Skip to content
Website
🧱 CFC 215Section 5 of 610 chapters

Composite facades: glass, metal and fixings: the execution standard

Intended for site managers, foremen and construction managers in steel construction, this section details the installation of composite facades combining steel framing, aluminium profiles and heavy glazing. From grid setting out to tightening three-dimensional fixings, from airtightness through to on-site water spray testing, it sets out the execution rules essential to guarantee the thermal and mechanical durability of the envelope in accordance with standards SIA 331 and SIA 263.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

OTConst art. 26

3 m

Fall height requiring facade scaffolding

OTConst art. 22

100 cm

Minimum height of the top rail of a guardrail

OTConst art. 22

15 cm

Minimum height of edge protection toeboards

OTConst art. 22

47 cm

Maximum spacing between rails of perimeter protection

Technical scope and limits of intervention

The modern composite facade relies on a load-bearing metal frame anchored directly to the main building structure. This field falls under the metal fabricator under CFC 215. Our scope encompasses workshop design, the manufacture of mullions and transoms, adjustable anchor brackets, as well as the installation of fixed or opening glazing integrated into this steel or aluminium grid. Managing manufacturing tolerances, free thermal expansion movement and continuous thermal insulation constitute the core of our trade on the construction site.

In regulatory terms, the metal framework must comply with standard SIA 263 for the design and stability of steel structures. All performances of the external envelope, notably driving rain tightness, air permeability, wind resistance and thermal transmittance, align strictly with the requirements of standard SIA 331 relating to windows and curtain walls.

Execution method and overview of the ten chapters

Erecting a metal curtain wall tolerates no improvisation. The chronological sequence of the chapters reflects the operational reality of a building envelope construction site, from topographic setting out to pressurised watertightness testing. Following this sequence ensures geometric alignment, prevents thermal glass breakage and eliminates damaging water infiltration.

  1. Setting out and three-dimensional compensationChapters [C5-01] and [C5-02] address grid layout and absorbing deviations in the structural work. The use of brackets adjustable in three axes compensates for the cumulative tolerances of cast-in-place concrete without placing the steel framework under forced stress.
  2. Thermal kinematics and glass settingChapters [C5-03] and [C5-04] address the calculation of steel-aluminium thermal expansion gaps and the methodical positioning of glazing blocks. Effective glazing rebate ventilation guarantees condensation drainage and preserves the edge seal of insulating glass units.
  3. Glazing safety and heavy handlingChapters [C5-05] and [C5-06] detail the criteria for choosing between toughened glass and laminated glass against impact or fall hazards, as well as lifting rules using a safety dual-circuit vacuum lifter.
  4. Watertightness, thermal performance and structural detailsChapters [C5-07] to [C5-10] finalise the envelope: structural bonding, on-site testing using a standardised spray nozzle, continuous thermal break preventing the dew point and rigid fixing of integrated balustrades transferring horizontal loads.

📘 Chapters in this section 10

Composite facades: glass, metal and fixings

Façade grid: layout, cumulative tolerances and compensation joint

Master cumulative dimensional tolerances to align vertical mullions perfectly over the full building height.

Composite facades: glass, metal and fixings

Adjustable fixings: compensating for structural work in all three directions

Adjust your anchor brackets along three axes to neutralise out-of-plumb concrete slab edges.

Composite facades: glass, metal and fixings

Expansion of a metal façade: actual amplitude and clearance to leave free

Calculate the actual gap at expansion joints to allow aluminium to expand without shearing load-bearing fasteners.

Composite facades: glass, metal and fixings

Installing Insulating Glazing: Setting Blocks, Rebate Drainage and Ventilation

Position setting blocks and location blocks to drain the glazing rebate perfectly without pinching the glazing.

Composite facades: glass, metal and fixings

Laminated or toughened glass: which provides safety by position

Choose between laminated and toughened glass to resist accidental impacts and ensure residual safety.

Composite facades: glass, metal and fixings

Lifting heavy glazing: vacuum lifter, air reserve and exclusion zone

Secure the handling of heavy glass units with a dual-circuit vacuum lifter and strict floor cordon controls.

Composite facades: glass, metal and fixings

Façade joints: structural silicone, compatibility and installation conditions

Apply weatherseals and structural silicone to prepared surfaces according to curing tolerances.

Composite facades: glass, metal and fixings

Façade hose testing: protocol, test areas and reading results

Verify facade watertightness through targeted pressurised water spray testing without risking floor-level leaks.

Composite facades: glass, metal and fixings

Thermal break in the profile: continuity, condensation and dew point

Ensure the continuity of thermal break strips to push the dew point clear of internal profiles.

Composite facades: glass, metal and fixings

Façade-integrated guardrail: horizontal load transfer and structural connection

Transfer statutory horizontal loads to the primary framework without distorting vertical glazing mullions.