Skip to content
Website
🧱 CFC 241Heat demand and sizing of the heat generationChapter 4 of 10 in the section

Hot water as a load: reheat capacity, priority and storage cylinder

This chapter gives you the method for adding the domestic hot water load to the thermal output of the boiler room. You will be able to calculate the reheat capacity of the cylinder according to standard SIA 384/1, size the storage volume to absorb peak demand, and set the domestic hot water priority without degrading comfort in the rooms.

Key takeaways

  • The peak draw-off calls for a strict trade-off between storage volume and generator output.
  • Standard SIA 384/1 governs the additional capacity allowed for thermal reheating of the domestic hot water storage.
  • Full domestic hot water priority interrupts space heating without measurable discomfort on distribution systems with high thermal inertia.
  • An undersized cylinder heat exchanger lengthens the reheat time and needlessly blocks the heating distribution.

Impact of draw-off peaks on sizing according to standard SIA 384/1

In a residential building, the demand for domestic hot water is not a constant flow but is concentrated in two very short daily peaks: in the morning between 6:30 and 8:30, then in the evening between 18:30 and 21:00. These episodes of heavy draw-off represent an instantaneous output far greater than the heat losses of the building envelope. Trying to cover this peak flow instantaneously would require tripling or quadrupling the size of the heat generator, leading to disastrous oversizing for continuous winter operation and for the seasonal efficiency.

The calculation of the power requirements for heating buildings includes the specific domestic hot water loads according to the mode of operation and the permissible time for thermal reheating of the storage volume.

norme SIA 384/1

The heating installer must therefore size the cylinder-and-generator pair by balancing the physical volume of the cylinder against the reheat capacity. The larger the storage volume, the more the output demanded from the generator to rebuild the thermal reserve can be spread over time. Standard SIA 384/1 sets the framework for determining whether a permanent additional capacity must be added to the nominal heating load of the building, or whether the storage capacity allows recharging to be deferred without changing the installed output.

Trade-off between reheat capacity and storage volume for the same peak demand
Selected configurationStorage volumeThermal reheat capacityImpact on the generator
Volume priority (large storage)High (covers 100% of the peak)Low (spread over 2 to 4 hours)No increase in boiler or heat pump output required
Standard residential balanceMedium (covers 60 to 70% of the peak)Medium (reheat in 60 to 90 minutes)Slight increase in output, or coverage by the reheat reserve
Output priority (compact footprint)Reduced (low autonomy)Very high (reheat in 20 to 30 minutes)Large increase in generator output, risk of short cycling in heating mode

Managing the domestic hot water charging priority and maintaining heating comfort

When the boiler room controller detects a drop in temperature in the lower or middle third of the domestic hot water cylinder, it switches the generation to charging mode. Conventional control applies absolute priority: the motorised diverter valve directs the entire flow to the cylinder heat exchanger, while the circulators of the heating circuits are temporarily stopped or their mixing valves are closed. During this phase, the building no longer receives its heat flow.

The thermal acceptability of this interruption depends entirely on the storage mass of the emission system. In a building fitted with underfloor heating in a cement or anhydrite screed, the thermal time constant often exceeds ten to twelve hours. An interruption of circulation of thirty to forty-five minutes goes completely unnoticed by the occupants, as the room temperature shows no measurable drop. Conversely, with light steel radiators or fan coil units whose response time is under fifteen minutes, a complete interruption of circulation causes an immediate cooling of the room air, noticeable by the end of the first quarter of an hour.

  1. Strict full priorityThe heating flow is cut off outright by stopping the circulator. All the kilowatts of the generator heat the domestic hot water. Recommended for underfloor heating with high thermal inertia.
  2. Sliding or partial priorityThe generator raises its flow temperature to the maximum available, and the heating mixing valve throttles the injection without cutting the flow of warm water to the radiators, in order to limit the temperature drop.
  3. Reheat safety time limitThe controller includes a time limit. If the cylinder has not reached its setpoint after sixty minutes, the priority is suspended so that heat is fed back into the building before the domestic hot water cycle resumes.

Calculating the reheat capacity and the trade-off on storage volume

In buildings fitted with heat pumps or low-temperature boilers, domestic hot water is the most severe thermal demand on the system. The load is not spread linearly over twenty-four hours: it is concentrated in two daily windows of about sixty to ninety minutes, in the morning and in the early evening. During these episodes, the storage volume undergoes a heavy draw-off of mixed water that abruptly lowers the temperature of the cylinder. For the heating installer, the technical equation consists of balancing the physical capacity of the tank against the thermal output available to rebuild the stock before the next demand.

The reheat capacity needed to heat the stored volume is determined directly from the elementary thermal formula applied to the heat transfer fluid. To raise a storage volume from its minimum draw-off temperature to its storage setpoint, the exchange capacity is the product of the mass of water, the specific heat capacity and the temperature difference, divided by the allotted reheat time. If the target reheat time is short, the instantaneous output required jumps and often exceeds the entire heating load of the building in severe cold.

Exchange capacity required to reheat a hot water cylinder (rise from 10 °C to 55 °C)
Usable storage volume (litres)Thermal energy required (kWh)Output for reheat in 60 min (kW)Output for reheat in 90 min (kW)Output for reheat in 120 min (kW)
30015,715,710,57,8
50026,226,217,513,1
80041,841,827,920,9
100052,352,334,926,2

The choice of volume also determines the internal exchange surface of the coil or the sizing of the external plate heat exchanger. A cylinder of small capacity coupled to a high-output heat source requires an oversized exchanger capable of dissipating the energy without causing a hydraulic short circuit or an untimely rise to high pressure on the generator. Conversely, a more generous storage volume allows the reheat load to be spread over two hours, reducing the demand output but increasing the floor space in the boiler room and the standby heat losses through the insulating jacket of the cylinder.

Priority strategy and hydraulic switching of the installation

The integration of the domestic hot water load on the generator almost always relies on the principle of absolute or sliding priority. With absolute priority, the control switches the entire heat transfer flow to the domestic hot water cylinder loop as soon as the immersion sensor detects a drop below the switch-on threshold. For the whole duration of this operation, the heating supply to the distribution networks is shut off. This mode of operation is particularly appropriate with underfloor heating, whose own screed inertia compensates, without perceptible discomfort, for an interruption of heat supply limited to one hour.

Hydraulic switching is carried out by two distinct technologies in the boiler room: the motorised three-way diverter valve or the double circulator with integrated non-return valves. The diverter valve has the advantage of avoiding flow interference but requires a travel time of thirty to sixty seconds, which must be synchronised with the output stage of the generator. Poor phasing causes a transient interruption of flow that trips the pressure safety switch or the safety thermostat of the heat generator.

  1. Detection of the setpoint being crossedThe immersion sensor located in the lower third of the cylinder records the temperature drop following the draw-off and sends the reheat command to the main controller.
  2. Switching of the hydraulic componentsThe control orders the motorised valve to switch to the domestic hot water exchanger, or starts the dedicated charging pump while locking the mixing valve of the heating circuit.
  3. Raising of the primary flow setpointThe generator leaves its weather-compensated heating curve to reach a primary water temperature at least 5 to 10 kelvins above the target setpoint temperature in the cylinder.
  4. End of cycle and gradual reintegrationThe upper sensor confirms that the domestic hot water setpoint has been reached, the generator output modulates down before hydraulically switching back to the heat emitters.

Standard SIA 384/1 governs how these consumptions are taken into account in order to avoid excessive oversizing of combustion generators or heat pumps. When the thermal output of the building is calculated as tightly as possible to limit premature wear of the compressors and maximise the seasonal coefficient of performance, fine management of the reheat becomes the guarantee of the viability of the installation. The installer must coordinate the settings with the operator so that the reheat cycles are set outside the morning peak hours of the heating network.

Resolving reheat malfunctions and thermal trade-offs

In a boiler room in service, a drift linked to the domestic hot water load shows up through two opposite symptoms: collapse of comfort in the rooms because the domestic hot water priority is held for too long, or a lack of hot water during peaks because the generator plateaus without regenerating the reserve. When absolute priority blocks the heating flows for more than 45 to 60 minutes in the depths of winter, the inertia of the building is no longer enough to mask the interruption, particularly on radiator systems with a low water content.

  1. Diagnosis of the primary charging flowMeasure the temperature difference between primary flow and return at the charging exchanger. An excessive difference indicates insufficient pump flow or a clogged charging circulator, reducing the heat transfer to the cylinder.
  2. Checking the diverter valve or the non-return valveCheck the tightness of the directional three-way valve. An internal leak towards the distribution circuit diverts part of the generator output, needlessly prolonging the hot water preparation cycle.
  3. Resetting the controller to sliding prioritySwitch the control from absolute priority to alternating priority if the heat-up time exceeds 45 minutes, in order to temporarily feed flow back to the heating groups.

If the internal exchanger or the external plate module proves unable to absorb the nominal output prescribed according to standard SIA 384/1 despite correct primary flows, the exchange surface must be re-assessed. Where the generator is sized as tightly as possible for heating with no output reserve, the installer adjusts the anticipated reheat windows to fall outside the hours of high space demand, thus avoiding the simultaneous accumulation of charging calls.

Frequently asked questions

How do you choose between absolute priority and sliding priority for charging?

Absolute priority suits individual heat pumps and boilers with underfloor heating, because the high inertia of the concrete compensates for the heating being stopped for 30 minutes. With radiators without inertia or a large number of dwellings, sliding or shared priority is necessary to avoid room temperature drops during prolonged morning cycles.

What consequence does an undersized hot water cylinder have on heat generation?

An insufficient storage volume forces the heat generator to supply a very high instantaneous reheat capacity during draw-off peaks. For a heat pump, this configuration requires a harmful oversizing that multiplies short cycles for the rest of the year, or forces the electric backup to switch on systematically, which degrades the overall seasonal energy efficiency of the boiler room.

Why does standard SIA 384/1 limit the strict addition of heating and domestic hot water loads?

Standard SIA 384/1 takes into account that the maximum demands are not perfectly simultaneous. Adding the nominal heating output and the maximum domestic hot water peak load would lead to heavy oversizing of the generators. Applying a diversity factor and using the storage capacity of the cylinder allow the demand to be smoothed while guaranteeing the required setpoint temperatures.

What should be checked if the cylinder reheat time exceeds the calculation forecasts?

First check the flow temperature of the primary circuit feeding the coil, which must be at least 10 to 15 kelvins above the target hot water setpoint. Then check that the charging circulator is working properly, that there is no air in the primary loop, and that the heating curve dedicated to the heater is correctly set.

Texts and standards cited

  • SIA 384/1Heating systems in buildings - Calculation of the nominal heat load

In the same section