minimum internal tension through controlled tightening, ensuring load transmission by friction between steel contact surfaces.

Achieving the required preload force demands a calibrated torque wrench checked to a strict schedule, generally annually or after any abnormal impact. Using an uncontrolled impact wrench for the final pass is prohibited by trade standards, as thermal energy dispersion and jolting completely distort the conversion between torque and tension. On the assembly construction site, the crew uses clear-break manual torque wrenches or automatic shut-off electromechanical wrenches, whose calibration certificate is filed in the technical works binder.

Preload fasteners must be tightened applying a standardised method: torque method, combined method, or HRC method. Tightening tools must be checked for accuracy and recalibrated at regular intervals.

SN EN 1090-2

Sequence tightening passes and document traceability in an inspection report

Full contact between metallic parts is an absolute prerequisite for preloading. If residual gaps remain between the assembled plates, the applied torque is spent deforming the steel instead of generating tension in the bolt shank. The crew achieves complete bedding of the plate pack using drift pins and fitting-up bolts before starting the standardised two-step cycle: an initial bedding pass at approximately 75% of the target torque, followed by the final pass at 100%.

  1. Bedding and mechanical clampingAlign holes using conical drift pins without ovalising them. Fit the HR bolts with their chamfered washers correctly oriented under the head and under the nut, then clamp the plate pack to eliminate any gap between mating surfaces.
  2. First tightening pass (75%)Apply the torque fraction specified by the chosen method, working strictly from the centre of the connection (stiffest area) towards the free edges, in order to drive out air and residual warping towards the outside.
  3. Final finishing pass (100%)Retighten all bolts in the same geometric sequence until the calibrated torque wrench clicks. Mark each nut with an indelible paint line to visually confirm completion of the cycle.

Compliance with trade standards requires avoiding any negligence likely to compromise the structural integrity of steel frames; deliberate or reckless breaches fall under art. 229 CP where endangerment occurs. In contractual and quality terms, a lack of traceability constitutes a major non-conformity during the acceptance of the work under standard SIA 118.

Minimum contents of the HR bolt tightening report
Mandatory sectionData to be recordedConformity criterion
Joint identificationDrawing mark, level, grid line, connection typeExact match with approved erection drawings
Fastener batchFactory batch number, 3.1 certificate, k-classBolts, nuts, and washers from the same manufacturer
Measuring toolsWrench type, serial number, date of last calibrationValid certificate less than 12 months old
Applied torqueTarget value in Nm, value measured during inspectionTolerance compliant with SN EN 1090 requirements
Site sign-offFitter name, signature of foreman or inspectorJoint sign-off before closing the joint

Torque tightening inspection and dynamometer calibration

On a structural steel or heavy facade construction site, an uncontrolled preloaded connection loses its friction-grip capability, dropping to an ordinary bearing-type fastener. Applying the specified torque according to standard SN EN 1090 requires faultless measuring equipment. Using a torque wrench with an expired calibration certificate directly exposes the structure to a lack of axial preloading in the shanks, compromising the non-slip performance of splice joints under working loads.

For the torque method, manual torque wrenches or powered torque wrenches must have a minimum accuracy of plus or minus 4% and be calibrated at least once a year or after any significant impact.

SN EN 1090-2

Site tooling requires rigorous documentary tracking. The foreman or lead erector systematically checks that the serial number stamped on the handle of the calibrated torque wrench matches the certificate in the site quality file. The mechanical drift of an unverified release mechanism can distort the target value by more than 15%, creating critical disparities within the same bolt group.

Tightening equipment and on-site inspection frequency
EquipmentPermissible toleranceInspection intervalRequired validation
Manual click-type torque wrench± 4 % of target valueAnnual or after impactAccredited laboratory certificate
Motorised torque wrench± 4 % of target valueWeekly on site test rigSkidmore-type load testing bench
Mechanical torque multiplier± 5 % of nominal ratioAnnual with its pilot wrenchSystem calibration certificate
Inspection wrench for torque-checking± 2 % (dedicated equipment)Before each acceptance campaignDated internal calibration sheet

Geometric preloading sequence and completion of the report

The distribution of preloading requires strict adherence to the joint tightening sequence to bring steel parts into full contact without restraining contact deformations. The erection crew systematically starts at the centre of gravity of the fastener group and works outwards towards the perimeter. Tightening outer fasteners first causes irreversible central bowing, preventing metal-to-metal contact of machined or shot-blasted surfaces.

  1. Phase 1: Bringing into contact and beddingTighten all bolts using an ordinary wrench or with an initial torque pass limited to approximately 75% of the specified final torque, moving from the centre toward the free edges to eliminate assembly play.
  2. Phase 2: Final torque applicationApply 100% of the nominal torque calculated according to standard SN EN 1090, strictly repeating the sequence from the centre outwards without sudden stops during the tightening sweep.
  3. Phase 3: Visual marking and identificationDraw a clear line with an indelible marker or centre punch across the nut, washer, and steel plate to confirm final tightening and detect any residual loosening.
  4. Phase 4: Drafting the tightening reportRecord applied values, fastener batch numbers, weather conditions, and calibrated wrench ID on the inspection form for joint sign-off with site management.

The tightening report is the centrepiece of the as-built documentation (DOE). Under art. 364 CO, the contractor is liable for the proper and faithful execution of their work, which includes documentary proof that critical connections are compliant. A joint lacking documentation via a signed report is deemed uninspected, which halts acceptance of the work for the steel frame and engages the contractor's liability regarding the civil engineer's design calculations.

On construction sites subject to major safety constraints, lead erectors also enforce accident prevention rules. In accordance with LAA, the employer must take all measures that experience has shown to be necessary, that the state of the art permits, and that are suited to the circumstances to preserve the safety of their crews. Maintaining wrenches in good mechanical condition and strictly banning homemade extension bars on torque tools directly serve this legal duty during high-leverage tightening.

Tightening non-conformities: diagnosis, rework and traceability

On a structural steel construction site governed by standard SN EN 1090, a high-strength bolt with a failed tightening protocol loses its preloading function. The classic mistake is attempting jerky retightening or applying uncalculated over-rotation. Exceeding the bolt's yield point causes immediate thread necking, leaving the connection unable to take up the slip or tensile loads required by the engineering drawings.

  • Calibration out of tolerance: if the certificate of the calibrated torque wrench exceeds the specified interval or if the device has been dropped, all connections tightened since the drift occurred must be re-examined.
  • Incomplete contact of parts: if play remains between splice plates after the first pass, the final torque will be consumed by mechanical deformation friction rather than actual preloading of the shank.
  • Loss of lubrication: a bolt-nut-washer assembly that has been degreased, corroded, or wetted on site drastically alters the tightening factor k, causing premature binding before reaching the nominal tension level.

Managing an erection incident requires immediate drafting of a non-conformity report filed in the erection records. Under CO, the contractor notifies the client of any circumstance compromising the proper execution of the work. Rework requires loosening all bolts at the joint, discarding compromised fasteners, checking that steel plates show no residual waviness, and restarting the geometric sequence from the intermediate torque pass.

Any remedial work requires a dedicated tightening report, signed by the lead erector and countersigned by site management, recording the replacement batch number, tooling used, and systematic verification of the joint tightening sequence.

Frequently asked questions

Can an impact wrench be used for final preloading?

No. An impact wrench or impact driver provides no accurate control over torque or angle. Its use is strictly restricted to preliminary bedding of parts. The final phase strictly requires a calibrated torque wrench or a regulated tool with controlled torque shut-off. Thermal build-up and unmeasured micro-impacts also risk damaging the surface treatment and the nut lubricant beneath the head.

What should be done if play remains between plates after tightening?

If a gap remains between steel framing plates after the first pass, the procedure must stop immediately. Forcing torque onto an isolated bolt to crush the steel completely distorts preloading. The joint must be relaxed, machined shims compliant with manufacturing tolerances inserted, and the joint tightening sequence methodically restarted from the centre outwards to guarantee full metal-to-metal contact.

What is the minimum information required on the tightening report?

The tightening report must document the exact joint location, working drawing mark, fastener property class, and manufacturer batch number. It states the preloading method used, part number and calibration date of the calibrated torque wrench, theoretical torque applied in the first and second passes, plus the date, name, and signature of the installer in charge of inspection.

Why is site lubrication of high-strength bolts prohibited?

High-strength bolting assemblies conforming to standard SN EN 1090 are delivered factory pre-lubricated to a defined k-class. Adding grease or any oil on site reduces thread friction unpredictably. For an identical tightening torque, the axial force generated in the shank increases considerably, creating a major risk of bolt failure due to excessive tension during installation.

Texts and standards cited

  • COmaterials and site: the contractor is liable for the sound quality of the materials they supply; if material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor must immediately notify the client, under penalty of bearing the consequences (para. 3).